6426 N HANNA AVE 91303
Certificate Information: 6426 N HANNA AVE 91303
- Application / Permit
- 23010-20000-00011
- Plan Check / Job No.
- B23VN00053
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW IRR. SHAPED 20'-1" x 41'-4" ONE-STORY DET. ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(B)
- Permit Issued
- Issued on 5/1/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/4/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/19/2023 | SEAN SHAHMIRI |
| Corrections Issued | 1/23/2023 | SEAN SHAHMIRI |
| Quality Review Completed | 1/24/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 1/26/2023 | APPLICANT |
| Plan Check Approved | 5/1/2023 | SEAN SHAHMIRI |
| Issued | 5/1/2023 | APPLICANT |
| CofO in Progress | 4/30/2024 | TROY SANDERS |
| CofO Issued | 8/1/2024 | JOHN JANSON |
| Permit Finaled | 8/1/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 1/26/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 2/8/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 2/8/2023 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 3/11/2023 | KURT CORRAL |
| ZI | Cleared | 3/13/2023 | DANG NGUYEN |
| Low Impact Development | Cleared | 4/10/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 4/18/2023 | MARKOS PEREZ-BRAN |
Contact Information
| Contractor | Tamam A Construction Inc; Lic. No.: 1003075-B | 41060 HIGH ST UNIT H FREMONT, CA 94538 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/10/2023 | Partial Approval | TROY SANDERS |
| Excavation/Setback/Form/Re-Bar | 7/19/2023 | Approved | PETER FOLLING |
| Footing/Foundation/Slab | 7/19/2023 | Approved | PETER FOLLING |
| BUILDING-Rough-Frame | 8/10/2023 | Partial Approval | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2023 | Partial Approval | TROY SANDERS |
| Rough-Elec/Plmb/HVAC | 8/10/2023 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 8/30/2023 | Corrections Issued | TROY SANDERS |
| Green Building Rough | 8/30/2023 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 8/30/2023 | Partial Approval | TROY SANDERS |
| Verify Sprinkler Sign Off | 8/30/2023 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 10/3/2023 | Approved | TROY SANDERS |
| Shower Pan | 10/3/2023 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 2/22/2024 | Approved | TROY SANDERS |
| Drywall Nailing | 2/22/2024 | Approved | TROY SANDERS |
| Final | 2/22/2024 | Corrections Issued | TROY SANDERS |
| Green Building Final | 2/22/2024 | Not Ready for Inspection | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 2/22/2024 | SGSOV Approved | TROY SANDERS |
| Service/Power Release | 2/22/2024 | Approved | TROY SANDERS |
| Smoke Detectors | 2/22/2024 | Approved | TROY SANDERS |
| Final | 4/30/2024 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 4/30/2024 | Approved | TROY SANDERS |
| Special/Order Compliance | 5/31/2024 | Corrections Issued | TROY SANDERS |