12342 W OSBORNE PL 91331

Certificate Information: 12342 W OSBORNE PL 91331

Application / Permit
23010-10003-02162
Plan Check / Job No.
B24LA28268
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Supplemental to permit 23010 - 10000 - 02162. Revision of the corridor shear walls to eliminate double sheated walls. In order to optimize construction sequencing and corridor wall assembly, we have used more linear corridor walls as shear walls. Foundation at the corridor walls has been adjusted accordingly.
Permit Issued
Issued on 11/12/2024
Issuing Office
Current Status
Issued on 11/12/2024

Permit Application Status History

Submitted 10/22/2024 APPLICANT
Assigned to Plan Check Engineer 10/24/2024 VU NGUYEN
Corrections Issued 10/29/2024 VU NGUYEN
Quality Review Completed 10/29/2024 EUGENE BARBEAU
Plan Check Approved 11/8/2024 VU NGUYEN
Issued 11/12/2024 APPLICANT

Permit Application Clearance Information

No Data Available.

Contact Information

Architect Zbikowski,, Jeffrey; Lic. No.: NA35389       ,
Contractor Donaldson John R Construction Inc; Lic. No.: 641405-B       ,
Engineer Benichou,, Ety; Lic. No.: S5263 888 S FIGUEROA ST 18TH FLOOR      LOS ANGELES, CA 90017
Engineer Pukkanasut,, Jirayus; Lic. No.: C73728 1424 ROLLING HILLS DR      FULLERTON, CA 92835

Inspector Information

JOHN KITCKO, (818) 374-1109 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 11/22/2024 Conditional Approval ANDREW DORSO
Deputy Reinf. Masonry 12/3/2024 Conditional Approval JEFFREY DURAN
Footing/Foundation/Slab 12/19/2024 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 1/22/2025 Conditional Approval ANDREW DORSO
Excavation/Setback/Form/Re-Bar 1/23/2025 Partial Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 1/23/2025 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 1/24/2025 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 2/26/2025 Conditional Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 2/27/2025 Partial Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 3/3/2025 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 3/4/2025 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 3/18/2025 Approved DANNY RODRIGUEZ
Footing/Foundation/Slab 3/18/2025 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 3/20/2025 Conditional Approval DANNY RODRIGUEZ
Deputy Wood Construction 4/11/2025 Conditional Approval DANNY RODRIGUEZ
Deputy Wood Construction 4/14/2025 Conditional Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 4/14/2025 Partial Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 5/2/2025 Partial Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 6/12/2025 Corrections Issued ANDREW DORSO
Floor/Roof Diaphrgm/Shear Wall 6/17/2025 Partial Approval GREGORY POMISH
Wood Frame 7/21/2025 Partial Approval GREGORY POMISH
Deputy Wood Construction 7/24/2025 Conditional Approval GREGORY POMISH
Deputy Drilled-In Anchors 9/15/2025 Conditional Approval ANDREW DORSO
Deputy Wood Construction 9/23/2025 Conditional Approval GREGORY POMISH
Deputy Wood Construction 11/7/2025 Conditional Approval BRIAN KELLY