10606 W CHALON ROAD 90077

Certificate Information: 10606 W CHALON ROAD 90077

Application / Permit
23010-10002-03062
Plan Check / Job No.
B25LA20556
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan - SUPPLEMENTAL TO 23010-10000-03062 TO ADD TWO STORY ADU (928 SF) PER 12.22 A33 C & E TO SFD W GARAGE AND REVISE SFD LAYOUT
Permit Issued
Issued on 7/17/2025
Issuing Office
Current Status
Issued on 7/17/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/20/2025 APPLICANT
Assigned to Plan Check Engineer 5/22/2025 STARR CHEN
Corrections Issued 5/27/2025 STARR CHEN
Quality Review Completed 5/28/2025 EUGENE BARBEAU
Applicant returned to address corrections 6/18/2025 STARR CHEN
Applicant returned to address corrections 6/25/2025 STARR CHEN
Plan Check Approved 7/11/2025 STARR CHEN
Issued 7/17/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 6/7/2025 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 6/9/2025 DARIN LAM
Hydrant and Access approval Cleared 6/10/2025 KURT CORRAL
Watercourse Cleared 6/11/2025 HISASHI KOBAYAKAWA
GPI Written Notices Cleared 6/18/2025 STARR CHEN
Grading Pre-Inspection Cleared 6/18/2025 STARR CHEN
Flood clearance Cleared 6/26/2025 SAMSON WONG

Contact Information

Contractor Turpin Levin Builders Inc; Lic. No.: 827748-B 15445 VENTURA BLVD #760      SHERMAN OAKS, CA 91403
Engineer De, Leon, Cynthia Aguilar; Lic. No.: C31604 347 ROBERTSON BLVD      BEVERLY HILLS, CA 90211
Engineer Hanna,, Emil Ramzy; Lic. No.: NA63602       ,
Engineer Tran,, Quang Tai; Lic. No.: C70929 355 N LANTANA ST 333      CAMARILLO, CA 93010
Geologist Barrett,, Mark A; Lic. No.: EG2088 14428 HAMLIN ST 200      VAN NUYS, CA 91401

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/21/2025 Not Ready for Inspection EVAN COOPER
BUILDING-Rough-Frame 7/28/2025 Corrections Issued CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 7/28/2025 Corrections Issued CHRISTOPHER WILSON
Footing/Foundation/Slab 8/18/2025 Not Ready for Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 8/20/2025 Not Ready for Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 8/22/2025 Corrections Issued CHRISTOPHER WILSON
Deputy Reinf. Concrete 8/25/2025 Conditional Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 8/26/2025 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 9/2/2025 Conditional Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 9/5/2025 No Access for Inspection CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 9/12/2025 Corrections Issued DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 9/16/2025 Partial Approval CHRISTOPHER WILSON
Deputy Wood Construction 9/25/2025 Conditional Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 9/29/2025 No Access for Inspection CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 10/1/2025 Corrections Issued DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 10/3/2025 Partial Approval SEAN HAUPT
HVAC-Rough 11/7/2025 Approved CARLOS MATAMOROS
Special/Order Compliance 11/7/2025 Corrections Issued CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 11/25/2025 Partial Approval DANIEL VERA
ELECTRICAL-Rough 12/5/2025 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 12/8/2025 No Access for Inspection CHRISTOPHER WILSON
FLOOD-Proofing Certificate 12/8/2025 Not Ready for Inspection CHRISTOPHER WILSON
Green Building Rough 12/8/2025 No Access for Inspection CHRISTOPHER WILSON
Verify Sprinkler Sign Off 12/8/2025 No Access for Inspection CHRISTOPHER WILSON
ELECTRICAL-Rough 12/9/2025 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 12/9/2025 Approved CHRISTOPHER WILSON
Verify Sprinkler Sign Off 12/9/2025 Approved CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 12/10/2025 Approved CHRISTOPHER WILSON
Interior/Exterior Lathing 12/10/2025 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 12/22/2025 Not Ready for Inspection CHRISTOPHER WILSON
Insulation 12/22/2025 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 12/23/2025 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 12/23/2025 Partial Approval CHRISTOPHER WILSON
Shower Pan 12/23/2025 Approved CHRISTOPHER WILSON
Insulation 12/31/2025 Not Ready for Inspection CHRISTOPHER WILSON
Drywall Nailing 1/7/2026 Partial Approval CHRISTOPHER WILSON