4327 S VERMONT AVE 90037
Certificate Information: 4327 S VERMONT AVE 90037
- Application / Permit
- 23010-10002-01459
- Plan Check / Job No.
- B26LA10599
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Supplemental to 23010-10000-01459 for early-start foundation only.
- Permit Issued
- Issued on 4/21/2026
- Issuing Office
- Current Status
- Issued on 4/21/2026
Permit Application Status History
| Submitted | 4/13/2026 | APPLICANT |
| Assigned to Plan Check Engineer | 4/14/2026 | MANUEL MONTUFAR |
| Plan Check Approved | 4/21/2026 | MANUEL MONTUFAR |
| Issued | 4/21/2026 | APPLICANT |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Edward, J Cronin; Lic. No.: C39728 | , |
| Contractor | Equis Construction Inc.; Lic. No.: 1119268-B | , |
| Engineer | Lee,, David Chong; Lic. No.: C70897 | 124 S GUADALUPE AVE, UNIT B REDONDO BEACH, CA 90277 |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 6/18/2026 | Conditional Approval | RAFAEL ESPINOZA |
| Excavation/Setback/Form/Re-Bar | 6/18/2026 | Partial Approval | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 6/18/2026 | Partial Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 6/22/2026 | Conditional Approval | JOEY BUCHANAN |
| Excavation/Setback/Form/Re-Bar | 6/22/2026 | Not Ready for Inspection | JOEY BUCHANAN |
| Footing/Foundation/Slab | 6/22/2026 | Corrections Issued | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 6/23/2026 | Approved | JOEY BUCHANAN |
| Footing/Foundation/Slab | 6/23/2026 | Partial Approval | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 6/24/2026 | Approved | JOEY BUCHANAN |
| Footing/Foundation/Slab | 6/29/2026 | Not Ready for Inspection | RAFAEL CORTES |
| Footing/Foundation/Slab | 6/30/2026 | Corrections Issued | RAFAEL CORTES |
| Footing/Foundation/Slab | 7/1/2026 | Partial Approval | JAMES POWERS |
| Excavation/Setback/Form/Re-Bar | 7/8/2026 | Partial Approval | JAMES POWERS |
| Footing/Foundation/Slab | 7/8/2026 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 7/13/2026 | Conditional Approval | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 7/13/2026 | Partial Inspection | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 7/14/2026 | Partial Approval | RAFAEL CORTES |