142 E 84TH ST 90003
Certificate Information: 142 E 84TH ST 90003
- Application / Permit
- 23010-10002-00972
- Plan Check / Job No.
- B24LA27377
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SUPPLEMENTAL TO 23010-10000-00972 TO CHANGE CONSTRUCTION TYPE FROM IIIA TO VA. APPROVED FIRE MODIFICATION IS ATTACHED ON PAGE A-3
- Permit Issued
- Issued on 11/25/2024
- Issuing Office
- Current Status
- Permit Finaled on 5/7/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/17/2024 | MANUEL MONTUFAR |
| Corrections Issued | 10/30/2024 | MANUEL MONTUFAR |
| Quality Review Completed | 10/31/2024 | EUGENE BARBEAU |
| Plan Check Approved | 11/22/2024 | MANUEL MONTUFAR |
| Issued | 11/25/2024 | APPLICANT |
| Permit Finaled | 5/7/2026 | RAFAEL CORTES |
Permit Application Clearance Information
| Fire Marshal Fire Life Safety | Cleared | 11/18/2024 | RONILO MULAWIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chatsky,, German; Lic. No.: C84153 | 3876 HUNTERS GROVE CT MOORPARK, CA 93021 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Drywall Nailing | 11/27/2024 | Not Ready for Inspection | RAFAEL CORTES |
| Floor/Roof Diaphrgm/Shear Wall | 11/27/2024 | Approved | RAFAEL CORTES |
| Wood Frame | 11/27/2024 | Partial Approval | RAFAEL CORTES |
| Insulation | 12/3/2024 | Approved | DARRYL ARNOLD |
| Interior/Exterior Lathing | 12/3/2024 | Approved | DARRYL ARNOLD |
| Drywall Nailing | 12/10/2024 | Partial Approval | ALFREDO LOPEZ |
| Interior/Exterior Lathing | 12/10/2024 | Approved | ALFREDO LOPEZ |
| Drywall Nailing | 12/12/2024 | Partial Approval | RAFAEL ESPINOZA |
| Drywall Nailing | 12/18/2024 | Partial Approval | RAFAEL ESPINOZA |
| Light Gage Steel Frame | 12/18/2024 | Partial Approval | RAFAEL ESPINOZA |
| Special/Order Compliance | 6/20/2025 | Partial Approval | RAFAEL ESPINOZA |
| Final | 9/18/2025 | Not Ready for Inspection | JOEY BUCHANAN |
| Wood Frame | 9/18/2025 | Not Ready for Inspection | JOEY BUCHANAN |
| Final | 11/26/2025 | Not Ready for Inspection | JOEY BUCHANAN |
| Wood Frame | 11/26/2025 | Approved | JOEY BUCHANAN |
| Final | 12/10/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Final | 2/17/2026 | Not Ready for Inspection | RAFAEL CORTES |
| Final | 3/16/2026 | Not Ready for Inspection | RAFAEL CORTES |
| Final | 4/29/2026 | Not Ready for Inspection | RAFAEL CORTES |
| Final | 5/7/2026 | Permit Finaled | RAFAEL CORTES |