15025 W HESBY ST 91403

Certificate Information: 15025 W HESBY ST 91403

Application / Permit
23010-10001-05216
Plan Check / Job No.
B24LA09627
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
SUPPLEMENTAL PERMIT TO 23010-10000-05216 TO REVISE ADU PLANS AND SCOPE OF WORK TO "NEW DETACHED ADU PER STATE LAW, ALL WORK PER WFPP"
Permit Issued
Issued on 5/31/2024
Issuing Office
Current Status
Issued on 5/31/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/21/2024 APPLICANT
Assigned to Plan Check Engineer 5/23/2024 MINA HABILI
Corrections Issued 5/24/2024 MINA HABILI
Building Plans Picked Up 5/29/2024 APPLICANT
Plan Check Approved 5/31/2024 FERNANDO FLORES
Issued 5/31/2024 APPLICANT
Permit Finaled-Status Void 10/9/2025 JACK KARGODORIAN
Re-Activate Permit 10/9/2025 JACK KARGODORIAN

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/28/2024 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 5/28/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 5/28/2024 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/4/2024 Partial Approval JACK KARGODORIAN
Underground Mechanical 6/4/2024 Partial Approval JACK KARGODORIAN
Pre-Inspection 6/7/2024 Partial Approval JACK KARGODORIAN
Underground Mechanical 7/18/2025 Not Ready for Inspection JACK KARGODORIAN
PLUMBING-Rough 7/23/2025 Partial Approval MICHEL ABAJAN
Excavation/Setback/Form/Re-Bar 8/4/2025 Corrections Issued MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 8/8/2025 Corrections Issued JACK KARGODORIAN
Excavation/Setback/Form/Re-Bar 8/13/2025 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 8/26/2025 Not Ready for Inspection WILLIAM WREN
ELECTRICAL-Rough 8/26/2025 Not Ready for Inspection WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 8/26/2025 Approved WILLIAM WREN
Green Building Rough 8/26/2025 Not Ready for Inspection WILLIAM WREN
Verify Sprinkler Sign Off 8/26/2025 Approved WILLIAM WREN
BUILDING-Rough-Frame 10/9/2025 Corrections Issued JACK KARGODORIAN
ELECTRICAL-Rough 10/9/2025 Approved JACK KARGODORIAN
Green Building Rough 10/9/2025 Approved JACK KARGODORIAN
HVAC-Rough 10/9/2025 Approved JACK KARGODORIAN
PLUMBING-Rough 10/9/2025 Approved JACK KARGODORIAN
Insulation 10/30/2025 Approved JACK KARGODORIAN
Interior/Exterior Lathing 10/30/2025 Partial Approval JACK KARGODORIAN
Drywall Nailing 11/14/2025 Approved JACK KARGODORIAN
Interior/Exterior Lathing 1/7/2026 Approved JACK KARGODORIAN
Shower Pan 1/7/2026 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 6/3/2026 Approved MISAEL ESPARZA
ELECTRICAL-Final 6/3/2026 Corrections Issued MISAEL ESPARZA
Final 6/3/2026 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 6/3/2026 Approved MISAEL ESPARZA
Green Building Final 6/3/2026 Not Ready for Inspection MISAEL ESPARZA
HVAC-Final 6/3/2026 Corrections Issued MISAEL ESPARZA
PLUMBING-Final 6/3/2026 Corrections Issued MISAEL ESPARZA
Service/Power Release 6/3/2026 Not Required MISAEL ESPARZA