1447 W 90TH PL 90047

Certificate Information: 1447 W 90TH PL 90047

Application / Permit
23010-10001-02467
Plan Check / Job No.
B24LA10121
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
SUPPLEMENTAL TO 23010-10000-02467 TO REVISE SCOPE OF WORK TO NEW 1 STORY DETACHED ADU PER ENGINEER DESIGN AND STRUCTURAL INVENTORY (1,200 SF max per Ordinance, LAMC 12.22 A.33 (c)-(d))
Permit Issued
Issued on 7/2/2024
Issuing Office
San Pedro
Current Status
Permit Finaled on 2/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/28/2024 APPLICANT
Assigned to Plan Check Engineer 5/30/2024 AUNG SOE
Corrections Issued 6/3/2024 AUNG SOE
Building Plans Picked Up 6/5/2024 APPLICANT
Applicant returned to address corrections 6/13/2024 JOSE VELAZQUEZ
Applicant returned to address corrections 6/18/2024 NEHEMIAS RAMOS
Plan Check Approved 6/25/2024 YAQUB MIRZA
Issued 7/2/2024 APPLICANT
Permit Finaled 2/4/2025 MICHAEL LEWIS

Permit Application Clearance Information

Construction near power lines Cleared 6/18/2024 EDGAR PASCUA
Eng Process Fee Ord 176,300 Cleared 6/24/2024 WALLIE JONG
Roof/Waste drainage to street Cleared 6/24/2024 WALLIE JONG

Contact Information

Contractor J W Construction Company; Lic. No.: 362075-B 956 WEST UPLAND AVE      SAN PEDRO, CA 90731
Contractor Owner-Builder       ,
Engineer Cooke,, Conway Cecil; Lic. No.: NA5524       ,

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 9/4/2024 Not Ready for Inspection AMIR NAZARIAN
ELECTRICAL-Rough 9/4/2024 Corrections Issued AMIR NAZARIAN
Floor/Roof Diaphrgm/Shear Wall 9/4/2024 Partial Approval AMIR NAZARIAN
Green Building Rough 9/4/2024 Not Ready for Inspection AMIR NAZARIAN
HVAC-Rough 9/4/2024 Corrections Issued AMIR NAZARIAN
PLUMBING-Rough 9/4/2024 Corrections Issued AMIR NAZARIAN
Verify Sprinkler Sign Off 9/4/2024 Not Ready for Inspection AMIR NAZARIAN
BUILDING-Rough-Frame 9/10/2024 Corrections Issued AMIR NAZARIAN
ELECTRICAL-Rough 9/10/2024 Conditional Approval AMIR NAZARIAN
Floor/Roof Diaphrgm/Shear Wall 9/10/2024 Corrections Issued AMIR NAZARIAN
Green Building Rough 9/10/2024 Not Ready for Inspection AMIR NAZARIAN
PLUMBING-Rough 9/10/2024 Approved AMIR NAZARIAN
Verify Sprinkler Sign Off 9/10/2024 Corrections Issued AMIR NAZARIAN
Deputy Drilled-In Anchors 9/16/2024 Conditional Approval ALEX COLIN
Deputy Wood Construction 9/16/2024 Conditional Approval ALEX COLIN
BUILDING-Rough-Frame 10/11/2024 Not Ready for Inspection AMIR NAZARIAN
ELECTRICAL-Rough 10/11/2024 Conditional Approval AMIR NAZARIAN
Floor/Roof Diaphrgm/Shear Wall 10/11/2024 Approved AMIR NAZARIAN
Green Building Rough 10/11/2024 Not Ready for Inspection AMIR NAZARIAN
HVAC-Rough 10/11/2024 Conditional Approval AMIR NAZARIAN
PLUMBING-Rough 10/11/2024 Approved AMIR NAZARIAN
Verify Sprinkler Sign Off 10/11/2024 Corrections Issued AMIR NAZARIAN
Drywall Nailing 11/15/2024 Approved ALEX COLIN
Insulation 11/15/2024 Approved ALEX COLIN
Interior/Exterior Lathing 11/15/2024 Approved ALEX COLIN
BUILDING-Rough-Frame 1/27/2025 Approved MICHAEL LEWIS
Final 1/27/2025 Partial Inspection MICHAEL LEWIS
Footing/Foundation/Slab 1/27/2025 Approved MICHAEL LEWIS
Green Building Final 1/27/2025 Approved MICHAEL LEWIS
Green Building Rough 1/27/2025 Approved MICHAEL LEWIS
Service/Power Release 1/27/2025 Not Ready for Inspection MICHAEL LEWIS
Smoke Detectors 1/27/2025 Approved MICHAEL LEWIS
Verify Sprinkler Sign Off 1/27/2025 Approved MICHAEL LEWIS
ELECTRICAL-Final 2/4/2025 Approved MICHAEL LEWIS
Final 2/4/2025 Permit Finaled MICHAEL LEWIS
Service/Power Release 2/4/2025 Approved MICHAEL LEWIS