6671 1/2 W COLGATE AVE 90048
Certificate Information: 6671 1/2 W COLGATE AVE 90048
- Application / Permit
- 23010-10001-00069
- Plan Check / Job No.
- B24LA15043
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *ATTN MAHNAZ NOURHASHEMI, CHAD DOI EMAILED 7/24/24 Eplan SUPPLEMENTAL TO 23010-10000-00069 TO CHANGE REC ROOM (POOL HOUSE) TO ADU PER CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g) -BLDG SPRINKLERED THRU-OUT
- Permit Issued
- Issued on 8/29/2024
- Issuing Office
- Current Status
- Permit Finaled on 5/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/25/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/25/2024 | MAHNAZ NOURHASHEMI |
| Assigned to Zoning Architect | 7/30/2024 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 8/7/2024 | MAHNAZ NOURHASHEMI |
| Applicant returned to address corrections | 8/8/2024 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 8/23/2024 | MAHNAZ NOURHASHEMI |
| Issued | 8/29/2024 | APPLICANT |
| Permit Finaled | 3/13/2025 | EVAN COOPER |
| Permit Finaled | 5/8/2025 | EVAN COOPER |
Permit Application Clearance Information
| Address approval | Cleared | 8/10/2024 | CELINA MORENO |
| Sewer availability | Cleared | 8/10/2024 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 8/13/2024 | CELINA MORENO |
| Zoning Plan Check | Cleared | 8/14/2024 | Mahnaz Nourhashemi |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Alexander,, Andy; Lic. No.: NA84086 | , |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/3/2024 | Not Ready for Inspection | KIRK SANDERS |
| Special/Order Compliance | 9/3/2024 | Not Ready for Inspection | KIRK SANDERS |
| Wood Frame | 9/3/2024 | Corrections Issued | KIRK SANDERS |
| Special/Order Compliance | 11/14/2024 | Partial Approval | MEL KHACHATOURIAN |
| Wood Frame | 11/14/2024 | Partial Approval | MEL KHACHATOURIAN |
| Insulation | 11/25/2024 | Approved | MEL KHACHATOURIAN |
| Final | 3/13/2025 | Permit Finaled | EVAN COOPER |
| METHANE-Final | 3/13/2025 | Approved | EVAN COOPER |
| Smoke Detectors | 3/13/2025 | Approved | EVAN COOPER |
| Special/Order Compliance | 3/13/2025 | Corrections Issued | EVAN COOPER |
| Final | 5/8/2025 | Permit Finaled | EVAN COOPER |