202-204 W 90TH ST 90003

Certificate Information: 202-204 W 90TH ST 90003

Application / Permit
23010-10000-05311
Plan Check / Job No.
B23LA24551
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
eplan NEW 2-STORY DUPLEX WITH ATTACHED GARAGE
Permit Issued
Issued on 4/17/2024
Issuing Office
Current Status
CofO Issued on 10/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/2/2024 APPLICANT
Assigned to Plan Check Engineer 1/4/2024 DANIEL YIP
Corrections Issued 1/6/2024 DANIEL YIP
Quality Review Completed 1/8/2024 PRANITA SHAH
Plan Check Approved 4/2/2024 DANIEL YIP
Issued 4/17/2024 APPLICANT
CofO in Progress 10/1/2024 CHARLES BOGHOSKHAN
Permit Finaled 10/1/2024 RUBEN SALAS
CofO Issued 10/1/2024 RUBEN SALAS
Permit Finaled 10/1/2024 RUBEN SALAS

Permit Application Clearance Information

Low Impact Development (LID) Cleared 1/31/2024 PATRICK LOPEZ
Address approval Cleared 2/2/2024 JUSTIN BICOL
Roof/Waste drainage to street Cleared 2/2/2024 JUSTIN BICOL
Permit Cleared 2/6/2024 JUSTIN BICOL
Eng Process Fee Ord 176,300 Cleared 2/16/2024 JUSTIN BICOL
Sewer availability Cleared 2/16/2024 JUSTIN BICOL
Hydrant and Access approval Cleared 2/17/2024 JOHN CONNEALLY
Trees in Parkway Cleared 3/21/2024 ADALBERTO VERA
SB8 RUD Cleared 3/26/2024 BLAKE BOULIGNY

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: NA81695       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/1/2024 Approved MICHAEL LEWIS
Footing/Foundation/Slab 5/1/2024 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 5/16/2024 Partial Approval MICHAEL LEWIS
Underground Mechanical 5/16/2024 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 5/17/2024 Partial Approval MICHAEL LEWIS
Insulation 5/17/2024 Partial Approval MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 6/6/2024 Partial Approval MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 6/21/2024 Approved MICHAEL LEWIS
HVAC-Rough 7/10/2024 Approved MICHAEL LEWIS
PLUMBING-Rough 7/10/2024 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 7/11/2024 Approved MICHAEL LEWIS
ELECTRICAL-Rough 7/11/2024 Approved MICHAEL LEWIS
Green Building Rough 7/11/2024 Approved MICHAEL LEWIS
Verify Sprinkler Sign Off 7/11/2024 Approved MICHAEL LEWIS
Insulation 7/12/2024 Approved MICHAEL LEWIS
Drywall Nailing 7/26/2024 Approved ALEX COLIN
Interior/Exterior Lathing 7/26/2024 Partial Approval ALEX COLIN
ELECTRICAL-Final 9/11/2024 Corrections Issued CRAIG DAVIS
HVAC-Final 9/19/2024 Approved MICHAEL LEWIS
PLUMBING-Final 9/19/2024 Approved MICHAEL LEWIS
ELECTRICAL-Final 9/20/2024 Partial Approval MICHAEL LEWIS
Final 9/20/2024 Partial Inspection MICHAEL LEWIS
Green Building Final 9/20/2024 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 9/20/2024 SGSOV Not Required MICHAEL LEWIS
Service/Power Release 9/20/2024 Approved MICHAEL LEWIS
Smoke Detectors 9/20/2024 Approved MICHAEL LEWIS
ELECTRICAL-Final 9/27/2024 Approved MICHAEL LEWIS
Final 9/27/2024 OK to Issue CofO MICHAEL LEWIS
Service/Power Release 9/27/2024 Approved MICHAEL LEWIS