202-204 W 90TH ST 90003
Certificate Information: 202-204 W 90TH ST 90003
- Application / Permit
- 23010-10000-05311
- Plan Check / Job No.
- B23LA24551
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- eplan NEW 2-STORY DUPLEX WITH ATTACHED GARAGE
- Permit Issued
- Issued on 4/17/2024
- Issuing Office
- Current Status
- CofO Issued on 10/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/2/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/4/2024 | DANIEL YIP |
| Corrections Issued | 1/6/2024 | DANIEL YIP |
| Quality Review Completed | 1/8/2024 | PRANITA SHAH |
| Plan Check Approved | 4/2/2024 | DANIEL YIP |
| Issued | 4/17/2024 | APPLICANT |
| CofO in Progress | 10/1/2024 | CHARLES BOGHOSKHAN |
| Permit Finaled | 10/1/2024 | RUBEN SALAS |
| CofO Issued | 10/1/2024 | RUBEN SALAS |
| Permit Finaled | 10/1/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 1/31/2024 | PATRICK LOPEZ |
| Address approval | Cleared | 2/2/2024 | JUSTIN BICOL |
| Roof/Waste drainage to street | Cleared | 2/2/2024 | JUSTIN BICOL |
| Permit | Cleared | 2/6/2024 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 2/16/2024 | JUSTIN BICOL |
| Sewer availability | Cleared | 2/16/2024 | JUSTIN BICOL |
| Hydrant and Access approval | Cleared | 2/17/2024 | JOHN CONNEALLY |
| Trees in Parkway | Cleared | 3/21/2024 | ADALBERTO VERA |
| SB8 RUD | Cleared | 3/26/2024 | BLAKE BOULIGNY |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: NA81695 | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/1/2024 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 5/1/2024 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2024 | Partial Approval | MICHAEL LEWIS |
| Underground Mechanical | 5/16/2024 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 5/17/2024 | Partial Approval | MICHAEL LEWIS |
| Insulation | 5/17/2024 | Partial Approval | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 6/6/2024 | Partial Approval | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2024 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 7/10/2024 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 7/10/2024 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 7/11/2024 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 7/11/2024 | Approved | MICHAEL LEWIS |
| Green Building Rough | 7/11/2024 | Approved | MICHAEL LEWIS |
| Verify Sprinkler Sign Off | 7/11/2024 | Approved | MICHAEL LEWIS |
| Insulation | 7/12/2024 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 7/26/2024 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 7/26/2024 | Partial Approval | ALEX COLIN |
| ELECTRICAL-Final | 9/11/2024 | Corrections Issued | CRAIG DAVIS |
| HVAC-Final | 9/19/2024 | Approved | MICHAEL LEWIS |
| PLUMBING-Final | 9/19/2024 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Final | 9/20/2024 | Partial Approval | MICHAEL LEWIS |
| Final | 9/20/2024 | Partial Inspection | MICHAEL LEWIS |
| Green Building Final | 9/20/2024 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 9/20/2024 | SGSOV Not Required | MICHAEL LEWIS |
| Service/Power Release | 9/20/2024 | Approved | MICHAEL LEWIS |
| Smoke Detectors | 9/20/2024 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Final | 9/27/2024 | Approved | MICHAEL LEWIS |
| Final | 9/27/2024 | OK to Issue CofO | MICHAEL LEWIS |
| Service/Power Release | 9/27/2024 | Approved | MICHAEL LEWIS |