1911 S FEDERAL AVE 90025

Certificate Information: 1911 S FEDERAL AVE 90025

Application / Permit
23010-10000-05303
Plan Check / Job No.
B23LA24034
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: SINGLE FAMILY RESIDENCES WITH ATTACHED GARAGES (REAR)
Permit Issued
Issued on 1/22/2025
Issuing Office
Current Status
Issued on 1/22/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/21/2023 APPLICANT
Assigned to Plan Check Engineer 12/28/2023 SUNMIN LEE
Corrections Issued 12/30/2023 SUNMIN LEE
Quality Review Completed 1/4/2024 GARO TELMI
Applicant returned to address corrections 6/25/2024 SUNMIN LEE
Applicant returned to address corrections 10/10/2024 SUNMIN LEE
Plan Check Approved 11/12/2024 SUNMIN LEE
Plan Check Approved 12/3/2024 SUNMIN LEE
Issued 1/22/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 3/6/2024 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 3/7/2024 DINAH GARIN
Sewer availability Cleared 3/7/2024 DINAH GARIN
Hydrant and Access approval Cleared 4/26/2024 MATTHEW CRAIG
SB8 RUD Cleared 4/26/2024 KEVIN SCHULTZ
Low Impact Development (LID) Cleared 5/20/2024 LUIS LUVANO
Roof/Waste drainage to street Cleared 5/30/2024 DINAH GARIN
Frnt yard landscape/Water mgmt Cleared 5/31/2024 DORIAN AGUILAR
ZI Cleared 7/3/2024 KYLE WINSTON
Specific Plan Cleared 9/30/2024 RICHARD WOO
Miscellaneous Cleared 10/8/2024 MAYELA VILLA

Contact Information

Contractor Jburton Inc; Lic. No.: 981184-B       ,
Engineer Berkoz,, Ertunga; Lic. No.: S2504 4665 ELLENITA AVE      TARZANA, CA 91356
Engineer Tabirara,, Vernon Nicolas; Lic. No.: C75492 17520 DAPHNE AVE      TORRANCE, CA 90504
Engineer Zhang,, Quguang; Lic. No.: L8968 9080 TELSTAR AVE 303      EL MONTE, CA 91731
Landscape Architect Morrison,, Jeremi Steven; Lic. No.: LA5515 9215 NE 103RD STREET      VANCOUVER, WA 98662

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 6/5/2025 Corrections Issued KIRK SANDERS
Footing/Foundation/Slab 6/5/2025 Partial Approval KIRK SANDERS
Deputy Reinf. Concrete 6/9/2025 Conditional Approval KIRK SANDERS
Underground Mechanical 6/16/2025 Partial Approval KIRK SANDERS
Deputy Steel/Welding 7/10/2025 Conditional Approval KIRK SANDERS
Deputy Other (see comments) 7/14/2025 Conditional Approval KIRK SANDERS
Deputy Steel/Welding 7/18/2025 Conditional Approval KIRK SANDERS
Footing/Foundation/Slab 7/22/2025 Conditional Approval ARAM AVEDISIAN
Footing/Foundation/Slab 8/4/2025 No Access for Inspection KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 8/5/2025 Approved TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 9/8/2025 Corrections Issued ARAM AVEDISIAN
Deputy Wood Construction 9/9/2025 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 9/9/2025 Partial Approval ARAM AVEDISIAN
Structural Steel Frame 9/9/2025 Conditional Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 9/29/2025 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 11/5/2025 Approved MICHAEL ALLEN
PLUMBING-Rough 12/17/2025 Approved MICHAEL ALLEN
ELECTRICAL-Rough 12/18/2025 Approved MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 12/18/2025 Conditional Approval MICHAEL ALLEN
BUILDING-Rough-Frame 1/28/2026 Conditional Approval MICHAEL ALLEN
HVAC-Rough 1/28/2026 Approved MICHAEL ALLEN
Interior/Exterior Lathing 2/5/2026 Not Ready for Inspection MICHAEL ALLEN
BUILDING-Rough-Frame 2/12/2026 Approved ASHLEY THOMPSON
Green Building Rough 2/12/2026 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 2/12/2026 Partial Approval ASHLEY THOMPSON
Verify Sprinkler Sign Off 2/12/2026 Approved ASHLEY THOMPSON
Insulation 2/18/2026 Approved MICHAEL ALLEN
Drywall Nailing 2/25/2026 Approved ANTHONY EGSON
Interior/Exterior Lathing 4/8/2026 Approved WILBER ROSALES
Shower Pan 4/8/2026 Approved WILBER ROSALES
Deputy Drilled-In Anchors 4/16/2026 Conditional Approval ANDREW NAVE