3031 E ASBURY ST 90065
Certificate Information: 3031 E ASBURY ST 90065
- Application / Permit
- 23010-10000-05218
- Plan Check / Job No.
- B23LA24350
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- **ePlan** New dettached Accessory Dwelling Unit at rear of the lot per CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 4/5/2024
- Issuing Office
- Current Status
- CofO Issued on 3/2/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/26/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/29/2023 | EDWIN ESPIN |
| Corrections Issued | 1/1/2024 | EDWIN ESPIN |
| Applicant returned to address corrections | 1/27/2024 | EDWIN ESPIN |
| Plan Check Approved | 2/27/2024 | EDWIN ESPIN |
| Issued | 4/5/2024 | APPLICANT |
| CofO in Progress | 2/26/2025 | ALIZAH MAYAGOITIA |
| Permit Finaled | 3/2/2025 | DEROLD HAUFF |
| Permit Finaled | 3/2/2025 | DEROLD HAUFF |
| CofO Issued | 3/2/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 1/1/2024 | EDWIN ESPIN |
| Address approval | Cleared | 1/4/2024 | AMBER CAMPBELL |
| Roof/Waste drainage to street | Cleared | 1/4/2024 | AMBER CAMPBELL |
| Eng Process Fee Ord 176,300 | Cleared | 1/5/2024 | AMBER CAMPBELL |
| Sewer availability | Cleared | 1/5/2024 | AMBER CAMPBELL |
| Supp. Use District POD/CDO/TDO | Cleared | 1/25/2024 | ANDREA MAGANA-WITHERS |
| ZI | Cleared | 1/25/2024 | ANDREA MAGANA-WITHERS |
Contact Information
| Contractor | J Z J B Cnst Inv; Lic. No.: 1013600-B | , |
| Engineer | Builoff,, Sergei; Lic. No.: L8099 | 4004 SCHUYLKILL DR CALABASAS, CA 91302 |
| Engineer | Ramos,, Victor; Lic. No.: C86568 | 4823 ALMAGUER AVE GUADALUPE, CA 93434 |
| Engineer | Ramos,, Victor; Lic. No.: NA86568 | , |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/21/2024 | Partial Approval | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 6/6/2024 | Approved | RICHARD DOCKUS |
| PLUMBING-Rough | 7/12/2024 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Rough | 8/1/2024 | Approved | OSVALDO PARAMO |
| HVAC-Rough | 8/1/2024 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 8/16/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 8/16/2024 | Partial Approval | OSVALDO PARAMO |
| Green Building Rough | 8/16/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 8/16/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Deputy Wood Construction | 8/19/2024 | Conditional Approval | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 9/6/2024 | Approved | ALIZAH MAYAGOITIA |
| Green Building Rough | 9/6/2024 | Approved | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 9/6/2024 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 9/9/2024 | Partial Approval | OSVALDO PARAMO |
| Insulation | 9/19/2024 | Approved | OSVALDO PARAMO |
| Shower Pan | 9/24/2024 | Approved | LUIS CASTRO |
| Drywall Nailing | 9/30/2024 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 10/10/2024 | Approved | JOHN QUINTANILLA |
| Sewer | 11/7/2024 | Approved | ALIZAH MAYAGOITIA |
| Underground Mechanical | 11/7/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 2/14/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Final | 2/14/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 2/14/2025 | Approved | ALIZAH MAYAGOITIA |
| Green Building Final | 2/14/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Final | 2/14/2025 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 2/14/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 2/14/2025 | SGSOV Not Required | ALIZAH MAYAGOITIA |
| Service/Power Release | 2/14/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Smoke Detectors | 2/14/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 2/24/2025 | Conditional Approval | ALIZAH MAYAGOITIA |
| Green Building Final | 2/24/2025 | Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 2/24/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 2/26/2025 | OK to Issue CofO | ALIZAH MAYAGOITIA |