3319 1/2 W MONT CLAIR ST 90018
Certificate Information: 3319 1/2 W MONT CLAIR ST 90018
- Application / Permit
- 23010-10000-05211
- Plan Check / Job No.
- B23LA24303
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ****ePlan**** New 1-story ADU at rear of the lot per LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 2/26/2025
- Issuing Office
- Current Status
- CofO Issued on 8/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/4/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/25/2024 | REZA HAGHIGHAT |
| Corrections Issued | 1/28/2024 | REZA HAGHIGHAT |
| Quality Review Completed | 2/8/2024 | KAVIAN REFAHI |
| Applicant returned to address corrections | 3/20/2024 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 5/13/2024 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 6/24/2024 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 12/27/2024 | REZA HAGHIGHAT |
| Plan Check Approved | 2/24/2025 | REZA HAGHIGHAT |
| Issued | 2/26/2025 | APPLICANT |
| CofO in Progress | 8/12/2025 | JUSTIN HAWLEY |
| Permit Finaled | 8/12/2025 | DEROLD HAUFF |
| CofO Issued | 8/12/2025 | DEROLD HAUFF |
| Permit Finaled | 8/12/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/31/2024 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/3/2024 | DAVID LOPEZ |
| Sewer availability | Cleared | 6/3/2024 | DAVID LOPEZ |
| Hydrant and Access approval | Cleared | 7/6/2024 | JOHN CONNEALLY |
| Low Impact Development (LID) | Cleared | 7/8/2024 | LUIS LUVANO |
| HPOZ | Cleared | 10/31/2024 | DANIEL MATA |
| ZI | Cleared | 10/31/2024 | DANIEL MATA |
| Roof/Waste drainage to street | Cleared | 2/10/2025 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sin,, John Paul; Lic. No.: C91162 | 122 N GRAMERCY PL LOS ANGELES, CA 90004 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/1/2025 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 4/1/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| METHANE-Barrier | 4/1/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| METHANE-Subgrade | 4/1/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| Sewer | 4/1/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 4/3/2025 | Corrections Issued | JEFFREY MEAD |
| Underground Mechanical | 4/3/2025 | Approved | JEFFREY MEAD |
| Excavation/Setback/Form/Re-Bar | 4/9/2025 | Approved | JOSE MACIAS |
| BUILDING-Rough-Frame | 5/5/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2025 | Corrections Issued | WILLIAM SIERRA |
| Green Building Rough | 5/5/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| METHANE-Rough | 5/5/2025 | Approved | WILLIAM SIERRA |
| Verify Sprinkler Sign Off | 5/5/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| Wood Frame | 5/5/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| Deputy Wood Construction | 5/6/2025 | Conditional Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 5/19/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 5/19/2025 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 5/19/2025 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 5/19/2025 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 5/19/2025 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 5/19/2025 | Approved | ENRIQUE MIRELES |
| Rough-Elec/Plmb/HVAC | 5/19/2025 | Approved | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 5/19/2025 | Approved | ENRIQUE MIRELES |
| Wood Frame | 5/19/2025 | Approved | ENRIQUE MIRELES |
| Insulation | 5/23/2025 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 6/2/2025 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 6/2/2025 | Approved | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 7/3/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| ELECTRICAL-Final | 7/3/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| Final | 7/3/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| Footing/Foundation/Slab | 7/3/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| Green Building Final | 7/3/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| HVAC-Final | 7/3/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| METHANE-Barrier | 7/3/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| METHANE-Subgrade | 7/3/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| PLUMBING-Final | 7/3/2025 | Corrections Issued | WILLIAM SIERRA |
| SGSOV-Seismic Gas S/O Valve | 7/3/2025 | SGSOV Not Ready | WILLIAM SIERRA |
| Service/Power Release | 7/3/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| Smoke Detectors | 7/3/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| Verify Sprinkler Sign Off | 7/3/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| ELECTRICAL-Final | 7/8/2025 | Not Ready for Inspection | JUSTIN HAWLEY |
| Final | 7/8/2025 | Corrections Issued | JUSTIN HAWLEY |
| HVAC-Final | 7/8/2025 | Approved | JUSTIN HAWLEY |
| PLUMBING-Final | 7/8/2025 | Approved | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 7/10/2025 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Final | 7/10/2025 | Approved | JUSTIN HAWLEY |
| Final | 7/10/2025 | Not Ready for Inspection | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 7/10/2025 | Approved | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 7/10/2025 | SGSOV Not Required | JUSTIN HAWLEY |
| Smoke Detectors | 7/10/2025 | Approved | JUSTIN HAWLEY |
| Final | 7/31/2025 | Conditional Approval | FREDDIE RIVERA |
| Green Building Final | 7/31/2025 | Approved | FREDDIE RIVERA |
| Service/Power Release | 7/31/2025 | Approved | FREDDIE RIVERA |
| Final | 8/12/2025 | OK to Issue CofO | JUSTIN HAWLEY |