5638 N LEMONA AVE 91411

Certificate Information: 5638 N LEMONA AVE 91411

Application / Permit
23010-10000-05200
Plan Check / Job No.
B23LA24271
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*EPLAN* NEW DETACHED 1-STORY ADU WITH ATTACHED PATIO COVER (280 SF) NFPA 13D
Permit Issued
Issued on 6/5/2024
Issuing Office
Current Status
CofO Issued on 11/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/8/2024 APPLICANT
Assigned to Plan Check Engineer 1/25/2024 VIVIAN LAO
Corrections Issued 1/26/2024 VIVIAN LAO
Quality Review Completed 1/26/2024 GARO TELMI
Plan Check Approved 6/5/2024 VIVIAN LAO
Issued 6/5/2024 APPLICANT
CofO in Progress 10/9/2025 RYAN SALAZAR
Permit Finaled 11/4/2025 RUBEN SALAS
CofO Issued 11/4/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/29/2024 LEE GUILBEAUX
Sewer availability Cleared 1/29/2024 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 2/5/2024 LEE GUILBEAUX
Low Impact Development (LID) Cleared 5/15/2024 LUIS LUVANO
Roof/Waste drainage to street Cleared 5/20/2024 LEE GUILBEAUX
Construction near power lines Cleared 5/22/2024 RIDWAN HARDY
Construction within easement Cleared 5/22/2024 RIDWAN HARDY

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Contractor Owner-Builder       ,
Engineer Thompson,, Matthew Gregory; Lic. No.: C86051 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Grading Pre-Inspection 9/4/2024 Not Ready for Inspection RYAN SALAZAR
Footing/Foundation/Slab 11/8/2024 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 12/16/2024 Partial Approval RYAN SALAZAR
BUILDING-Rough-Frame 1/28/2025 Approved RYAN SALAZAR
ELECTRICAL-Rough 1/28/2025 Approved RYAN SALAZAR
Green Building Rough 1/28/2025 Approved RYAN SALAZAR
HVAC-Rough 1/28/2025 Approved RYAN SALAZAR
PLUMBING-Rough 1/28/2025 Approved RYAN SALAZAR
Sewer 1/28/2025 Approved RYAN SALAZAR
Verify Sprinkler Sign Off 1/28/2025 Approved RYAN SALAZAR
Insulation 2/12/2025 Approved RYAN SALAZAR
Interior/Exterior Lathing 2/12/2025 Partial Approval RYAN SALAZAR
Drywall Nailing 2/18/2025 Not Ready for Inspection JACK KARGODORIAN
Interior/Exterior Lathing 2/18/2025 Partial Approval JACK KARGODORIAN
Drywall Nailing 2/20/2025 Approved RYAN SALAZAR
ELECTRICAL-Final 5/29/2025 Not Ready for Inspection RYAN SALAZAR
Final 5/29/2025 Not Ready for Inspection RYAN SALAZAR
Green Building Final 5/29/2025 Not Ready for Inspection RYAN SALAZAR
HVAC-Final 5/29/2025 Not Ready for Inspection RYAN SALAZAR
PLUMBING-Final 5/29/2025 Not Ready for Inspection RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 5/29/2025 SGSOV Not Required RYAN SALAZAR
Service/Power Release 5/29/2025 Not Ready for Inspection RYAN SALAZAR
Smoke Detectors 5/29/2025 Approved RYAN SALAZAR
Green Building Final 8/26/2025 Approved RYAN SALAZAR
Pre-Inspection 8/26/2025 Approved RYAN SALAZAR
Service/Power Release 8/26/2025 Not Ready for Inspection RYAN SALAZAR
Final 10/6/2025 OK to Issue CofO RYAN SALAZAR
Service/Power Release 10/6/2025 Approved RYAN SALAZAR