5638 N LEMONA AVE 91411
Certificate Information: 5638 N LEMONA AVE 91411
- Application / Permit
- 23010-10000-05200
- Plan Check / Job No.
- B23LA24271
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *EPLAN* NEW DETACHED 1-STORY ADU WITH ATTACHED PATIO COVER (280 SF) NFPA 13D
- Permit Issued
- Issued on 6/5/2024
- Issuing Office
- Current Status
- CofO Issued on 11/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/8/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/25/2024 | VIVIAN LAO |
| Corrections Issued | 1/26/2024 | VIVIAN LAO |
| Quality Review Completed | 1/26/2024 | GARO TELMI |
| Plan Check Approved | 6/5/2024 | VIVIAN LAO |
| Issued | 6/5/2024 | APPLICANT |
| CofO in Progress | 10/9/2025 | RYAN SALAZAR |
| Permit Finaled | 11/4/2025 | RUBEN SALAS |
| CofO Issued | 11/4/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/29/2024 | LEE GUILBEAUX |
| Sewer availability | Cleared | 1/29/2024 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 2/5/2024 | LEE GUILBEAUX |
| Low Impact Development (LID) | Cleared | 5/15/2024 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 5/20/2024 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 5/22/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 5/22/2024 | RIDWAN HARDY |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: C30383 | 5739 KANAN ROAD # 133 AGOURA HILLS, CA 91301 |
| Contractor | Owner-Builder | , |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grading Pre-Inspection | 9/4/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Footing/Foundation/Slab | 11/8/2024 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2024 | Partial Approval | RYAN SALAZAR |
| BUILDING-Rough-Frame | 1/28/2025 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 1/28/2025 | Approved | RYAN SALAZAR |
| Green Building Rough | 1/28/2025 | Approved | RYAN SALAZAR |
| HVAC-Rough | 1/28/2025 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 1/28/2025 | Approved | RYAN SALAZAR |
| Sewer | 1/28/2025 | Approved | RYAN SALAZAR |
| Verify Sprinkler Sign Off | 1/28/2025 | Approved | RYAN SALAZAR |
| Insulation | 2/12/2025 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 2/12/2025 | Partial Approval | RYAN SALAZAR |
| Drywall Nailing | 2/18/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Interior/Exterior Lathing | 2/18/2025 | Partial Approval | JACK KARGODORIAN |
| Drywall Nailing | 2/20/2025 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 5/29/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Final | 5/29/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Green Building Final | 5/29/2025 | Not Ready for Inspection | RYAN SALAZAR |
| HVAC-Final | 5/29/2025 | Not Ready for Inspection | RYAN SALAZAR |
| PLUMBING-Final | 5/29/2025 | Not Ready for Inspection | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 5/29/2025 | SGSOV Not Required | RYAN SALAZAR |
| Service/Power Release | 5/29/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Smoke Detectors | 5/29/2025 | Approved | RYAN SALAZAR |
| Green Building Final | 8/26/2025 | Approved | RYAN SALAZAR |
| Pre-Inspection | 8/26/2025 | Approved | RYAN SALAZAR |
| Service/Power Release | 8/26/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Final | 10/6/2025 | OK to Issue CofO | RYAN SALAZAR |
| Service/Power Release | 10/6/2025 | Approved | RYAN SALAZAR |