441-441 1/2 N HARVARD BLVD 90004
Certificate Information: 441-441 1/2 N HARVARD BLVD 90004
- Application / Permit
- 23010-10000-05195
- Plan Check / Job No.
- B23LA24252
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- EPLAN: NEW 3-STORY 38'-0" x 27'-10" DUPLEX AT FRONT OF LOT NFPA 13D SPRINKLERED THROUGH OUT
- Permit Issued
- Issued on 4/8/2024
- Issuing Office
- Current Status
- CofO Corrected on 12/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/24/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/28/2023 | JAD BASMA |
| Corrections Issued | 12/31/2023 | JAD BASMA |
| Quality Review Completed | 1/5/2024 | PRANITA SHAH |
| Applicant returned to address corrections | 4/3/2024 | JAD BASMA |
| Plan Check Approved | 4/5/2024 | JAD BASMA |
| Issued | 4/8/2024 | APPLICANT |
| CofO in Progress | 4/12/2025 | JEFFREY MEAD |
| CofO Issued-Status Void | 4/13/2025 | DEROLD HAUFF |
| Permit Finaled-Status Void | 4/13/2025 | DEROLD HAUFF |
| Re-Activate Permit | 5/30/2025 | RAUL BARAJAS |
| CofO in Progress | 5/30/2025 | RAUL BARAJAS |
| CofO in Progress | 10/2/2025 | JEFFREY MEAD |
| No Progress | 10/11/2025 | DEROLD HAUFF |
| CofO in Progress | 10/11/2025 | DEROLD HAUFF |
| No Progress | 11/29/2025 | DEROLD HAUFF |
| CofO in Progress | 11/29/2025 | DEROLD HAUFF |
| Permit Finaled | 12/4/2025 | DEROLD HAUFF |
| CofO Corrected | 12/4/2025 | DEROLD HAUFF |
| Permit Finaled | 12/4/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/10/2024 | DAVID LOPEZ |
| Frnt yard landscape/Water mgmt | Cleared | 1/26/2024 | MATHEW QUAN |
| Hydrant and Access approval | Cleared | 2/10/2024 | RUEL COLE |
| Low Impact Development (LID) | Cleared | 3/21/2024 | MARCO SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/22/2024 | DAVID LOPEZ |
| Sewer availability | Cleared | 3/22/2024 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 3/26/2024 | DAVID LOPEZ |
| SB8 RUD | Cleared | 4/2/2024 | OLIVIA JIN |
Contact Information
| Contractor | Riviera Building & Design Inc; Lic. No.: 878203-B | , |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/23/2024 | Approved | JEFFREY MEAD |
| Footing/Foundation/Slab | 6/4/2024 | Approved | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2024 | Partial Approval | JOSEPH MCGARRY |
| Deputy Steel/Welding | 6/28/2024 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2024 | Corrections Issued | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 8/27/2024 | Corrections Issued | JEFFREY MEAD |
| HVAC-Rough | 9/3/2024 | Corrections Issued | JEFFREY MEAD |
| PLUMBING-Rough | 9/3/2024 | Approved | JEFFREY MEAD |
| ELECTRICAL-Rough | 9/9/2024 | Approved | JEFFREY MEAD |
| HVAC-Rough | 9/9/2024 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 9/18/2024 | Partial Inspection | JEFFREY MEAD |
| Green Building Rough | 9/18/2024 | Approved | JEFFREY MEAD |
| Verify Sprinkler Sign Off | 9/18/2024 | Not Ready for Inspection | JEFFREY MEAD |
| Deputy Wood Construction | 9/24/2024 | Partial Approval | JEFFREY MEAD |
| Interior/Exterior Lathing | 9/30/2024 | Approved | JEFFREY MEAD |
| Insulation | 10/8/2024 | Approved | JEFFREY MEAD |
| Drywall Nailing | 10/15/2024 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 10/17/2024 | Approved | JEFFREY MEAD |
| Sewer | 11/13/2024 | Corrections Issued | JEFFREY MEAD |
| Sewer | 11/15/2024 | Approved | JEFFREY MEAD |
| ELECTRICAL-Final | 1/13/2025 | Not Ready for Inspection | JEFFREY MEAD |
| HVAC-Final | 1/13/2025 | No Access for Inspection | JEFFREY MEAD |
| PLUMBING-Final | 1/13/2025 | Not Ready for Inspection | JEFFREY MEAD |
| ELECTRICAL-Final | 1/23/2025 | Approved | JEFFREY MEAD |
| Gas Test | 1/23/2025 | Approved | JEFFREY MEAD |
| HVAC-Final | 1/23/2025 | Corrections Issued | JEFFREY MEAD |
| PLUMBING-Final | 1/23/2025 | Approved | JEFFREY MEAD |
| Service/Power Release | 1/23/2025 | Not Ready for Inspection | JEFFREY MEAD |
| BUILDING-Rough-Frame | 4/8/2025 | Approved | JEFFREY MEAD |
| Final | 4/8/2025 | Corrections Issued | JEFFREY MEAD |
| Green Building Final | 4/8/2025 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 4/8/2025 | SGSOV Not Ready | JEFFREY MEAD |
| Service/Power Release | 4/8/2025 | Not Ready for Inspection | JEFFREY MEAD |
| Smoke Detectors | 4/8/2025 | Approved | JEFFREY MEAD |
| Verify Sprinkler Sign Off | 4/8/2025 | Approved | JEFFREY MEAD |
| Final | 4/11/2025 | Not Ready for Inspection | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 4/11/2025 | SGSOV Approved | JEFFREY MEAD |
| Service/Power Release | 4/11/2025 | Approved | JEFFREY MEAD |
| Final | 5/30/2025 | Corrections Issued | JEFFREY MEAD |
| Special/Order Compliance | 8/13/2025 | Approved | JEFFREY MEAD |
| Final | 10/2/2025 | OK to Issue CofO | JEFFREY MEAD |
| Special/Order Compliance | 10/20/2025 | Partial Inspection | JOSH MEISTER |