4545-4547 W PROSPECT AVE 90027
Certificate Information: 4545-4547 W PROSPECT AVE 90027
- Application / Permit
- 23010-10000-05170
- Plan Check / Job No.
- B23LA24168
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- ****ePlan**** New 3-story duplex
- Permit Issued
- Issued on 12/10/2024
- Issuing Office
- Current Status
- Issued on 12/10/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/18/2024 | REZA HAGHIGHAT |
| Corrections Issued | 1/22/2024 | REZA HAGHIGHAT |
| Quality Review Completed | 1/30/2024 | KAVIAN REFAHI |
| Applicant returned to address corrections | 3/4/2024 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 3/19/2024 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 4/8/2024 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 4/27/2024 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 5/2/2024 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 6/24/2024 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 11/7/2024 | REZA HAGHIGHAT |
| Plan Check Approved | 11/19/2024 | REZA HAGHIGHAT |
| Issued | 12/10/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/25/2024 | WALLIE JONG |
| Highway dedication | Cleared | 1/25/2024 | WALLIE JONG |
| Permit | Cleared | 1/25/2024 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 1/26/2024 | WALLIE JONG |
| Sewer availability | Cleared | 1/26/2024 | WALLIE JONG |
| Grading Pre-Inspection | Cleared | 2/7/2024 | SERGIO VALENZUELA |
| Hydrant and Access approval | Cleared | 3/8/2024 | MATTHEW CRAIG |
| GPI Written Notices | Cleared | 5/5/2024 | REZA HAGHIGHAT |
| Low Impact Development (LID) | Cleared | 5/29/2024 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 5/30/2024 | WALLIE JONG |
| Trees in Parkway | Cleared | 9/30/2024 | ADALBERTO VERA |
| Frnt yard landscape/Water mgmt | Cleared | 10/9/2024 | DAVID URITA |
| Specific Plan | Cleared | 10/9/2024 | DAVID URITA |
Contact Information
| Contractor | Luban Z Construction Corp; Lic. No.: 1033129-B | , |
| Engineer | Hwang,, Junho; Lic. No.: S5592 | 815 FAIRVIEW AVE #205 SOUTH PASADENA, CA 91030 |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Masonry Wall/Backfill | 2/25/2025 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 3/20/2025 | Approved | ENRIQUE MIRELES |
| Masonry Wall/Backfill | 3/27/2025 | Approved | ENRIQUE MIRELES |
| Sewer | 4/30/2025 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 5/29/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| Underground Mechanical | 5/30/2025 | Corrections Issued | ENRIQUE MIRELES |
| Underground Mechanical | 6/3/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| Underground Mechanical | 6/5/2025 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 6/23/2025 | Corrections Issued | ENRIQUE MIRELES |
| Underground Mechanical | 6/23/2025 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 6/25/2025 | Approved | ENRIQUE MIRELES |
| Wood Frame | 7/24/2025 | Partial Approval | ENRIQUE MIRELES |
| Wood Frame | 8/8/2025 | Partial Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 8/28/2025 | Approved | ENRIQUE MIRELES |
| Wood Frame | 8/28/2025 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 12/9/2025 | Corrections Issued | ENRIQUE MIRELES |
| PLUMBING-Rough | 12/9/2025 | Corrections Issued | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 2/6/2026 | Corrections Issued | ENRIQUE MIRELES |
| Deputy Wood Construction | 2/10/2026 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2026 | Approved | ENRIQUE MIRELES |
| Special/Order Compliance | 2/11/2026 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 2/24/2026 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 3/18/2026 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 3/18/2026 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 3/18/2026 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 4/8/2026 | Approved | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 4/8/2026 | Approved | ENRIQUE MIRELES |
| Insulation | 4/22/2026 | Approved | ENRIQUE MIRELES |
| Shower Pan | 4/22/2026 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 4/30/2026 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 4/30/2026 | Approved | ENRIQUE MIRELES |