5657 E BUCHANAN ST 90042

Certificate Information: 5657 E BUCHANAN ST 90042

Application / Permit
23010-10000-05155
Plan Check / Job No.
B23LA24096
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 36'-9" X 26'-9" DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g) - PER ENGINEER
Permit Issued
Issued on 9/26/2024
Issuing Office
Current Status
CofO Issued on 11/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/21/2023 APPLICANT
Assigned to Plan Check Engineer 12/22/2023 DANIEL ABRAMYAN
Corrections Issued 12/25/2023 DANIEL ABRAMYAN
Plan Check Approved 4/14/2024 DANIEL ABRAMYAN
Issued 9/26/2024 APPLICANT
CofO in Progress 11/14/2025 DAVID WILLIAMS
Permit Finaled 11/15/2025 DEROLD HAUFF
Permit Finaled 11/15/2025 DEROLD HAUFF
CofO Issued 11/15/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/31/2024 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 2/3/2024 ADRIAN SANCHEZ
Sewer availability Cleared 2/3/2024 ADRIAN SANCHEZ
Grading Pre-Inspection Cleared 3/6/2024 LANNY MERRICK
HPOZ Cleared 3/13/2024 MICAELA TORRES-GIL
Miscellaneous Cleared 3/13/2024 MICAELA TORRES-GIL
Low Impact Development (LID) Cleared 4/10/2024 PATRICK LOPEZ
Roof/Waste drainage to street Cleared 4/11/2024 JUSTIN BICOL
GPI Written Notices Cleared 4/14/2024 DANIEL ABRAMYAN

Contact Information

Contractor Md Patchin Construction; Lic. No.: 1105506-B       ,
Engineer Boranian,, Paul; Lic. No.: S5944 23261 BURBANK BL      WOODLAND HILLS, CA 91367

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/8/2024 Partial Approval ALIZAH MAYAGOITIA
Sewer 11/8/2024 Approved ALIZAH MAYAGOITIA
Underground Mechanical 11/8/2024 Partial Approval ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 11/15/2024 Corrections Issued ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 11/19/2024 Corrections Issued ROY SPAULDING
Excavation/Setback/Form/Re-Bar 12/3/2024 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 12/20/2024 Not Ready for Inspection BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 12/20/2024 Corrections Issued BRENDAN MORELLI
Green Building Rough 12/20/2024 Not Ready for Inspection BRENDAN MORELLI
Verify Sprinkler Sign Off 12/20/2024 Not Ready for Inspection BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 12/23/2024 Not Ready for Inspection CRAIG DAVIS
PLUMBING-Rough 1/6/2025 Approved CRAIG DAVIS
HVAC-Rough 1/16/2025 Corrections Issued CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 2/25/2025 Approved ALIZAH MAYAGOITIA
Green Building Rough 2/25/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Verify Sprinkler Sign Off 2/25/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Rough 3/20/2025 Approved DAVID WILLIAMS
HVAC-Rough 3/20/2025 Approved DAVID WILLIAMS
Interior/Exterior Lathing 4/15/2025 Approved DAVID WILLIAMS
Insulation 4/24/2025 Approved DAVID WILLIAMS
Drywall Nailing 5/22/2025 Approved DAVID WILLIAMS
Green Building Rough 5/22/2025 Approved DAVID WILLIAMS
Shower Pan 6/3/2025 Approved REGINA MENDEZ
Interior/Exterior Lathing 6/5/2025 Approved REGINA MENDEZ
ELECTRICAL-Final 8/20/2025 Corrections Issued LILIANA PORTILLO
Service/Power Release 8/20/2025 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Final 9/10/2025 Not Ready for Inspection DAVID WILLIAMS
PLUMBING-Final 9/10/2025 Corrections Issued DAVID WILLIAMS
Service/Power Release 9/10/2025 Approved DAVID WILLIAMS
BUILDING-Rough-Frame 10/14/2025 Approved DAVID WILLIAMS
Final 10/14/2025 Corrections Issued DAVID WILLIAMS
Footing/Foundation/Slab 10/14/2025 Approved DAVID WILLIAMS
Green Building Final 10/14/2025 Approved DAVID WILLIAMS
SGSOV-Seismic Gas S/O Valve 10/14/2025 SGSOV Approved DAVID WILLIAMS
Smoke Detectors 10/14/2025 Approved DAVID WILLIAMS
Verify Sprinkler Sign Off 10/14/2025 Approved DAVID WILLIAMS
Final 11/13/2025 OK to Issue CofO DAVID WILLIAMS