3215 S FEDERAL AVE 90066
Certificate Information: 3215 S FEDERAL AVE 90066
- Application / Permit
- 23010-10000-05090
- Plan Check / Job No.
- B23LA23908
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ALTERATION TO EXISTING SFD WITH TWO STORY ADDITION, GARAGE + ROOF DECK.
- Permit Issued
- Issued on 4/2/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/19/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/21/2023 | NGHI SU |
| Corrections Issued | 12/23/2023 | NGHI SU |
| Quality Review Completed | 12/29/2023 | KEN GILL |
| Building Plans Picked Up | 1/2/2024 | APPLICANT |
| Plan Check Approved | 3/29/2024 | NGHI SU |
| Issued | 4/2/2024 | APPLICANT |
| CofO in Progress | 5/22/2025 | WILBER ROSALES |
| Permit Finaled | 5/30/2025 | RICHARD STEINBACH |
| CofO Issued | 5/30/2025 | RICHARD STEINBACH |
| Permit Finaled | 5/30/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/8/2024 | LIAM ODONOVAN |
| Sewer availability | Cleared | 1/8/2024 | LIAM ODONOVAN |
| Hydrant and Access approval | Cleared | 2/3/2024 | KURT CORRAL |
| Low Impact Development (LID) | Cleared | 2/14/2024 | SAMUEL LINN |
| Specific Plan | Cleared | 2/15/2024 | ALESSANDRO MERCURI |
| Roof/Waste drainage to street | Cleared | 2/16/2024 | LIAM ODONOVAN |
| GPI Written Notices | Cleared | 3/13/2024 | NGHI SU |
| Grading Pre-Inspection | Cleared | 3/13/2024 | NGHI SU |
Contact Information
| Architect | Rezvani,, Farbod; Lic. No.: C32315 | 9055 ALCOTT STREET #1 LOS ANGELES, CA 90035 |
| Contractor | Di Nalli Consulting Llc; Lic. No.: 942979-B | 9055 ALCOTT STREET UNIT 1 LOS ANGELES, CA 90035 |
| Engineer | Askarian,, Soroosh; Lic. No.: C83413 | 22287 MULHOLLAND HWY 163 CALABASAS, CA 91302 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/17/2024 | Partial Inspection | JESUS PINEDA |
| Special/Order Compliance | 5/2/2024 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Rough | 7/24/2024 | Corrections Issued | JESUS PINEDA |
| Footing/Foundation/Slab | 8/5/2024 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 8/5/2024 | Approved | JESUS PINEDA |
| Deputy Reinf. Concrete | 8/15/2024 | Conditional Approval | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2024 | Approved | DANIEL VERA |
| Deputy Wood Construction | 10/2/2024 | Conditional Approval | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 10/10/2024 | Approved | DANIEL VERA |
| Wood Frame | 10/10/2024 | Approved | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2024 | Approved | DANIEL VERA |
| PLUMBING-Rough | 10/17/2024 | Approved | DANIEL VERA |
| ELECTRICAL-Rough | 10/22/2024 | Approved | DANIEL VERA |
| Interior/Exterior Lathing | 10/22/2024 | Partial Approval | DANIEL VERA |
| HVAC-Rough | 10/31/2024 | Not Ready for Inspection | DANIEL VERA |
| BUILDING-Rough-Frame | 11/1/2024 | Approved | DANIEL VERA |
| Green Building Rough | 11/1/2024 | Approved | DANIEL VERA |
| HVAC-Rough | 11/1/2024 | Approved | DANIEL VERA |
| Insulation | 11/6/2024 | Approved | DANIEL VERA |
| Shower Pan | 11/6/2024 | Approved | DANIEL VERA |
| Drywall Nailing | 11/12/2024 | Approved | REGINA MENDEZ |
| Interior/Exterior Lathing | 11/12/2024 | Approved | REGINA MENDEZ |
| ELECTRICAL-Final | 4/21/2025 | Approved | MEL KHACHATOURIAN |
| Gas Test | 4/21/2025 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Final | 4/21/2025 | Approved | MEL KHACHATOURIAN |
| HVAC-Final | 4/22/2025 | Approved | WILBER ROSALES |
| Final | 5/12/2025 | Corrections Issued | WILBER ROSALES |
| Green Building Final | 5/12/2025 | Approved | WILBER ROSALES |
| SGSOV-Seismic Gas S/O Valve | 5/12/2025 | SGSOV Approved | WILBER ROSALES |
| Smoke Detectors | 5/12/2025 | Approved | WILBER ROSALES |
| Final | 5/21/2025 | OK to Issue CofO | WILBER ROSALES |
| Service/Power Release | 5/29/2025 | Approved | WILBER ROSALES |