2072 W 27TH ST 90018
Certificate Information: 2072 W 27TH ST 90018
- Application / Permit
- 23010-10000-05057
- Plan Check / Job No.
- B23LA23730
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 25' X 33'6" DETACHED, FULLY ELECTRIC, IRREGULARLY SHAPED ACCESSORY DWELLING UNIT (554 SF) PER LAMC 12.22.A.33(c) AND (d). WORK DONE PER ENGINEER DESIGN.
- Permit Issued
- Issued on 8/31/2024
- Issuing Office
- Current Status
- CofO Issued on 8/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/19/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/22/2023 | MADISON ODELL |
| Corrections Issued | 12/23/2023 | MADISON ODELL |
| Applicant returned to address corrections | 1/31/2024 | MADISON ODELL |
| Applicant returned to address corrections | 3/13/2024 | MADISON ODELL |
| Applicant returned to address corrections | 3/26/2024 | MADISON ODELL |
| Plan Check Approved | 8/21/2024 | MADISON O'DELL |
| Issued | 8/31/2024 | APPLICANT |
| CofO in Progress | 8/7/2025 | SABAS ALONSO |
| Permit Finaled | 8/9/2025 | DEROLD HAUFF |
| CofO Issued | 8/9/2025 | DEROLD HAUFF |
| Permit Finaled | 8/9/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/29/2023 | DAVID LOPEZ |
| HPOZ | Cleared | 2/27/2024 | DANIEL MATA |
| Historic monument | Cleared | 2/27/2024 | DANIEL MATA |
| Miscellaneous | Cleared | 2/27/2024 | DANIEL MATA |
| Miscellaneous | Cleared | 2/27/2024 | DANIEL MATA |
| Miscellaneous | Cleared | 2/27/2024 | DANIEL MATA |
| Miscellaneous | Cleared | 2/27/2024 | DANIEL MATA |
| Eng Process Fee Ord 176,300 | Cleared | 3/15/2024 | JUSTIN BICOL |
| Sewer availability | Cleared | 3/15/2024 | JUSTIN BICOL |
| Construction near power lines | Cleared | 3/18/2024 | TINA MIRANDA |
| Low Impact Development (LID) | Cleared | 8/6/2024 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 8/8/2024 | CHRISTINA BRACO |
Contact Information
| Contractor | J Z J B Cnst Inv; Lic. No.: 1013600-B | 345 W LORAINE ST 3 GLENDALE, CA 91202 |
| Engineer | Jaramillo,, Mauricio; Lic. No.: C69957 | 578 WASHINGTON BLVD 743 MARINA DEL REY, CA 90292 |
| Engineer | Ramos,, Victor; Lic. No.: C86568 | 4823 ALMAGUER AVE GUADALUPE, CA 93434 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 10/8/2024 | Partial Approval | SABAS ALONSO |
| METHANE-Subgrade | 10/23/2024 | Approved | SABAS ALONSO |
| Deputy Methane Barrier | 11/1/2024 | Conditional Approval | JOSH MEISTER |
| Deputy Methane Barrier | 11/4/2024 | Conditional Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 11/15/2024 | Conditional Approval | SABAS ALONSO |
| METHANE-Barrier | 11/15/2024 | Approved | SABAS ALONSO |
| METHANE-Rough | 11/15/2024 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 1/16/2025 | Approved | SABAS ALONSO |
| HVAC-Rough | 1/16/2025 | Approved | SABAS ALONSO |
| METHANE-Rough | 1/16/2025 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 1/16/2025 | Corrections Issued | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2025 | Approved | SABAS ALONSO |
| HVAC-Rough | 1/31/2025 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 1/31/2025 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 2/24/2025 | Approved | SABAS ALONSO |
| Green Building Rough | 2/24/2025 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 2/24/2025 | Partial Approval | SABAS ALONSO |
| Insulation | 2/27/2025 | Approved | SABAS ALONSO |
| Drywall Nailing | 3/6/2025 | Approved | SABAS ALONSO |
| Shower Pan | 3/26/2025 | Not Ready for Inspection | SABAS ALONSO |
| Interior/Exterior Lathing | 4/16/2025 | Approved | ANTHONY RAMOS |
| Shower Pan | 4/16/2025 | Approved | ANTHONY RAMOS |
| Sewer | 4/22/2025 | Partial Approval | BRENDAN MORELLI |
| Underground Mechanical | 4/22/2025 | Partial Approval | BRENDAN MORELLI |
| ELECTRICAL-Final | 7/23/2025 | Corrections Issued | SABAS ALONSO |
| HVAC-Final | 7/23/2025 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Final | 7/23/2025 | Approved | SABAS ALONSO |
| Final | 7/30/2025 | Corrections Issued | WAYNE REGESTER |
| Footing/Foundation/Slab | 7/30/2025 | Approved | WAYNE REGESTER |
| Green Building Final | 7/30/2025 | Approved | WAYNE REGESTER |
| SGSOV-Seismic Gas S/O Valve | 7/30/2025 | SGSOV Not Required | WAYNE REGESTER |
| Service/Power Release | 7/30/2025 | Corrections Issued | WAYNE REGESTER |
| Smoke Detectors | 7/30/2025 | Not Ready for Inspection | WAYNE REGESTER |
| ELECTRICAL-Final | 8/1/2025 | Approved | SABAS ALONSO |
| Final | 8/1/2025 | Corrections Issued | SABAS ALONSO |
| HVAC-Final | 8/1/2025 | Approved | SABAS ALONSO |
| Service/Power Release | 8/1/2025 | Not Ready for Inspection | SABAS ALONSO |
| Smoke Detectors | 8/1/2025 | Corrections Issued | SABAS ALONSO |
| Final | 8/6/2025 | OK to Issue CofO | SABAS ALONSO |
| Service/Power Release | 8/6/2025 | Not Required | SABAS ALONSO |
| Smoke Detectors | 8/6/2025 | Approved | SABAS ALONSO |