9521 N PETIT AVE 91343
Certificate Information: 9521 N PETIT AVE 91343
- Application / Permit
- 23010-10000-05046
- Plan Check / Job No.
- B23LA23688
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT per LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 7/16/2024
- Issuing Office
- Metro
- Current Status
- Issued on 7/16/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/15/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/20/2023 | LUKE GONZALES |
| Corrections Issued | 12/23/2023 | LUKE GONZALES |
| Building Plans Picked Up | 1/5/2024 | APPLICANT |
| Applicant returned to address corrections | 6/3/2024 | JOSE VELAZQUEZ |
| Applicant returned to address corrections | 7/11/2024 | SUNMIN LEE |
| Plan Check Approved | 7/15/2024 | NEHEMIAS RAMOS |
| Issued | 7/16/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/13/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 1/23/2024 | CARLOS AGUILERA |
| Grading Pre-Inspection | Cleared | 2/20/2024 | CHARLES POWELL |
| Hold | Cleared | 4/15/2024 | MARIA VENDIVIL |
| Low Impact Development (LID) | Cleared | 5/30/2024 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 6/3/2024 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 6/26/2024 | EDGAR PASCUA |
| Eng Process Fee Ord 176,300 | Cleared | 7/9/2024 | CARLOS AGUILERA |
| GPI Written Notices | Cleared | 7/15/2024 | LUKE GONZALES |
Contact Information
| Contractor | Cgs Home Improvement Inc; Lic. No.: 1037939-B | 7189 N FIGUEROA ST LOS ANGELES, CA 90042 |
| Engineer | Nagovitsyn,, Evgeny; Lic. No.: C93527 | 17436 ARMINTA ST NORTHRIDGE, CA 91325 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/28/2024 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 8/28/2024 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 9/4/2024 | Partial Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 12/9/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Excavation/Setback/Form/Re-Bar | 12/13/2024 | Approved | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Underground Mechanical | 1/13/2025 | Partial Approval | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/17/2025 | Approved | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 2/21/2025 | Corrections Issued | SALVADOR MARTINEZ |
| HVAC-Rough | 2/21/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 2/21/2025 | Approved | SALVADOR MARTINEZ |
| Sewer | 2/21/2025 | Approved | SALVADOR MARTINEZ |
| Underground Mechanical | 2/21/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 3/26/2025 | Partial Approval | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 4/3/2025 | Partial Approval | GAREN HAYRAPETYAN |
| ELECTRICAL-Rough | 4/3/2025 | Approved | GAREN HAYRAPETYAN |
| Green Building Rough | 4/3/2025 | Approved | GAREN HAYRAPETYAN |
| HVAC-Rough | 4/3/2025 | Approved | GAREN HAYRAPETYAN |
| Insulation | 4/11/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Shower Pan | 5/13/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 5/29/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 5/29/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 6/6/2025 | Approved | SALVADOR MARTINEZ |
| Insulation | 6/6/2025 | Approved | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 6/6/2025 | Approved | SALVADOR MARTINEZ |
| Verify Sprinkler Sign Off | 6/6/2025 | Approved | SALVADOR MARTINEZ |
| Drywall Nailing | 8/15/2025 | Approved | LOUIS ESCOTO |
| PLUMBING-Rough | 8/15/2025 | Approved | LOUIS ESCOTO |
| Final | 2/6/2026 | Corrections Issued | GAREN HAYRAPETYAN |
| Footing/Foundation/Slab | 2/6/2026 | Approved | GAREN HAYRAPETYAN |
| Green Building Final | 2/6/2026 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 2/6/2026 | SGSOV No Gas | GAREN HAYRAPETYAN |
| Service/Power Release | 2/6/2026 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Smoke Detectors | 2/6/2026 | Approved | GAREN HAYRAPETYAN |
| Pre-Inspection | 5/20/2026 | Partial Inspection | MICHAEL CORTEZ |