2465-2465 1/2 W 18TH ST 90019

Certificate Information: 2465-2465 1/2 W 18TH ST 90019

Application / Permit
23010-10000-05034
Plan Check / Job No.
B23LA23656
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New two-story two-unit detached ADU. 442sf per unit.
Permit Issued
Issued on 12/26/2024
Issuing Office
Current Status
CofO Issued on 11/25/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/15/2023 APPLICANT
Assigned to Plan Check Engineer 1/4/2024 JOE VO
Corrections Issued 1/7/2024 JOE VO
Quality Review Completed 1/8/2024 GARO TELMI
Plan Check Approved 3/18/2024 JOE VO
Issued 12/26/2024 APPLICANT
CofO in Progress 11/24/2025 WILLIAM SIERRA
Permit Finaled 11/25/2025 DEROLD HAUFF
CofO Issued 11/25/2025 DEROLD HAUFF
Permit Finaled 11/25/2025 DEROLD HAUFF

Permit Application Clearance Information

Hydrant and Access approval Cleared 1/25/2024 LAVEON RIDER
Low Impact Development (LID) Cleared 2/28/2024 ROGELIO CORTES
Address approval Cleared 3/1/2024 TREVOR QUAN
Roof/Waste drainage to street Cleared 3/1/2024 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 3/4/2024 TREVOR QUAN
Sewer availability Cleared 3/4/2024 TREVOR QUAN
Community Plan Implem. Overlay Cleared 3/11/2024 MANERI ROMAN

Contact Information

Contractor Build Tuff Construction; Lic. No.: 1076283-B       ,
Engineer Sutrisno,, Raivyno; Lic. No.: C93874 19423 VANOWEN ST      RESEDA, CA 91335

Inspector Information

WILLIAM SIERRA, (213) 202-3122 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/19/2025 Partial Approval WILLIAM SIERRA
Underground Mechanical 2/19/2025 Approved WILLIAM SIERRA
Pre-Inspection 3/4/2025 Partial Inspection WILLIAM SIERRA
Deputy Reinf. Concrete 5/23/2025 No Result Entered WILLIAM KUEHN
Deputy Methane Barrier 5/28/2025 Conditional Approval FREDDIE RIVERA
Deputy Methane Barrier 6/10/2025 Conditional Approval WILLIAM SIERRA
Deputy Methane Barrier 6/13/2025 Conditional Approval WILLIAM SIERRA
Footing/Foundation/Slab 6/17/2025 Approved WILLIAM SIERRA
METHANE-Barrier 6/17/2025 Approved WILLIAM SIERRA
METHANE-Subgrade 6/17/2025 Approved WILLIAM SIERRA
Floor/Roof Diaphrgm/Shear Wall 6/27/2025 Partial Approval WILLIAM SIERRA
Pre-Inspection 6/27/2025 Partial Inspection WILLIAM SIERRA
Wood Frame 6/27/2025 Partial Inspection WILLIAM SIERRA
Floor/Roof Diaphrgm/Shear Wall 7/10/2025 Corrections Issued WILLIAM SIERRA
ELECTRICAL-Rough 7/29/2025 Approved ARTHUR NEGRETE
HVAC-Rough 7/29/2025 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 7/29/2025 Conditional Approval ARTHUR NEGRETE
PLUMBING-Rough 7/29/2025 Corrections Issued ARTHUR NEGRETE
ELECTRICAL-Rough 8/1/2025 Corrections Issued WILLIAM SIERRA
Floor/Roof Diaphrgm/Shear Wall 8/1/2025 Approved WILLIAM SIERRA
HVAC-Rough 8/1/2025 Corrections Issued WILLIAM SIERRA
METHANE-Rough 8/1/2025 Approved WILLIAM SIERRA
PLUMBING-Rough 8/1/2025 Approved WILLIAM SIERRA
Deputy Methane Barrier 8/4/2025 Conditional Approval WILLIAM SIERRA
HVAC-Rough 8/4/2025 Approved DEVON JACKSON
Insulation 8/4/2025 Approved DEVON JACKSON
Insulation 8/6/2025 Approved DEVON JACKSON
Drywall Nailing 8/8/2025 Approved ANTHONY RAMOS
BUILDING-Rough-Frame 8/14/2025 No Access for Inspection HAMIK HARTOUNIAN
Green Building Rough 8/14/2025 No Access for Inspection HAMIK HARTOUNIAN
Interior/Exterior Lathing 8/14/2025 No Access for Inspection HAMIK HARTOUNIAN
Shower Pan 8/14/2025 No Access for Inspection HAMIK HARTOUNIAN
Special/Order Compliance 8/14/2025 Corrections Issued ANTHONY RAMOS
Verify Sprinkler Sign Off 8/14/2025 No Access for Inspection HAMIK HARTOUNIAN
Wood Frame 8/14/2025 No Access for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 8/18/2025 Corrections Issued WILLIAM SIERRA
BUILDING-Rough-Frame 8/29/2025 Approved WILLIAM SIERRA
Green Building Rough 8/29/2025 Approved WILLIAM SIERRA
Interior/Exterior Lathing 8/29/2025 Approved WILLIAM SIERRA
Shower Pan 8/29/2025 Approved WILLIAM SIERRA
Verify Sprinkler Sign Off 8/29/2025 Approved WILLIAM SIERRA
Wood Frame 8/29/2025 Approved WILLIAM SIERRA
SGSOV-Seismic Gas S/O Valve 10/10/2025 SGSOV Not Ready WILLIAM SIERRA
SGSOV-Seismic Gas S/O Valve 10/16/2025 SGSOV Not Ready WILLIAM SIERRA
ELECTRICAL-Final 10/17/2025 Approved WILLIAM SIERRA
Final 10/17/2025 Corrections Issued WILLIAM SIERRA
HVAC-Final 10/17/2025 Approved WILLIAM SIERRA
PLUMBING-Final 10/17/2025 Approved WILLIAM SIERRA
Smoke Detectors 10/17/2025 Approved WILLIAM SIERRA
Final 11/24/2025 OK to Issue CofO WILLIAM SIERRA
Green Building Final 11/24/2025 Approved WILLIAM SIERRA
SGSOV-Seismic Gas S/O Valve 11/24/2025 SGSOV Not Required WILLIAM SIERRA
Service/Power Release 11/24/2025 Approved WILLIAM SIERRA