2223 N VALENTINE ST 90026
Certificate Information: 2223 N VALENTINE ST 90026
- Application / Permit
- 23010-10000-05018
- Plan Check / Job No.
- B23LA23608
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW THREE STORY SINGLE FAMILY DWELLING WITH ATTACHED 2 CAR GARAGE AND STORAGE NFPA 13D SPRINKLERED THROUGH OUT
- Permit Issued
- Issued on 5/7/2024
- Issuing Office
- Metro
- Current Status
- Issued on 5/7/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/21/2023 | JAD BASMA |
| Corrections Issued | 12/25/2023 | JAD BASMA |
| Quality Review Completed | 12/29/2023 | KEN GILL |
| Building Plans Picked Up | 1/4/2024 | APPLICANT |
| Plan Check Approved | 5/7/2024 | JAD BASMA |
| Issued | 5/7/2024 | APPLICANT |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 1/20/2024 | STEVEN JIN |
| BHO/Hillside ordinance | Cleared | 1/20/2024 | STEVEN JIN |
| BHO/Hillside ordinance | Cleared | 1/20/2024 | STEVEN JIN |
| BHO/Hillside ordinance | Cleared | 1/20/2024 | STEVEN JIN |
| BHO/Hillside ordinance | Cleared | 1/20/2024 | STEVEN JIN |
| Address approval | Cleared | 1/23/2024 | ARNULFO CHAMU |
| Eng Process Fee Ord 176,300 | Cleared | 1/23/2024 | ARNULFO CHAMU |
| Sewer availability | Cleared | 1/23/2024 | ARNULFO CHAMU |
| Permit | Cleared | 1/30/2024 | DAVID VO |
| Hydrant and Access approval | Cleared | 2/2/2024 | KURT CORRAL |
| Work Adjacent to Public Way | Cleared | 2/7/2024 | LARRY LEE |
| Disturb/Remove Protected Trees | Cleared | 2/15/2024 | ADALBERTO VERA |
| Trees in Parkway | Cleared | 2/15/2024 | ADALBERTO VERA |
| Low Impact Development (LID) | Cleared | 3/25/2024 | PATRICK LOPEZ |
| Roof/Waste drainage to street | Cleared | 3/28/2024 | AMBER CAMPBELL |
| Excavation more than 5-ft deep | Cleared | 4/16/2024 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 4/16/2024 | JAD BASMA |
| Grading Pre-Inspection | Cleared | 4/16/2024 | JAD BASMA |
| Green Code | Cleared | 4/16/2024 | JAD BASMA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 9/11/2024 | Partial Approval | LUIS CASTRO |
| Piling/Pier/Caisson | 9/11/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Deputy Reinf. Concrete | 9/13/2024 | Conditional Approval | LANNY MERRICK |
| Piling/Pier/Caisson | 9/17/2024 | Partial Approval | HAMIK HARTOUNIAN |
| Deputy Reinf. Concrete | 9/23/2024 | Conditional Approval | HAMIK HARTOUNIAN |
| Deputy Reinf. Concrete | 12/19/2024 | Conditional Approval | JOSH MEISTER |
| Footing/Foundation/Slab | 1/13/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 1/22/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Deputy Wood Construction | 3/6/2025 | Conditional Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Deputy Wood Construction | 3/19/2025 | Conditional Approval | REGINA MENDEZ |
| Deputy Wood Construction | 4/8/2025 | Conditional Approval | HAMIK HARTOUNIAN |
| Deputy Wood Construction | 4/10/2025 | Conditional Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 4/14/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 4/17/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 5/8/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Sewer | 5/15/2025 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 7/10/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| HVAC-Rough | 7/10/2025 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 7/10/2025 | Approved | HAMIK HARTOUNIAN |
| Special/Order Compliance | 7/10/2025 | Partial Inspection | OSVALDO PARAMO |
| Deputy Wood Construction | 7/11/2025 | Conditional Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 7/18/2025 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/18/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Shower Pan | 7/18/2025 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/21/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Insulation | 7/23/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/4/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 8/7/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 9/26/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Insulation | 9/30/2025 | No Access for Inspection | HAMIK HARTOUNIAN |
| Insulation | 10/1/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/2/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 10/2/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 10/8/2025 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 10/8/2025 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 10/8/2025 | Conditional Approval | FREDDIE RIVERA |
| Green Building Rough | 10/8/2025 | Approved | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 10/8/2025 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 10/23/2025 | Partial Approval | OSVALDO PARAMO |
| Sewer | 2/3/2026 | No Access for Inspection | HAMIK HARTOUNIAN |
| Sewer | 2/6/2026 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 4/28/2026 | Approved | HAMIK HARTOUNIAN |