314 N AMALFI DR 90402
Certificate Information: 314 N AMALFI DR 90402
- Application / Permit
- 23010-10000-04958
- Plan Check / Job No.
- B23LA23357
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- <ePLAN> NEW 54'2"X38'0 IRREGULAR SHAPED 2-STORY SINGLE FAMILY DWELLING WITH AN ATTACHED 2-CAR GARAGE. NFPA 13 D FIRE SPRINKLERS REQUIRED THROUGHOUT. {ALL ELECTRIC BUILDING}
- Permit Issued
- Issued on 1/30/2025
- Issuing Office
- Current Status
- Issued on 1/30/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/11/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/4/2024 | MARVEL DELACRUZ |
| Corrections Issued | 1/11/2024 | MARVEL DELACRUZ |
| Quality Review Completed | 1/17/2024 | OMID HEDAYAT |
| Applicant returned to address corrections | 10/9/2024 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 10/11/2024 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 12/5/2024 | MARVEL DELACRUZ |
| Plan Check Approved | 12/26/2024 | MARVEL DELACRUZ |
| Plan Check Approved | 1/3/2025 | MARVEL DELACRUZ |
| Issued | 1/30/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/25/2024 | BRENDEN HAWK |
| BHO/Hillside ordinance | Cleared | 1/25/2024 | BRENDEN HAWK |
| BHO/Hillside ordinance | Cleared | 1/25/2024 | BRENDEN HAWK |
| BHO/Hillside ordinance | Cleared | 1/25/2024 | BRENDEN HAWK |
| BHO/Hillside ordinance | Cleared | 1/25/2024 | BRENDEN HAWK |
| BHO/Hillside ordinance | Cleared | 1/25/2024 | BRENDEN HAWK |
| Eng Process Fee Ord 176,300 | Cleared | 1/29/2024 | BRENDEN HAWK |
| Sewer availability | Cleared | 2/8/2024 | BRENDEN HAWK |
| Distance to fire station | Cleared | 3/9/2024 | KURT CORRAL |
| Hydrant and Access approval | Cleared | 3/9/2024 | KURT CORRAL |
| Coastal Zone | Cleared | 9/23/2024 | MATHEW QUAN |
| Miscellaneous | Cleared | 9/23/2024 | MATHEW QUAN |
| ZI | Cleared | 9/23/2024 | MATHEW QUAN |
| Trees in Parkway | Cleared | 11/5/2024 | MIGUEL ORNELAS |
| Low Impact Development (LID) | Cleared | 11/17/2024 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 11/24/2024 | LIAM ODONOVAN |
| GPI Written Notices | Cleared | 12/26/2024 | MARVEL DELACRUZ |
| Grading Pre-Inspection | Cleared | 12/26/2024 | MARVEL DELACRUZ |
Contact Information
| Architect | Wilkinson,, Clive Robert; Lic. No.: NA23671 | , |
| Contractor | Danbuilt/Color Blind Design; Lic. No.: 1086691-B | , |
| Contractor | Danbuilt; Lic. No.: 1086691-B | , |
| Engineer | Baad,, Katherine Firestone; Lic. No.: C64669 | 5232 ZAKON RD TORRANCE, CA 90505 |
| Engineer | Daneshfar,, Kourosh Dan; Lic. No.: C68377 | 19722 ARMINTA ST WINNETKA, CA 91306 |
| Engineer | Echeverria,, Andres; Lic. No.: C89926 | 18142 ARMINTA ST RESEDA, CA 91335 |
| Engineer | Varela,, Benjamin; Lic. No.: S5714 | 6007 WASHINGTON BLVD CULVER CITY, CA 90232 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 4/10/2025 | No Access for Inspection | MEL KHACHATOURIAN |
| Deputy Reinf. Concrete | 4/14/2025 | Conditional Approval | HERBERT GIRON |
| Excavation/Setback/Form/Re-Bar | 5/6/2025 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 5/6/2025 | Corrections Issued | HERBERT GIRON |
| Excavation/Setback/Form/Re-Bar | 5/16/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 5/16/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 5/20/2025 | Not Ready for Inspection | HERBERT GIRON |
| Footing/Foundation/Slab | 5/22/2025 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 5/23/2025 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 5/23/2025 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 6/9/2025 | Partial Approval | HERBERT GIRON |
| PLUMBING-Rough | 6/9/2025 | Partial Inspection | HERBERT GIRON |
| PLUMBING-Rough | 6/13/2025 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 7/3/2025 | Partial Approval | HERBERT GIRON |
| Deputy Reinf. Concrete | 7/7/2025 | Conditional Approval | HERBERT GIRON |
| Deputy Reinf. Concrete | 7/8/2025 | Conditional Approval | HERBERT GIRON |
| Deputy Reinf. Concrete | 12/22/2025 | Conditional Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/29/2026 | Partial Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2026 | Not Ready for Inspection | HERBERT GIRON |
| Footing/Foundation/Slab | 2/4/2026 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 2/10/2026 | Partial Approval | HERBERT GIRON |
| Deputy Wood Construction | 2/13/2026 | Conditional Approval | JUAN VALENZUELA |
| Deputy Wood Construction | 2/20/2026 | Conditional Approval | JUAN VALENZUELA |
| Deputy Wood Construction | 2/23/2026 | Conditional Approval | JUAN VALENZUELA |