1522 W 98TH ST 90047

Certificate Information: 1522 W 98TH ST 90047

Application / Permit
23010-10000-04945
Plan Check / Job No.
B23LA23293
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: (N) 1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
Permit Issued
Issued on 6/6/2024
Issuing Office
Current Status
CofO Issued on 1/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/11/2023 APPLICANT
Assigned to Plan Check Engineer 12/14/2023 LUISANGEL VALENZUELA
Corrections Issued 12/14/2023 LUISANGEL VALENZUELA
Applicant returned to address corrections 5/21/2024 LUISANGEL VALENZUELA
Applicant returned to address corrections 5/29/2024 DANIEL YIP
Plan Check Approved 6/3/2024 DANIEL YIP
Issued 6/6/2024 APPLICANT
CofO in Progress 1/27/2025 MICHAEL LEWIS
Permit Finaled 1/27/2025 DEROLD HAUFF
CofO Issued 1/27/2025 DEROLD HAUFF
Permit Finaled 1/27/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/7/2024 JEANIE LAM
Roof/Waste drainage to street Cleared 3/7/2024 JEANIE LAM
Construction near power lines Cleared 4/24/2024 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 5/20/2024 JEANIE LAM
Sewer availability Cleared 5/20/2024 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Gonzalez,, Daniel; Lic. No.: NA87405       ,

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/6/2024 Corrections Issued AMIR NAZARIAN
METHANE-Barrier 9/6/2024 Approved AMIR NAZARIAN
METHANE-Subgrade 9/6/2024 Approved AMIR NAZARIAN
Excavation/Setback/Form/Re-Bar 9/23/2024 Approved AMIR NAZARIAN
BUILDING-Rough-Frame 9/27/2024 Not Ready for Inspection AMIR NAZARIAN
METHANE-Rough 9/27/2024 Approved AMIR NAZARIAN
PLUMBING-Rough 9/27/2024 Partial Approval AMIR NAZARIAN
Verify Sprinkler Sign Off 9/27/2024 Not Ready for Inspection AMIR NAZARIAN
Floor/Roof Diaphrgm/Shear Wall 9/30/2024 Corrections Issued AMIR NAZARIAN
Underground Mechanical 10/18/2024 Not Ready for Inspection JOSE MACIAS
Floor/Roof Diaphrgm/Shear Wall 10/23/2024 Approved JOSE MACIAS
Interior/Exterior Lathing 10/30/2024 Approved JOSE MACIAS
PLUMBING-Rough 10/30/2024 Approved JOSE MACIAS
ELECTRICAL-Rough 11/8/2024 Corrections Issued AMIR NAZARIAN
ELECTRICAL-Rough 11/13/2024 Approved AMIR NAZARIAN
Floor/Roof Diaphrgm/Shear Wall 11/13/2024 Approved AMIR NAZARIAN
HVAC-Rough 11/13/2024 Conditional Approval AMIR NAZARIAN
PLUMBING-Rough 11/13/2024 Conditional Approval AMIR NAZARIAN
BUILDING-Rough-Frame 11/19/2024 Approved ALEX COLIN
Insulation 11/19/2024 Approved ALEX COLIN
Verify Sprinkler Sign Off 11/19/2024 Approved ALEX COLIN
Drywall Nailing 11/22/2024 Approved ALEX COLIN
Final 12/17/2024 Corrections Issued MICHAEL LEWIS
Footing/Foundation/Slab 12/17/2024 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 12/17/2024 SGSOV Not Required MICHAEL LEWIS
Service/Power Release 12/17/2024 Corrections Issued MICHAEL LEWIS
Smoke Detectors 12/17/2024 Corrections Issued MICHAEL LEWIS
Final 12/23/2024 Corrections Issued AMIR NAZARIAN
Service/Power Release 12/23/2024 Not Ready for Inspection AMIR NAZARIAN
Smoke Detectors 12/23/2024 Not Ready for Inspection AMIR NAZARIAN
Final 12/26/2024 Corrections Issued AMIR NAZARIAN
Service/Power Release 12/26/2024 Not Ready for Inspection AMIR NAZARIAN
Smoke Detectors 12/26/2024 Approved AMIR NAZARIAN
Final 1/24/2025 OK to Issue CofO MICHAEL LEWIS
Service/Power Release 1/24/2025 Approved MICHAEL LEWIS