2207 W 20TH ST 90018

Certificate Information: 2207 W 20TH ST 90018

Application / Permit
23010-10000-04904
Plan Check / Job No.
B23LA23134
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 1-STORY (41'-0"x49'-0"), 1200 SQFT ACCESSORY DWELLING UNIT W/ATTACHED 2-CAR GARAGE (400 SQFT) PER LAMC 12.22 A.33(c)(d). ALL ELECTRIC BUILDING
Permit Issued
Issued on 8/13/2024
Issuing Office
Current Status
CofO Issued on 12/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/24/2024 APPLICANT
Assigned to Plan Check Engineer 2/8/2024 PETER MOSESIAN
Corrections Issued 2/14/2024 PETER MOSESIAN
Quality Review Completed 2/16/2024 OMID HEDAYAT
Plan Check Approved 5/7/2024 PETER MOSESIAN
Issued 8/13/2024 APPLICANT
CofO in Progress 12/22/2025 WILLIAM SIERRA
Permit Finaled 12/23/2025 DEROLD HAUFF
CofO Issued 12/23/2025 DEROLD HAUFF
Permit Finaled 12/23/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/20/2024 JUSTIN BICOL
Eng Process Fee Ord 176,300 Cleared 2/20/2024 JUSTIN BICOL
HPOZ Cleared 2/20/2024 ERIK VAN BREENE
Sewer availability Cleared 2/20/2024 JUSTIN BICOL
ZA Case Cleared 2/20/2024 ERIK VAN BREENE
ZA Case Cleared 2/20/2024 ERIK VAN BREENE
ZI Cleared 2/20/2024 ERIK VAN BREENE
Construction near power lines Cleared 3/15/2024 JOSHUA MARTIN
Low Impact Development (LID) Cleared 5/1/2024 MITESH PATEL
Roof/Waste drainage to street Cleared 5/3/2024 CELINA MORENO

Contact Information

Contractor Mrod Construction Services; Lic. No.: 1000636-B       ,
Engineer Castillo,, Margarito; Lic. No.: S4808 1205 PINE AVE   SUITE 201    LONG BEACH, CA 90813

Inspector Information

WILLIAM SIERRA, (213) 202-3122 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 9/25/2024 Approved WILLIAM SIERRA
Excavation/Setback/Form/Re-Bar 10/9/2024 Partial Approval WILLIAM SIERRA
METHANE-Barrier 10/9/2024 Not Ready for Inspection WILLIAM SIERRA
METHANE-Subgrade 10/9/2024 Not Ready for Inspection WILLIAM SIERRA
Sewer 10/9/2024 Approved WILLIAM SIERRA
Footing/Foundation/Slab 11/26/2024 Not Ready for Inspection WILLIAM SIERRA
METHANE-Barrier 11/26/2024 Not Ready for Inspection WILLIAM SIERRA
METHANE-Subgrade 11/26/2024 Approved WILLIAM SIERRA
Footing/Foundation/Slab 12/6/2024 Partial Approval WILLIAM SIERRA
METHANE-Rough 12/6/2024 Approved WILLIAM SIERRA
Footing/Foundation/Slab 1/7/2025 Partial Inspection FREDDIE RIVERA
METHANE-Barrier 1/7/2025 Approved FREDDIE RIVERA
Footing/Foundation/Slab 1/10/2025 Approved WILLIAM SIERRA
Special/Order Compliance 1/10/2025 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 2/28/2025 Not Ready for Inspection WILLIAM SIERRA
ELECTRICAL-Rough 2/28/2025 Corrections Issued WILLIAM SIERRA
HVAC-Rough 2/28/2025 Not Ready for Inspection WILLIAM SIERRA
MERV13>=Rough 2/28/2025 Not Ready for Inspection WILLIAM SIERRA
PLUMBING-Rough 2/28/2025 Not Ready for Inspection WILLIAM SIERRA
Verify Sprinkler Sign Off 2/28/2025 Approved WILLIAM SIERRA
Deputy Wood Construction 3/3/2025 No Result Entered WILLIAM KUEHN
BUILDING-Rough-Frame 3/4/2025 Not Ready for Inspection WILLIAM SIERRA
ELECTRICAL-Rough 3/4/2025 Approved WILLIAM SIERRA
Floor/Roof Diaphrgm/Shear Wall 3/4/2025 Approved WILLIAM SIERRA
MERV13>=Rough 3/4/2025 Not Ready for Inspection WILLIAM SIERRA
PLUMBING-Rough 3/4/2025 Corrections Issued WILLIAM SIERRA
BUILDING-Rough-Frame 3/17/2025 Corrections Issued NICHOLAS LOPEZ
Green Building Rough 3/17/2025 Not Ready for Inspection NICHOLAS LOPEZ
PLUMBING-Rough 3/17/2025 Approved NICHOLAS LOPEZ
BUILDING-Rough-Frame 4/1/2025 Corrections Issued WILLIAM SIERRA
Interior/Exterior Lathing 4/1/2025 Partial Approval WILLIAM SIERRA
MERV13>=Rough 4/1/2025 Approved WILLIAM SIERRA
BUILDING-Rough-Frame 4/7/2025 Corrections Issued WILLIAM SIERRA
HVAC-Rough 4/7/2025 Corrections Issued WILLIAM SIERRA
BUILDING-Rough-Frame 4/11/2025 Approved WILLIAM SIERRA
HVAC-Rough 4/11/2025 Approved WILLIAM SIERRA
Insulation 4/11/2025 Approved WILLIAM SIERRA
Drywall Nailing 4/25/2025 Approved WILLIAM SIERRA
Interior/Exterior Lathing 4/25/2025 Approved WILLIAM SIERRA
Pre-Inspection 5/8/2025 Partial Inspection WILLIAM SIERRA
Final 7/11/2025 No Access for Inspection ALIZAH MAYAGOITIA
MERV13>=Final 7/11/2025 No Access for Inspection ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 7/11/2025 SGSOV Not Ready ALIZAH MAYAGOITIA
Service/Power Release 7/11/2025 No Access for Inspection ALIZAH MAYAGOITIA
Smoke Detectors 7/11/2025 No Access for Inspection ALIZAH MAYAGOITIA
Final 9/23/2025 Corrections Issued WILLIAM SIERRA
MERV13>=Final 9/23/2025 Approved WILLIAM SIERRA
SGSOV-Seismic Gas S/O Valve 9/23/2025 SGSOV Not Required WILLIAM SIERRA
Service/Power Release 9/23/2025 Not Ready for Inspection WILLIAM SIERRA
Smoke Detectors 9/23/2025 Approved WILLIAM SIERRA
Pre-Inspection 10/29/2025 Partial Inspection WILLIAM SIERRA
Final 12/15/2025 Corrections Issued WILLIAM SIERRA
Service/Power Release 12/15/2025 Not Required WILLIAM SIERRA
Final 12/22/2025 OK to Issue CofO WILLIAM SIERRA