2267 W 29TH PL 90018
Certificate Information: 2267 W 29TH PL 90018
- Application / Permit
- 23010-10000-04898
- Plan Check / Job No.
- B23LA23077
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- NEW 14' X 20' DETACHED GARAGE WITH ATTIC SPACE ABOVE. WORK DONE PER ENGINEER DESIGN.
- Permit Issued
- Issued on 2/28/2025
- Issuing Office
- Current Status
- CofO Issued on 1/5/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/7/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/11/2023 | MADISON ODELL |
| Corrections Issued | 12/12/2023 | MADISON ODELL |
| Applicant returned to address corrections | 11/26/2024 | MADISON ODELL |
| Applicant returned to address corrections | 1/24/2025 | MADISON ODELL |
| Plan Check Approved | 2/17/2025 | MADISON O'DELL |
| Issued | 2/28/2025 | APPLICANT |
| CofO in Progress | 1/5/2026 | SABAS ALONSO |
| Permit Finaled | 1/5/2026 | DEROLD HAUFF |
| CofO Issued | 1/5/2026 | DEROLD HAUFF |
| Permit Finaled | 1/5/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 3/22/2024 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/26/2024 | DAVID LOPEZ |
| Construction near power lines | Cleared | 8/4/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 8/4/2024 | RIDWAN HARDY |
| HPOZ | Cleared | 8/16/2024 | DANIEL MATA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/27/2025 | Not Ready for Inspection | SABAS ALONSO |
| METHANE-Barrier | 6/27/2025 | Not Ready for Inspection | SABAS ALONSO |
| METHANE-Subgrade | 6/27/2025 | Not Ready for Inspection | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 8/1/2025 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 8/1/2025 | Not Ready for Inspection | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 9/5/2025 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Rough | 9/18/2025 | Not Ready for Inspection | SABAS ALONSO |
| Interior/Exterior Lathing | 9/18/2025 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 10/3/2025 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Rough | 10/3/2025 | Approved | BRENDAN MORELLI |
| METHANE-Rough | 10/3/2025 | Approved | BRENDAN MORELLI |
| Final | 12/19/2025 | Not Ready for Inspection | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 12/19/2025 | SGSOV Not Ready | SABAS ALONSO |
| Smoke Detectors | 12/19/2025 | Approved | SABAS ALONSO |
| Final | 12/30/2025 | OK to Issue CofO | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 12/30/2025 | SGSOV Approved | SABAS ALONSO |
| Service/Power Release | 12/30/2025 | Not Ready for Inspection | SABAS ALONSO |