2267 W 29TH PL 90018

Certificate Information: 2267 W 29TH PL 90018

Application / Permit
23010-10000-04898
Plan Check / Job No.
B23LA23077
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
NEW 14' X 20' DETACHED GARAGE WITH ATTIC SPACE ABOVE. WORK DONE PER ENGINEER DESIGN.
Permit Issued
Issued on 2/28/2025
Issuing Office
Current Status
CofO Issued on 1/5/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/7/2023 APPLICANT
Assigned to Plan Check Engineer 12/11/2023 MADISON ODELL
Corrections Issued 12/12/2023 MADISON ODELL
Applicant returned to address corrections 11/26/2024 MADISON ODELL
Applicant returned to address corrections 1/24/2025 MADISON ODELL
Plan Check Approved 2/17/2025 MADISON O'DELL
Issued 2/28/2025 APPLICANT
CofO in Progress 1/5/2026 SABAS ALONSO
Permit Finaled 1/5/2026 DEROLD HAUFF
CofO Issued 1/5/2026 DEROLD HAUFF
Permit Finaled 1/5/2026 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/22/2024 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 3/26/2024 DAVID LOPEZ
Construction near power lines Cleared 8/4/2024 RIDWAN HARDY
Construction within easement Cleared 8/4/2024 RIDWAN HARDY
HPOZ Cleared 8/16/2024 DANIEL MATA

Contact Information

Contractor Owner-Builder       ,
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/27/2025 Not Ready for Inspection SABAS ALONSO
METHANE-Barrier 6/27/2025 Not Ready for Inspection SABAS ALONSO
METHANE-Subgrade 6/27/2025 Not Ready for Inspection SABAS ALONSO
Excavation/Setback/Form/Re-Bar 8/1/2025 Approved SABAS ALONSO
Footing/Foundation/Slab 8/1/2025 Not Ready for Inspection SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 9/5/2025 Corrections Issued SABAS ALONSO
ELECTRICAL-Rough 9/18/2025 Not Ready for Inspection SABAS ALONSO
Interior/Exterior Lathing 9/18/2025 Approved SABAS ALONSO
BUILDING-Rough-Frame 10/3/2025 Approved BRENDAN MORELLI
ELECTRICAL-Rough 10/3/2025 Approved BRENDAN MORELLI
METHANE-Rough 10/3/2025 Approved BRENDAN MORELLI
Final 12/19/2025 Not Ready for Inspection SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 12/19/2025 SGSOV Not Ready SABAS ALONSO
Smoke Detectors 12/19/2025 Approved SABAS ALONSO
Final 12/30/2025 OK to Issue CofO SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 12/30/2025 SGSOV Approved SABAS ALONSO
Service/Power Release 12/30/2025 Not Ready for Inspection SABAS ALONSO