14254-14256 W MCCORMICK ST 91401

Certificate Information: 14254-14256 W MCCORMICK ST 91401

Application / Permit
23010-10000-04887
Plan Check / Job No.
B23LA22965
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan. New two-story single family dwelling with attached garage and attached ADU per LAMC 12.22 A.33(c) and (e)
Permit Issued
Issued on 9/19/2024
Issuing Office
Current Status
CofO in Progress on 7/17/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/6/2023 APPLICANT
Assigned to Plan Check Engineer 12/7/2023 GEORGE JOLAKIAN
Corrections Issued 12/14/2023 GEORGE JOLAKIAN
Quality Review Completed 12/19/2023 RODOLFO ARIAS
Plan Check Approved 9/13/2024 GEORGE JOLAKIAN
Issued 9/19/2024 APPLICANT
CofO in Progress 7/17/2026 VINCENT HANLEY

Permit Application Clearance Information

Address approval Cleared 1/5/2024 CARLOS AGUILERA
Address approval Cleared 1/5/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 1/16/2024 CARLOS AGUILERA
Sewer availability Cleared 1/16/2024 CARLOS AGUILERA
Hydrant and Access approval Cleared 2/5/2024 JOHN CONNEALLY
Trees in Parkway Cleared 2/8/2024 ADALBERTO VERA
Permit Cleared 6/12/2024 CARLOS AGUILERA
Low Impact Development (LID) Cleared 8/21/2024 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 8/22/2024 RYAN CASTRO
Construction near power lines Cleared 9/3/2024 ENRIQUE ACOSTA

Contact Information

Contractor Owner-Builder       ,
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/4/2024 Approved RYAN SALAZAR
Sewer 10/23/2024 Corrections Issued MATTHEW NELSON
PLUMBING-Rough 10/28/2024 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 12/27/2024 Partial Approval RYAN SALAZAR
ELECTRICAL-Rough 1/30/2025 Not Ready for Inspection KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 1/30/2025 Corrections Issued KEVIN BERBERYAN
HVAC-Rough 1/30/2025 Not Ready for Inspection KEVIN BERBERYAN
PLUMBING-Rough 1/30/2025 Partial Approval KEVIN BERBERYAN
ELECTRICAL-Rough 2/6/2025 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 2/6/2025 Approved RYAN SALAZAR
HVAC-Rough 2/6/2025 Approved RYAN SALAZAR
PLUMBING-Rough 2/6/2025 Conditional Approval RYAN SALAZAR
BUILDING-Rough-Frame 2/27/2025 Approved RYAN SALAZAR
Green Building Rough 2/27/2025 Approved RYAN SALAZAR
Insulation 2/27/2025 Approved RYAN SALAZAR
Verify Sprinkler Sign Off 2/27/2025 Approved RYAN SALAZAR
Shower Pan 3/6/2025 Approved RYAN SALAZAR
PLUMBING-Final 8/7/2025 Approved RYAN SALAZAR
ELECTRICAL-Final 8/8/2025 Not Ready for Inspection RYAN SALAZAR
Drywall Nailing 9/19/2025 Approved RYAN SALAZAR
ELECTRICAL-Final 9/19/2025 Not Ready for Inspection RYAN SALAZAR
Final 9/19/2025 Corrections Issued RYAN SALAZAR
Green Building Final 9/19/2025 Approved RYAN SALAZAR
HVAC-Final 9/19/2025 Approved RYAN SALAZAR
PLUMBING-Final 9/19/2025 Not Ready for Inspection RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 9/19/2025 SGSOV Not Required RYAN SALAZAR
Service/Power Release 9/19/2025 Not Ready for Inspection RYAN SALAZAR
Smoke Detectors 9/19/2025 Approved RYAN SALAZAR
ELECTRICAL-Final 5/21/2026 Corrections Issued VINCENT HANLEY
ELECTRICAL-Final 6/11/2026 No Access for Inspection VINCENT HANLEY
Final 6/11/2026 No Access for Inspection VINCENT HANLEY
Service/Power Release 6/11/2026 No Access for Inspection VINCENT HANLEY
ELECTRICAL-Final 6/16/2026 Approved VINCENT HANLEY
Final 6/16/2026 Corrections Issued VINCENT HANLEY
HVAC-Final 6/16/2026 Approved VINCENT HANLEY
PLUMBING-Final 6/16/2026 Approved VINCENT HANLEY
Service/Power Release 6/16/2026 Approved VINCENT HANLEY
Final 7/16/2026 OK to Issue CofO VINCENT HANLEY