414 W 103RD ST 90003
Certificate Information: 414 W 103RD ST 90003
- Application / Permit
- 23010-10000-04883
- Plan Check / Job No.
- B23LA22945
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- EPLAN (N) 1-STORY ONE CAR GARAGE / STORAGE/ LAUNDRY 453 sq.ft. AND (N) PATIO COVER 400 sq.ft.
- Permit Issued
- Issued on 9/19/2024
- Issuing Office
- Current Status
- CofO Issued on 2/20/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/8/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/13/2023 | KHUONG TRUONG |
| Corrections Issued | 12/14/2023 | KHUONG TRUONG |
| Applicant returned to address corrections | 2/20/2024 | KHUONG TRUONG |
| Plan Check Approved | 9/5/2024 | SAMUEL GONZALEZ |
| Issued | 9/19/2024 | APPLICANT |
| CofO in Progress | 2/18/2026 | JOSEPH MCGARRY |
| Permit Finaled | 2/20/2026 | ANSON MAGLASANG |
| Permit Finaled | 2/20/2026 | ANSON MAGLASANG |
| CofO Issued | 2/20/2026 | ANSON MAGLASANG |
Permit Application Clearance Information
| Construction near power lines | Cleared | 4/11/2024 | RIDWAN HARDY |
| Low Impact Development (LID) | Cleared | 8/16/2024 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 8/21/2024 | WALLIE JONG |
| Sewer availability | Cleared | 8/21/2024 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 9/3/2024 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ramirez, Cid, Jose Carlos; Lic. No.: C91046 | 5164 N RATON CIR LONG BEACH, CA 90807 |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/18/2025 | Approved | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 6/6/2025 | Partial Approval | BEN MOLSTAD |
| Wood Frame | 6/6/2025 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Rough | 6/9/2025 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Rough | 6/9/2025 | Corrections Issued | BEN MOLSTAD |
| Wood Frame | 6/9/2025 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Rough | 6/20/2025 | Approved | ANTHONY EGSON |
| Insulation | 6/20/2025 | Partial Approval | ANTHONY EGSON |
| PLUMBING-Rough | 6/20/2025 | Partial Approval | ANTHONY EGSON |
| Underground Mechanical | 6/20/2025 | Partial Approval | ANTHONY EGSON |
| Insulation | 6/25/2025 | Approved | BEN MOLSTAD |
| Drywall Nailing | 7/10/2025 | Approved | BEN MOLSTAD |
| BUILDING-Rough-Frame | 8/4/2025 | Approved | BEN MOLSTAD |
| Final | 8/4/2025 | Corrections Issued | BEN MOLSTAD |
| MERV13>=Final | 8/4/2025 | Not Ready for Inspection | BEN MOLSTAD |
| MERV13>=Rough | 8/4/2025 | Approved | BEN MOLSTAD |
| PLUMBING-Final | 8/4/2025 | Not Ready for Inspection | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 8/4/2025 | SGSOV Not Ready | BEN MOLSTAD |
| Service/Power Release | 8/4/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Smoke Detectors | 8/4/2025 | Corrections Issued | BEN MOLSTAD |
| ELECTRICAL-Final | 8/5/2025 | Corrections Issued | BEN MOLSTAD |
| Final | 2/17/2026 | OK to Issue CofO | JOSEPH MCGARRY |
| MERV13>=Final | 2/17/2026 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 2/17/2026 | SGSOV Approved | JOSEPH MCGARRY |
| Service/Power Release | 2/17/2026 | Not Required | JOSEPH MCGARRY |
| Smoke Detectors | 2/17/2026 | Approved | JOSEPH MCGARRY |