653 1/2-655 1/2 E 43RD PL 90011
Certificate Information: 653 1/2-655 1/2 E 43RD PL 90011
- Application / Permit
- 23010-10000-04864
- Plan Check / Job No.
- B23LA22883
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 2-STORY 2-UNIT ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(D) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 2/2/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/25/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/5/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/7/2023 | DANIEL YIP |
| Corrections Issued | 12/13/2023 | DANIEL YIP |
| Quality Review Completed | 12/15/2023 | KEN GILL |
| Building Plans Picked Up | 12/18/2023 | APPLICANT |
| Applicant returned to address corrections | 1/29/2024 | DANIEL YIP |
| Plan Check Approved | 1/31/2024 | DANIEL YIP |
| Issued | 2/2/2024 | APPLICANT |
| CofO in Progress | 9/20/2024 | SABAS ALONSO |
| Permit Finaled | 9/25/2024 | RUBEN SALAS |
| Permit Finaled | 9/25/2024 | RUBEN SALAS |
| CofO Issued | 9/25/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/18/2023 | JUSTIN BICOL |
| Sewer availability | Cleared | 12/18/2023 | JUSTIN BICOL |
| Low Impact Development (LID) | Cleared | 1/11/2024 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 1/13/2024 | ADRIAN SANCHEZ |
| Address approval | Cleared | 1/30/2024 | JUSTIN BICOL |
Contact Information
| Contractor | So Cal Construction Enterprises Inc; Lic. No.: 832488-B | P O BOX 96 SAN GABRIEL, CA 91778 |
| Engineer | Evangelista,, Gil Viernes; Lic. No.: S2422 | 749 N FEATHERWOOD DR DIAMOND BAR, CA 91765 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 2/9/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 2/12/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 2/12/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 2/15/2024 | Approved | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 2/15/2024 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 2/15/2024 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2024 | Partial Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 3/14/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 3/18/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 3/18/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 3/19/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 3/19/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 3/19/2024 | Approved | ALEJANDRO DE ARTOLA |
| Wood Frame | 3/19/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 3/20/2024 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 3/21/2024 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 3/21/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 3/21/2024 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 3/21/2024 | Approved | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 3/21/2024 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 3/22/2024 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 3/22/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 3/26/2024 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 3/26/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Sewer | 4/3/2024 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 5/30/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 5/30/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 5/30/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 5/30/2024 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 5/30/2024 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Final | 6/12/2024 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 6/12/2024 | Not Ready for Inspection | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 6/12/2024 | SGSOV Not Required | ANTHONY EGSON |
| Service/Power Release | 6/12/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Smoke Detectors | 6/12/2024 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 6/18/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 6/18/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 6/18/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 6/26/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 6/26/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 6/26/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 6/26/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 6/26/2024 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 6/26/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 7/26/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Service/Power Release | 7/26/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 8/28/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 8/28/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 8/28/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 9/13/2024 | Corrections Issued | WILLIAM SIERRA |
| Green Building Final | 9/13/2024 | Approved | WILLIAM SIERRA |
| Final | 9/19/2024 | OK to Issue CofO | SABAS ALONSO |