2116 W 27TH ST 90018
Certificate Information: 2116 W 27TH ST 90018
- Application / Permit
- 23010-10000-04862
- Plan Check / Job No.
- B23LA22880
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT WITH ATTACHED GARAGE AND PATIO COVER PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 6/6/2024
- Issuing Office
- Current Status
- Issued on 6/6/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/5/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/21/2023 | CARLOS MONTES |
| Corrections Issued | 12/24/2023 | CARLOS MONTES |
| Quality Review Completed | 1/4/2024 | PRANITA SHAH |
| Applicant returned to address corrections | 3/29/2024 | CARLOS MONTES |
| Plan Check Approved | 5/2/2024 | CARLOS MONTES |
| Issued | 6/6/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/5/2024 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 1/9/2024 | JUSTIN BICOL |
| Sewer availability | Cleared | 1/9/2024 | JUSTIN BICOL |
| HPOZ | Cleared | 1/10/2024 | DANIEL MATA |
| Historic monument | Cleared | 1/10/2024 | DANIEL MATA |
| Low Impact Development (LID) | Cleared | 2/20/2024 | LUIS CRUZ |
| Roof/Waste drainage to street | Cleared | 2/21/2024 | JUSTIN BICOL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Samadzadeh,, Hooman Ali; Lic. No.: NA87661 | , |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/16/2024 | Partial Approval | SABAS ALONSO |
| Sewer | 7/16/2024 | Approved | SABAS ALONSO |
| Underground Mechanical | 7/16/2024 | Partial Approval | SABAS ALONSO |
| METHANE-Subgrade | 7/31/2024 | Approved | SABAS ALONSO |
| Deputy Methane Barrier | 8/7/2024 | Conditional Approval | ALEJANDRO DE ARTOLA |
| METHANE-Barrier | 8/8/2024 | Approved | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 8/14/2024 | Corrections Issued | MICHAEL LEWIS |
| Footing/Foundation/Slab | 8/16/2024 | Partial Approval | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 9/11/2024 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Rough | 9/11/2024 | Not Ready for Inspection | SABAS ALONSO |
| METHANE-Rough | 9/11/2024 | Not Ready for Inspection | SABAS ALONSO |
| Verify Sprinkler Sign Off | 9/11/2024 | Not Ready for Inspection | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 12/3/2024 | Partial Approval | SABAS ALONSO |
| Deputy Wood Construction | 1/23/2025 | Conditional Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 1/27/2025 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Rough | 1/27/2025 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 3/5/2025 | Corrections Issued | BARRY HACHE |
| HVAC-Rough | 3/5/2025 | No Access for Inspection | BARRY HACHE |
| Shower Pan | 3/5/2025 | No Access for Inspection | BARRY HACHE |
| ELECTRICAL-Rough | 3/6/2025 | Corrections Issued | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2025 | Approved | SABAS ALONSO |
| Green Building Rough | 3/6/2025 | Approved | SABAS ALONSO |
| HVAC-Rough | 3/6/2025 | Not Ready for Inspection | SABAS ALONSO |
| METHANE-Rough | 3/6/2025 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Rough | 5/8/2025 | Approved | SABAS ALONSO |
| HVAC-Rough | 5/8/2025 | Approved | SABAS ALONSO |
| METHANE-Rough | 5/8/2025 | Approved | SABAS ALONSO |
| Shower Pan | 5/8/2025 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 9/2/2025 | Corrections Issued | BARRY HACHE |
| Insulation | 9/9/2025 | Corrections Issued | RONNIE MEDINA |
| BUILDING-Rough-Frame | 9/30/2025 | Conditional Approval | RONNIE MEDINA |
| Insulation | 9/30/2025 | Approved | RONNIE MEDINA |
| Drywall Nailing | 10/21/2025 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 10/21/2025 | Approved | ANTHONY RAMOS |