212 S SALTAIR AVE 90049
Certificate Information: 212 S SALTAIR AVE 90049
- Application / Permit
- 23010-10000-04837
- Plan Check / Job No.
- B23LA22769
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- NEW 15' x 12' DETACHED RECREATION ROOM WORK DONE PER ENGINEER DESIGN.
- Permit Issued
- Issued on 6/10/2024
- Issuing Office
- Current Status
- CofO Issued on 10/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/4/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/8/2023 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 12/11/2023 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 1/11/2024 | GIOVANNY CHAVEZ |
| Applicant returned to address corrections | 2/8/2024 | GIOVANNY CHAVEZ |
| Plan Check Approved | 4/2/2024 | GIOVANNY CHAVEZ |
| Issued | 6/10/2024 | APPLICANT |
| CofO in Progress | 9/25/2025 | HERBERT GIRON |
| Permit Finaled | 10/7/2025 | RICHARD STEINBACH |
| CofO Issued | 10/7/2025 | RICHARD STEINBACH |
| Permit Finaled | 10/7/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/9/2024 | BRENDEN HAWK |
| Sewer availability | Cleared | 1/9/2024 | BRENDEN HAWK |
| Grading Pre-Inspection | Cleared | 1/11/2024 | MIROOSH KHACHATOORIAN |
| Specific Plan | Cleared | 1/11/2024 | ALESSANDRO MERCURI |
| Roof/Waste drainage to street | Cleared | 2/5/2024 | BRENDEN HAWK |
| Miscellaneous | Cleared | 4/2/2024 | GIOVANNY CHAVEZ |
Contact Information
| Contractor | Neos Construction; Lic. No.: 1029695-B | , |
| Engineer | Mccovey-Good,, Michelle Marie; Lic. No.: C65495 | 684 CLARION COURT SAN LUIS OBISPO, CA 93401 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/25/2024 | Corrections Issued | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 7/11/2024 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 8/9/2024 | Partial Approval | ARAM AVEDISIAN |
| Deputy Drilled-In Anchors | 8/19/2024 | Conditional Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2024 | Conditional Approval | JESUS RODRIGUEZ |
| Deputy Wood Construction | 8/26/2024 | Conditional Approval | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 9/5/2024 | Conditional Approval | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 9/5/2024 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/5/2024 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 9/5/2024 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 9/5/2024 | Approved | JESUS RODRIGUEZ |
| Insulation | 9/11/2024 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 9/16/2024 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 7/1/2025 | Approved | HERBERT GIRON |
| Final | 7/1/2025 | Corrections Issued | HERBERT GIRON |
| Green Building Final | 7/1/2025 | Approved | HERBERT GIRON |
| PLUMBING-Final | 7/1/2025 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 7/1/2025 | SGSOV Approved | HERBERT GIRON |
| Smoke Detectors | 7/1/2025 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 9/25/2025 | Approved | HERBERT GIRON |
| Final | 9/25/2025 | OK to Issue CofO | HERBERT GIRON |
| Smoke Detectors | 9/25/2025 | Approved | HERBERT GIRON |