212 S SALTAIR AVE 90049

Certificate Information: 212 S SALTAIR AVE 90049

Application / Permit
23010-10000-04837
Plan Check / Job No.
B23LA22769
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
NEW 15' x 12' DETACHED RECREATION ROOM WORK DONE PER ENGINEER DESIGN.
Permit Issued
Issued on 6/10/2024
Issuing Office
Current Status
CofO Issued on 10/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/4/2023 APPLICANT
Assigned to Plan Check Engineer 12/8/2023 MIROOSH KHACHATOORIAN
Corrections Issued 12/11/2023 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 1/11/2024 GIOVANNY CHAVEZ
Applicant returned to address corrections 2/8/2024 GIOVANNY CHAVEZ
Plan Check Approved 4/2/2024 GIOVANNY CHAVEZ
Issued 6/10/2024 APPLICANT
CofO in Progress 9/25/2025 HERBERT GIRON
Permit Finaled 10/7/2025 RICHARD STEINBACH
CofO Issued 10/7/2025 RICHARD STEINBACH
Permit Finaled 10/7/2025 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/9/2024 BRENDEN HAWK
Sewer availability Cleared 1/9/2024 BRENDEN HAWK
Grading Pre-Inspection Cleared 1/11/2024 MIROOSH KHACHATOORIAN
Specific Plan Cleared 1/11/2024 ALESSANDRO MERCURI
Roof/Waste drainage to street Cleared 2/5/2024 BRENDEN HAWK
Miscellaneous Cleared 4/2/2024 GIOVANNY CHAVEZ

Contact Information

Contractor Neos Construction; Lic. No.: 1029695-B       ,
Engineer Mccovey-Good,, Michelle Marie; Lic. No.: C65495 684 CLARION COURT      SAN LUIS OBISPO, CA 93401

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/25/2024 Corrections Issued ARAM AVEDISIAN
Footing/Foundation/Slab 7/11/2024 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 8/9/2024 Partial Approval ARAM AVEDISIAN
Deputy Drilled-In Anchors 8/19/2024 Conditional Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 8/22/2024 Conditional Approval JESUS RODRIGUEZ
Deputy Wood Construction 8/26/2024 Conditional Approval JESUS RODRIGUEZ
BUILDING-Rough-Frame 9/5/2024 Conditional Approval JESUS RODRIGUEZ
ELECTRICAL-Rough 9/5/2024 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 9/5/2024 Approved JESUS RODRIGUEZ
Green Building Rough 9/5/2024 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 9/5/2024 Approved JESUS RODRIGUEZ
Insulation 9/11/2024 Approved JESUS RODRIGUEZ
Drywall Nailing 9/16/2024 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 7/1/2025 Approved HERBERT GIRON
Final 7/1/2025 Corrections Issued HERBERT GIRON
Green Building Final 7/1/2025 Approved HERBERT GIRON
PLUMBING-Final 7/1/2025 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 7/1/2025 SGSOV Approved HERBERT GIRON
Smoke Detectors 7/1/2025 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 9/25/2025 Approved HERBERT GIRON
Final 9/25/2025 OK to Issue CofO HERBERT GIRON
Smoke Detectors 9/25/2025 Approved HERBERT GIRON