1632 1/2 W MIDDLETON PL 90062

Certificate Information: 1632 1/2 W MIDDLETON PL 90062

Application / Permit
23010-10000-04836
Plan Check / Job No.
B23LA22767
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 9/22/2024
Issuing Office
Current Status
Issued on 9/22/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/12/2023 APPLICANT
Assigned to Plan Check Engineer 12/15/2023 OMAR GARNICA
Corrections Issued 12/15/2023 OMAR GARNICA
Applicant returned to address corrections 2/13/2024 KAMYAR EMAMI
Plan Check Approved 9/19/2024 GURUNATH NESARAJAH
Issued 9/22/2024 APPLICANT

Permit Application Clearance Information

Sewer availability Cleared 1/26/2024 JUSTIN BICOL
Address approval Cleared 1/29/2024 JUSTIN BICOL
Eng Process Fee Ord 176,300 Cleared 2/5/2024 JUSTIN BICOL
Hydrant and Access approval Cleared 6/23/2024 KURT CORRAL
Construction near power lines Cleared 8/3/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Mixter,, Thomas J; Lic. No.: C51041 2345 COUNTY RD 630      DEL RIO, TX 78840

Inspector Information

JOHN PARKER, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
MICHAEL SERETTI, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
HECTOR RODRIGUEZ, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
BRUCE TODD, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
JAVIER RAMOS SR, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
MARIAN PODPORA, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/22/2025 No Access for Inspection SABAS ALONSO
Pre-Inspection 10/1/2025 Approved JOHN PARKER
Pre-Inspection 11/7/2025 Corrections Issued JOHN PARKER
Deputy Drilled-In Anchors 12/10/2025 Approved JOHN PARKER
Floor/Roof Diaphrgm/Shear Wall 12/12/2025 Partial Approval JOHN PARKER
Footing/Foundation/Slab 12/12/2025 Approved JOHN PARKER
Underground Mechanical 12/12/2025 Partial Approval JOHN PARKER
BUILDING-Rough-Frame 1/13/2026 Approved JOHN PARKER
ELECTRICAL-Rough 1/13/2026 Approved JOHN PARKER
Floor/Roof Diaphrgm/Shear Wall 1/13/2026 Approved JOHN PARKER
Gas Test 1/13/2026 Approved JOHN PARKER
Green Building Rough 1/13/2026 Approved JOHN PARKER
HVAC-Rough 1/13/2026 Corrections Issued JOHN PARKER
METHANE-Rough 1/13/2026 Approved JOHN PARKER
PLUMBING-Rough 1/13/2026 Approved JOHN PARKER
Sewer 1/13/2026 Approved JOHN PARKER
Shower Pan 1/13/2026 Approved JOHN PARKER
Insulation 1/23/2026 Approved JAVIER RAMOS SR
Drywall Nailing 1/29/2026 Approved JOHN PARKER
Interior/Exterior Lathing 1/29/2026 Approved JOHN PARKER
Gas Test 3/4/2026 Approved JOHN PARKER
Interior/Exterior Lathing 3/4/2026 Approved JOHN PARKER
Underground Mechanical 3/4/2026 Approved JOHN PARKER
Final 6/9/2026 Conditional Approval JOHN PARKER
Green Building Final 6/9/2026 Approved JOHN PARKER
SGSOV-Seismic Gas S/O Valve 6/9/2026 SGSOV Approved JOHN PARKER
Smoke Detectors 6/9/2026 Approved JOHN PARKER