5730 W 83RD ST 90045
Certificate Information: 5730 W 83RD ST 90045
- Application / Permit
- 23010-10000-04830
- Plan Check / Job No.
- B23LA22745
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *eplan* Conversion of existing detached garage with addition to detached accessory dwelling unit per LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 5/27/2026
- Issuing Office
- Current Status
- Issued on 5/27/2026
Permit Application Status History
| Submitted | 12/1/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/14/2023 | ALEXIS VERDUGO |
| Corrections Issued | 1/3/2024 | MINA HABIB |
| Quality Review Completed | 1/12/2024 | RODOLFO ARIAS |
| Applicant returned to address corrections | 4/19/2024 | MINA HABIB |
| Applicant returned to address corrections | 4/22/2024 | MINA HABIB |
| Applicant returned to address corrections | 6/14/2024 | MINA HABIB |
| Applicant returned to address corrections | 8/26/2024 | MINA HABIB |
| Applicant returned to address corrections | 9/24/2024 | MINA HABIB |
| Applicant returned to address corrections | 3/21/2025 | MINA HABIB |
| Applicant returned to address corrections | 3/25/2025 | MINA HABIB |
| Applicant returned to address corrections | 3/26/2025 | MINA HABIB |
| Plan Check Approved | 5/27/2026 | ALEXIS VERDUGO |
| Issued | 5/27/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/3/2024 | KIMBERLY HERNANDEZ |
| Construction near power lines | Cleared | 6/2/2025 | RIDWAN HARDY |
| Construction within easement | Cleared | 6/2/2025 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 1/9/2026 | ABEL CASILLAS |
| Sewer availability | Cleared | 1/9/2026 | ABEL CASILLAS |
| Low Impact Development (LID) | Cleared | 3/9/2026 | JASMIN ASHLEY |
| Hydrant and Access approval | Cleared | 3/18/2026 | PATRICK PEREZ |
| Disturb/Remove Protected Trees | Cleared | 3/26/2026 | MIGUEL ORNELAS |
| Specific Plan | Cleared | 4/8/2026 | PEDRO AYALA |
| Roof/Waste drainage to street | Cleared | 4/18/2026 | JOHN LIN |
| GPI Written Notices | Cleared | 5/27/2026 | MINA HABIB |
| Grading Pre-Inspection | Cleared | 5/27/2026 | MINA HABIB |
Contact Information
| Contractor | Clt Building Inc; Lic. No.: 1110695-B | , |
| Engineer | Zhu,, Yinghui; Lic. No.: C95127 | 2045 GLENDON AVE LOS ANGELES, CA 90025 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Pre-Inspection | 6/16/2026 |
Inspection Request History
| No Data Available. |