1211 1/4 E ADAMS BLVD 90011
Certificate Information: 1211 1/4 E ADAMS BLVD 90011
- Application / Permit
- 23010-10000-04807
- Plan Check / Job No.
- B23LA22632
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 1-STORY ADU per LAMC 12.22 A.33(c)-(d)
- Permit Issued
- Issued on 6/25/2024
- Issuing Office
- South Los Angeles
- Current Status
- CofO Issued on 3/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/30/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/6/2023 | SAMUEL GONZALEZ |
| Corrections Issued | 12/10/2023 | SAMUEL GONZALEZ |
| Building Plans Picked Up | 12/20/2023 | APPLICANT |
| Plan Check Approved | 5/24/2024 | YAQUB MIRZA |
| Issued | 6/25/2024 | APPLICANT |
| CofO in Progress | 3/11/2025 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 3/18/2025 | DEROLD HAUFF |
| CofO Issued | 3/18/2025 | DEROLD HAUFF |
| Permit Finaled | 3/18/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/16/2024 | JESSICA OPINION |
| Roof/Waste drainage to street | Cleared | 2/16/2024 | JESSICA OPINION |
| Eng Process Fee Ord 176,300 | Cleared | 2/26/2024 | JESSICA OPINION |
| Sewer availability | Cleared | 2/26/2024 | JESSICA OPINION |
| "Q" conditions | Cleared | 5/24/2024 | DAVID URITA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/12/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 7/12/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 7/12/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 7/23/2024 | Approved | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 7/23/2024 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 7/23/2024 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 8/19/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Sewer | 8/19/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 8/23/2024 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 8/23/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Sewer | 8/23/2024 | Approved | ALEJANDRO DE ARTOLA |
| Deputy Wood Construction | 8/27/2024 | Conditional Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 8/30/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Green Building Rough | 8/30/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 8/30/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 9/18/2024 | Not Ready for Inspection | WILLIAM SIERRA |
| ELECTRICAL-Rough | 9/18/2024 | Partial Approval | WILLIAM SIERRA |
| Green Building Rough | 9/18/2024 | Approved | WILLIAM SIERRA |
| HVAC-Rough | 9/18/2024 | Corrections Issued | WILLIAM SIERRA |
| Interior/Exterior Lathing | 9/18/2024 | Partial Approval | WILLIAM SIERRA |
| PLUMBING-Rough | 9/18/2024 | Corrections Issued | WILLIAM SIERRA |
| BUILDING-Rough-Frame | 9/20/2024 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 9/20/2024 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 9/20/2024 | Approved | ALEJANDRO DE ARTOLA |
| Gas Test | 10/2/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Insulation | 10/2/2024 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 10/8/2024 | Approved | ALEX COLIN |
| ELECTRICAL-Final | 11/25/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 11/25/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 11/25/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 11/25/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 11/25/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 11/25/2024 | SGSOV Not Required | ALEJANDRO DE ARTOLA |
| Service/Power Release | 11/25/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 11/25/2024 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 2/25/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 2/25/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 2/25/2025 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 2/25/2025 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 2/25/2025 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 2/25/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 3/10/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 3/10/2025 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| Service/Power Release | 3/10/2025 | Approved | ALEJANDRO DE ARTOLA |