1721 S COLBY AVE 90025

Certificate Information: 1721 S COLBY AVE 90025

Application / Permit
23010-10000-04777
Plan Check / Job No.
B23LA22445
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
eplan. NEW 7 STORY WITH ROOF DECK 143 UNITS 100% AFFORDABLE HOUSING APARTMENT TO INCLUDE 5 STORY TYPE IIIA APARTMENT OVER 2 STORY TYPE IA APARTMENT OVER 2 LEVEL SUBTERRANEAN PARKING, PER 12.22.A.25 / AB 1763 INCENTIVES Construction shall not commence without CALOSHA permit
Permit Issued
Issued on 8/1/2025
Issuing Office
West Los Angeles
Current Status
Issued on 8/1/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/29/2023 APPLICANT
Assigned to Zoning Architect 11/30/2023 FRANCIS AHN
Assigned to Plan Check Engineer 12/7/2023 KEVIN MORALES
Corrections Issued 12/19/2023 KEVIN MORALES
Quality Review Completed 12/19/2023 EUGENE BARBEAU
Plan Check Approved 7/1/2025 PRANITA SHAH
Issued 8/1/2025 APPLICANT

Permit Application Clearance Information

Permit Cleared 1/10/2024 BRENDEN HAWK
Highway dedication Cleared 1/12/2024 DINAH GARIN
Hydrant and Access approval Cleared 4/22/2024 LAVEON RIDER
Trees in Parkway Cleared 10/28/2024 ADALBERTO VERA
Low Impact Development (LID) Cleared 10/31/2024 SARAH YOUSSEF
Construction near power lines Cleared 11/21/2024 RIDWAN HARDY
DAS Clearance Cleared 12/13/2024 KEVIN MORALES
Specific Plan Cleared 1/23/2025 JOSHUA JONES
Specific Plan Cleared 1/27/2025 JOSHUA JONES
Address approval Cleared 2/20/2025 HISASHI KOBAYAKAWA
Roof/Waste drainage to street Cleared 4/4/2025 HISASHI KOBAYAKAWA
Fire Marshal Fire Life Safety Cleared 4/18/2025 MENOA AGHAJANI
Density Bonus Cleared 4/25/2025 KEVIN SCHULTZ
SB8 RUD Cleared 4/25/2025 KEVIN SCHULTZ
Demo/Removal of Rental Units Cleared 5/2/2025 EDWARD JACOBS
Miscellaneous Cleared 5/2/2025 DANIEL CORONADO
Miscellaneous Cleared 5/2/2025 DANIEL CORONADO
Miscellaneous Cleared 5/2/2025 DANIEL CORONADO
Miscellaneous Cleared 5/2/2025 DANIEL CORONADO
Work Adjacent to Public Way Cleared 5/5/2025 LIAM ODONOVAN
Eng Process Fee Ord 176,300 Cleared 5/22/2025 HISASHI KOBAYAKAWA
Sewer availability Cleared 5/22/2025 HISASHI KOBAYAKAWA
Green Code Cleared 6/9/2025 KEVIN MORALES
"Q" conditions Cleared 6/16/2025 DANIEL CORONADO
Frnt yard landscape/Water mgmt Cleared 6/16/2025 DANIEL CORONADO
Miscellaneous Cleared 6/16/2025 DANIEL CORONADO
Miscellaneous Cleared 6/16/2025 DANIEL CORONADO
Miscellaneous Cleared 6/16/2025 DANIEL CORONADO
Miscellaneous Cleared 6/16/2025 DANIEL CORONADO
Miscellaneous Cleared 6/16/2025 DANIEL CORONADO
Miscellaneous Cleared 6/16/2025 DANIEL CORONADO
Miscellaneous Cleared 6/16/2025 DANIEL CORONADO
Miscellaneous Cleared 6/16/2025 DANIEL CORONADO
Opn space landscape/Water mgmt Cleared 6/16/2025 DANIEL CORONADO
Zoning Plan Check Cleared 6/18/2025 Eugene Barbeau

Contact Information

Architect Hefner,, Charles David; Lic. No.: C23963 6320 VAN NUYS BOULEVARD #225      VAN NUYS, CA 91401
Contractor P And N Construction Inc; Lic. No.: 800653-B       ,
Engineer Dejban,, Masoud; Lic. No.: S2521 17200 VENTURA BLVD STE 213A      ENCINO, CA 91316
Engineer Haddad,, Raymond M; Lic. No.: GE2985 17106 CEREDO PL      GRANADA HILLS, CA 91344

Inspector Information

DANIEL VARNUM, (310) 914-3914 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Deputy Shotcrete 6/8/2026   

Inspection Request History

Pre-Inspection 8/11/2025 Partial Inspection DANIEL VARNUM
Deputy Other (see comments) 9/24/2025 Conditional Approval DANIEL VARNUM
Deputy Other (see comments) 9/25/2025 Approved DERRICK SPENCER
Deputy Other (see comments) 9/26/2025 Conditional Approval DANIEL VARNUM
Deputy Steel/Welding 9/30/2025 Conditional Approval DANIEL VARNUM
Deputy Steel/Welding 10/1/2025 Conditional Approval DANIEL VARNUM
Deputy Steel/Welding 10/2/2025 Conditional Approval DANIEL VARNUM
Deputy Steel/Welding 10/3/2025 Conditional Approval DANIEL VARNUM
Deputy Steel/Welding 10/6/2025 Conditional Approval DANIEL VARNUM
Deputy Steel/Welding 10/7/2025 Conditional Approval DANIEL VARNUM
Deputy Steel/Welding 10/8/2025 Conditional Approval DANIEL VARNUM
Deputy Reinf. Concrete 12/16/2025 Conditional Approval DANIEL VARNUM
Excavation/Setback/Form/Re-Bar 12/16/2025 Partial Approval DANIEL VARNUM
Deputy Reinf. Concrete 12/17/2025 Approved DERRICK SPENCER
Deputy Reinf. Concrete 12/19/2025 Conditional Approval DANIEL VARNUM
Deputy Shotcrete 12/23/2025 Conditional Approval DANIEL VARNUM
Excavation/Setback/Form/Re-Bar 12/23/2025 Partial Approval DANIEL VARNUM
Deputy Shotcrete 12/24/2025 Conditional Approval DANIEL VARNUM
Deputy Shotcrete 12/26/2025 Conditional Approval DANIEL VARNUM
Deputy Shotcrete 12/29/2025 Conditional Approval DANIEL VARNUM
Deputy Other (see comments) 12/30/2025 Conditional Approval SCOTT SOBEL
Deputy Shotcrete 12/30/2025 Approved DERRICK SPENCER
Deputy Shotcrete 12/31/2025 Conditional Approval DANIEL VARNUM
Deputy Shotcrete 1/2/2026 Conditional Approval DANIEL VARNUM
Deputy Shotcrete 1/5/2026 Conditional Approval DANIEL VARNUM
Green Building Rough 1/7/2026 Not Ready for Inspection DANIEL VARNUM
Reinforced Concrete Frame 1/7/2026 Partial Approval DANIEL VARNUM
Verify Sprinkler Sign Off 1/7/2026 Not Ready for Inspection DANIEL VARNUM
Deputy Shotcrete 1/8/2026 Conditional Approval DANIEL VARNUM
Deputy Reinf. Concrete 1/12/2026 Conditional Approval DANIEL VARNUM
Deputy Reinf. Masonry 1/13/2026 Conditional Approval DANIEL VARNUM
Deputy Reinf. Masonry 1/14/2026 Conditional Approval DANIEL VARNUM
Deputy Shotcrete 1/14/2026 Conditional Approval DANIEL VARNUM
Deputy Reinf. Concrete 1/15/2026 Conditional Approval DANIEL VARNUM
Deputy Reinf. Masonry 1/15/2026 Conditional Approval DANIEL VARNUM
Deputy Shotcrete 1/15/2026 Conditional Approval DANIEL VARNUM
Deputy Reinf. Masonry 1/16/2026 Conditional Approval PAUL DAVIDSON
Pre-Inspection 1/16/2026 Partial Inspection ROGELIO REYNA
Deputy Reinf. Masonry 1/22/2026 Conditional Approval DANIEL VARNUM
Deputy Reinf. Masonry 1/23/2026 Conditional Approval DANIEL VARNUM
Masonry Wall/Backfill 1/23/2026 Partial Approval DANIEL VARNUM
Green Building Rough 2/3/2026 Not Ready for Inspection DANIEL VARNUM
Reinforced Concrete Frame 2/3/2026 Partial Approval DANIEL VARNUM
Verify Sprinkler Sign Off 2/3/2026 Not Ready for Inspection DANIEL VARNUM
Deputy Reinf. Concrete 2/11/2026 Conditional Approval DANIEL VARNUM
Excavation/Setback/Form/Re-Bar 2/11/2026 Partial Approval DANIEL VARNUM
Deputy Reinf. Concrete 2/12/2026 Conditional Approval DANIEL VARNUM
Deputy Reinf. Masonry 2/19/2026 Conditional Approval DANIEL VARNUM
Deputy Reinf. Concrete 3/6/2026 Conditional Approval DANIEL VARNUM
Deputy Reinf. Concrete 3/9/2026 Conditional Approval PAUL DAVIDSON
Deputy Reinf. Concrete 3/12/2026 Conditional Approval DANIEL VARNUM
Excavation/Setback/Form/Re-Bar 3/12/2026 Partial Approval DANIEL VARNUM
Footing/Foundation/Slab 3/12/2026 Partial Approval DANIEL VARNUM
Deputy Reinf. Concrete 3/13/2026 Conditional Approval DANIEL VARNUM
Excavation/Setback/Form/Re-Bar 3/17/2026 Partial Approval DANIEL VARNUM
Deputy Reinf. Concrete 3/19/2026 Conditional Approval DANIEL VARNUM
Deputy Reinf. Masonry 3/24/2026 Conditional Approval DANIEL VARNUM
Deputy Reinf. Masonry 3/25/2026 Conditional Approval DANIEL VARNUM
Masonry Wall/Backfill 3/26/2026 Partial Approval DERRICK SPENCER
Deputy Reinf. Masonry 3/27/2026 Conditional Approval PAUL DAVIDSON
Deputy Reinf. Concrete 4/1/2026 Conditional Approval DANIEL VARNUM
Deputy Reinf. Concrete 4/6/2026 Conditional Approval DANIEL VARNUM
Deputy Reinf. Masonry 4/6/2026 Conditional Approval DANIEL VARNUM
Deputy Reinf. Concrete 4/23/2026 Conditional Approval DANIEL VARNUM
Deputy Reinf. Concrete 4/24/2026 Conditional Approval PAUL DAVIDSON
Excavation/Setback/Form/Re-Bar 4/24/2026 Partial Approval PAUL DAVIDSON
Deputy Reinf. Concrete 4/27/2026 Conditional Approval DANIEL VARNUM
Deputy Reinf. Concrete 4/28/2026 Conditional Approval DANIEL VARNUM
Deputy Reinf. Concrete 4/29/2026 Conditional Approval DANIEL VARNUM
Deputy Reinf. Concrete 4/30/2026 Conditional Approval DANIEL VARNUM
Deputy Reinf. Concrete 5/4/2026 Conditional Approval DANIEL VARNUM
Deputy Reinf. Concrete 5/5/2026 Conditional Approval DANIEL VARNUM
Excavation/Setback/Form/Re-Bar 5/5/2026 Partial Approval DANIEL VARNUM
Deputy Reinf. Concrete 5/8/2026 Conditional Approval PAUL DAVIDSON
Deputy Reinf. Concrete 5/18/2026 Conditional Approval DANIEL VARNUM
Footing/Foundation/Slab 5/18/2026 Partial Approval DANIEL VARNUM
Deputy Reinf. Concrete 5/19/2026 Conditional Approval DANIEL VARNUM
Deputy Reinf. Concrete 5/21/2026 Conditional Approval DANIEL VARNUM
Deputy Shotcrete 5/27/2026 Conditional Approval DANIEL VARNUM
Deputy Shotcrete 5/28/2026 Conditional Approval DANIEL VARNUM
Deputy Shotcrete 5/29/2026 Conditional Approval DANIEL VARNUM
Deputy Shotcrete 6/1/2026 Conditional Approval DANIEL VARNUM
Deputy Shotcrete 6/2/2026 Conditional Approval DANIEL VARNUM
Deputy Shotcrete 6/3/2026 Conditional Approval DANIEL VARNUM
Excavation/Setback/Form/Re-Bar 6/3/2026 Partial Approval DANIEL VARNUM
Deputy Reinf. Concrete 6/4/2026 Conditional Approval DANIEL VARNUM
Deputy Shotcrete 6/4/2026 Conditional Approval DANIEL VARNUM
Excavation/Setback/Form/Re-Bar 6/4/2026 Partial Approval DANIEL VARNUM
Deputy Shotcrete 6/5/2026 Conditional Approval PAUL DAVIDSON