1348 W 222ND ST 90501

Certificate Information: 1348 W 222ND ST 90501

Application / Permit
23010-10000-04769
Plan Check / Job No.
B23LA22406
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan. New detached 2-story Accessory dwelling unit Per lamc 12.22A.33(c)and(d)
Permit Issued
Issued on 4/18/2024
Issuing Office
Current Status
CofO Issued on 2/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/28/2023 APPLICANT
Assigned to Plan Check Engineer 12/11/2023 PRANITA SHAH
Corrections Issued 12/12/2023 RAHEL BEYENE
Quality Review Completed 12/14/2023 GARO TELMI
Applicant returned to address corrections 3/22/2024 PRANITA SHAH
Applicant returned to address corrections 4/2/2024 PRANITA SHAH
Plan Check Approved 4/17/2024 PRANITA SHAH
Issued 4/18/2024 APPLICANT
CofO in Progress 2/18/2025 EUGENE CASSIDY
Permit Finaled 2/18/2025 ANSON MAGLASANG
CofO Issued 2/18/2025 ANSON MAGLASANG
Permit Finaled 2/18/2025 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 1/18/2024 KHAING AYE
Eng Process Fee Ord 176,300 Cleared 1/23/2024 KHAING AYE
Low Impact Development (LID) Cleared 2/29/2024 PATRICK LOPEZ
Sewer availability Cleared 3/7/2024 KHAING AYE
Roof/Waste drainage to street Cleared 3/12/2024 KHAING AYE

Contact Information

Contractor Owner-Builder       ,
Engineer Rodriguez,, Jacob; Lic. No.: S5084 8206 ENCINO AVE      NORTHRIDGE, CA 91325

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/23/2024 Partial Approval EUGENE CASSIDY
Footing/Foundation/Slab 6/6/2024 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 7/1/2024 Partial Approval EUGENE CASSIDY
Deputy Wood Construction 7/19/2024 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 8/5/2024 Approved EUGENE CASSIDY
HVAC-Rough 8/5/2024 Approved EUGENE CASSIDY
PLUMBING-Rough 8/5/2024 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 8/6/2024 Partial Approval EUGENE CASSIDY
Sewer 8/13/2024 Approved EUGENE CASSIDY
Underground Mechanical 8/13/2024 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 8/28/2024 Corrections Issued EUGENE CASSIDY
Green Building Rough 8/28/2024 Approved EUGENE CASSIDY
Verify Sprinkler Sign Off 8/28/2024 Approved EUGENE CASSIDY
Wood Frame 8/28/2024 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 9/6/2024 Approved JOSEPH MCGARRY
Wood Frame 9/6/2024 Approved JOSEPH MCGARRY
Insulation 9/23/2024 Approved EUGENE CASSIDY
Interior/Exterior Lathing 9/23/2024 Partial Approval EUGENE CASSIDY
Drywall Nailing 9/27/2024 Approved EUGENE CASSIDY
Interior/Exterior Lathing 9/27/2024 Approved EUGENE CASSIDY
Shower Pan 9/27/2024 Approved EUGENE CASSIDY
Underground Mechanical 11/7/2024 Approved EUGENE CASSIDY
ELECTRICAL-Final 12/11/2024 Not Ready for Inspection EUGENE CASSIDY
Final 12/11/2024 Corrections Issued EUGENE CASSIDY
Green Building Final 12/11/2024 Not Ready for Inspection EUGENE CASSIDY
HVAC-Final 12/11/2024 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Final 12/11/2024 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 12/11/2024 SGSOV Approved EUGENE CASSIDY
Service/Power Release 12/11/2024 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 12/11/2024 Approved EUGENE CASSIDY
Final 2/3/2025 Corrections Issued EUGENE CASSIDY
Green Building Final 2/3/2025 Not Ready for Inspection EUGENE CASSIDY
Service/Power Release 2/3/2025 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Final 2/14/2025 Approved EUGENE CASSIDY
Final 2/14/2025 OK to Issue CofO EUGENE CASSIDY
Green Building Final 2/14/2025 Approved EUGENE CASSIDY
HVAC-Final 2/14/2025 Approved EUGENE CASSIDY
Service/Power Release 2/14/2025 Approved EUGENE CASSIDY