1348 W 222ND ST 90501
Certificate Information: 1348 W 222ND ST 90501
- Application / Permit
- 23010-10000-04769
- Plan Check / Job No.
- B23LA22406
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan. New detached 2-story Accessory dwelling unit Per lamc 12.22A.33(c)and(d)
- Permit Issued
- Issued on 4/18/2024
- Issuing Office
- Current Status
- CofO Issued on 2/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/28/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/11/2023 | PRANITA SHAH |
| Corrections Issued | 12/12/2023 | RAHEL BEYENE |
| Quality Review Completed | 12/14/2023 | GARO TELMI |
| Applicant returned to address corrections | 3/22/2024 | PRANITA SHAH |
| Applicant returned to address corrections | 4/2/2024 | PRANITA SHAH |
| Plan Check Approved | 4/17/2024 | PRANITA SHAH |
| Issued | 4/18/2024 | APPLICANT |
| CofO in Progress | 2/18/2025 | EUGENE CASSIDY |
| Permit Finaled | 2/18/2025 | ANSON MAGLASANG |
| CofO Issued | 2/18/2025 | ANSON MAGLASANG |
| Permit Finaled | 2/18/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 1/18/2024 | KHAING AYE |
| Eng Process Fee Ord 176,300 | Cleared | 1/23/2024 | KHAING AYE |
| Low Impact Development (LID) | Cleared | 2/29/2024 | PATRICK LOPEZ |
| Sewer availability | Cleared | 3/7/2024 | KHAING AYE |
| Roof/Waste drainage to street | Cleared | 3/12/2024 | KHAING AYE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rodriguez,, Jacob; Lic. No.: S5084 | 8206 ENCINO AVE NORTHRIDGE, CA 91325 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/23/2024 | Partial Approval | EUGENE CASSIDY |
| Footing/Foundation/Slab | 6/6/2024 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2024 | Partial Approval | EUGENE CASSIDY |
| Deputy Wood Construction | 7/19/2024 | Partial Approval | EUGENE CASSIDY |
| ELECTRICAL-Rough | 8/5/2024 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 8/5/2024 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 8/5/2024 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 8/6/2024 | Partial Approval | EUGENE CASSIDY |
| Sewer | 8/13/2024 | Approved | EUGENE CASSIDY |
| Underground Mechanical | 8/13/2024 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 8/28/2024 | Corrections Issued | EUGENE CASSIDY |
| Green Building Rough | 8/28/2024 | Approved | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 8/28/2024 | Approved | EUGENE CASSIDY |
| Wood Frame | 8/28/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 9/6/2024 | Approved | JOSEPH MCGARRY |
| Wood Frame | 9/6/2024 | Approved | JOSEPH MCGARRY |
| Insulation | 9/23/2024 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 9/23/2024 | Partial Approval | EUGENE CASSIDY |
| Drywall Nailing | 9/27/2024 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 9/27/2024 | Approved | EUGENE CASSIDY |
| Shower Pan | 9/27/2024 | Approved | EUGENE CASSIDY |
| Underground Mechanical | 11/7/2024 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 12/11/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 12/11/2024 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 12/11/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| HVAC-Final | 12/11/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Final | 12/11/2024 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 12/11/2024 | SGSOV Approved | EUGENE CASSIDY |
| Service/Power Release | 12/11/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 12/11/2024 | Approved | EUGENE CASSIDY |
| Final | 2/3/2025 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 2/3/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| Service/Power Release | 2/3/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Final | 2/14/2025 | Approved | EUGENE CASSIDY |
| Final | 2/14/2025 | OK to Issue CofO | EUGENE CASSIDY |
| Green Building Final | 2/14/2025 | Approved | EUGENE CASSIDY |
| HVAC-Final | 2/14/2025 | Approved | EUGENE CASSIDY |
| Service/Power Release | 2/14/2025 | Approved | EUGENE CASSIDY |