4578 N ROUND TOP DR 90065
Certificate Information: 4578 N ROUND TOP DR 90065
- Application / Permit
- 23010-10000-04761
- Plan Check / Job No.
- B23LA22347
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Patio Cover
- Work Description
- (N) DETACHED PATIO COVER **TO BE FIRE SPRINKLERED BY NFPA-13D**
- Permit Issued
- Issued on 1/22/2025
- Issuing Office
- Metro
- Current Status
- Issued on 1/22/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/29/2023 | FERNANDO FLORES |
| Corrections Issued | 12/2/2023 | FERNANDO FLORES |
| Building Plans Picked Up | 12/4/2023 | APPLICANT |
| Applicant returned to address corrections | 12/17/2024 | NGHI SU |
| Plan Check Approved | 1/15/2025 | AUNG SOE |
| Issued | 1/22/2025 | APPLICANT |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 7/17/2024 | DAVID LOPEZ |
| BHO/Hillside ordinance | Cleared | 7/17/2024 | DAVID LOPEZ |
| BHO/Hillside ordinance | Cleared | 7/17/2024 | DAVID LOPEZ |
| BHO/Hillside ordinance | Cleared | 7/17/2024 | DAVID LOPEZ |
| BHO/Hillside ordinance | Cleared | 7/17/2024 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 7/17/2024 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/18/2024 | DAVID LOPEZ |
| Supp. Use District POD/CDO/TDO | Cleared | 8/15/2024 | ANDREA MAGANA-WITHERS |
| Distance to fire station | Cleared | 10/8/2024 | PATRICK PEREZ |
| Construction near power lines | Cleared | 11/9/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Carrillo,, Jesus Eduardo; Lic. No.: C77737 | 8207 BROOKGREEN RD DOWNEY, CA 90240 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/24/2025 | Corrections Issued | BRENDAN MORELLI |
| Deputy Reinf. Concrete | 2/25/2025 | Conditional Approval | JOSH MEISTER |
| Deputy Steel/Welding | 3/20/2025 | Conditional Approval | JOSH MEISTER |
| Footing/Foundation/Slab | 4/30/2025 | Partial Approval | JEFFREY MEAD |
| Footing/Foundation/Slab | 5/30/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Rough | 9/25/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| MERV13>=Rough | 9/25/2025 | Approved | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 9/25/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |