5522 E YORK BLVD 90042
Certificate Information: 5522 E YORK BLVD 90042
- Application / Permit
- 23010-10000-04729
- Plan Check / Job No.
- B23LA21407
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan. PROPOSED 3 STORY SFD WITH ATTACHED CARPORT AND STORAGE ROOM *** BUILDING TO BE FULLY EQUIPPED WITH NFPA-13D FIRE SPRINKLERS***
- Permit Issued
- Issued on 9/24/2024
- Issuing Office
- Current Status
- Issued on 9/24/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/13/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2023 | CRYSTEL MAALOUF |
| Corrections Issued | 11/30/2023 | CRYSTEL MAALOUF |
| Quality Review Completed | 12/20/2023 | SINA KHOSRAVI |
| Applicant returned to address corrections | 5/20/2024 | MARCELA FRANQUEZ |
| Applicant returned to address corrections | 6/18/2024 | MARCELA FRANQUEZ |
| Applicant returned to address corrections | 7/11/2024 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 8/12/2024 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 8/26/2024 | CRYSTEL MAALOUF |
| Plan Check Approved | 9/17/2024 | CRYSTEL MAALOUF |
| Plan Check Approved | 9/23/2024 | CRYSTEL MAALOUF |
| Plan Check Approved | 9/24/2024 | CRYSTEL MAALOUF |
| Plan Check Approved | 9/24/2024 | CRYSTEL MAALOUF |
| Issued | 9/24/2024 | APPLICANT |
Permit Application Clearance Information
| "Q" conditions | Cleared | 1/25/2024 | DALIA MOKAYED |
| Eng Process Fee Ord 176,300 | Cleared | 1/25/2024 | CELINA MORENO |
| Address approval | Cleared | 1/26/2024 | WALLIE JONG |
| Sewer availability | Cleared | 2/21/2024 | WALLIE JONG |
| Low Impact Development (LID) | Cleared | 3/6/2024 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 3/7/2024 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 4/26/2024 | GILBERT URREA |
| GPI Written Notices | Cleared | 8/26/2024 | ROBERT HUGHES |
| Grading Pre-Inspection | Cleared | 8/26/2024 | ROBERT HUGHES |
| Zoning Information File | Cleared | 8/26/2024 | CRYSTEL MAALOUF |
| SB8 RUD | Cleared | 9/11/2024 | OLIVIA JIN |
Contact Information
| Architect | Bressler,, Adam Lloyd; Lic. No.: C32288 | 7631 LEXINGTON AVE WEST HOLLYWOOD, CA 90046 |
| Contractor | Owner-Builder | , |
| Engineer | Attaalla,, Sayed Ahmed; Lic. No.: S5339 | 11254 HANNUM AVE CULVER CITY, CA 90230 |
| Engineer | Obando,, Gaspar Eduardo; Lic. No.: C71382 | 3101 OCEAN PARK BLVD STE 100, PMB 122 SANTA MONICA, CA 90405 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/31/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 4/9/2025 | Partial Approval | DAVID WILLIAMS |
| Underground Mechanical | 4/9/2025 | Approved | DAVID WILLIAMS |
| Deputy Reinf. Concrete | 4/11/2025 | Conditional Approval | DAVID WILLIAMS |
| Underground Mechanical | 5/6/2025 | Partial Approval | DAVID WILLIAMS |
| Deputy Drilled-In Anchors | 5/29/2025 | Conditional Approval | REGINA MENDEZ |
| Footing/Foundation/Slab | 5/30/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| Footing/Foundation/Slab | 6/3/2025 | Approved | DAVID WILLIAMS |
| Deputy Wood Construction | 7/7/2025 | Conditional Approval | DAVID WILLIAMS |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2025 | Partial Approval | DAVID WILLIAMS |
| Deputy Drilled-In Anchors | 7/17/2025 | Conditional Approval | DAVID WILLIAMS |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2025 | Partial Approval | DAVID WILLIAMS |
| Deputy Wood Construction | 7/22/2025 | Conditional Approval | DAVID WILLIAMS |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2025 | Partial Approval | DAVID WILLIAMS |
| Deputy Wood Construction | 8/19/2025 | Conditional Approval | DAVID WILLIAMS |
| Rough-Elec/Plmb/HVAC | 10/28/2025 | Approved | DAVID WILLIAMS |
| Wood Frame | 10/28/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| BUILDING-Rough-Frame | 11/7/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| Green Building Rough | 11/7/2025 | Approved | DAVID WILLIAMS |
| Verify Sprinkler Sign Off | 11/7/2025 | Approved | DAVID WILLIAMS |
| BUILDING-Rough-Frame | 11/25/2025 | Approved | DAVID WILLIAMS |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2025 | Approved | DAVID WILLIAMS |
| Insulation | 1/9/2026 | Approved | DAVID WILLIAMS |
| Interior/Exterior Lathing | 1/9/2026 | Partial Approval | DAVID WILLIAMS |
| Drywall Nailing | 1/28/2026 | Approved | GEM DE OCAMPO |
| Pre-Inspection | 2/11/2026 | Partial Approval | GEM DE OCAMPO |
| ELECTRICAL-Rough | 2/12/2026 | Approved | DAVID WILLIAMS |
| HVAC-Rough | 2/12/2026 | Approved | DAVID WILLIAMS |
| PLUMBING-Rough | 2/12/2026 | Approved | DAVID WILLIAMS |
| Interior/Exterior Lathing | 2/18/2026 | Not Ready for Inspection | GEM DE OCAMPO |
| Shower Pan | 2/20/2026 | Approved | DAVID WILLIAMS |
| Interior/Exterior Lathing | 3/2/2026 | Corrections Issued | DAVID WILLIAMS |
| Interior/Exterior Lathing | 3/5/2026 | Approved | DAVID WILLIAMS |
| Interior/Exterior Lathing | 3/17/2026 | Approved | GEM DE OCAMPO |