10915 1/2 S ANZAC AVE 90059

Certificate Information: 10915 1/2 S ANZAC AVE 90059

Application / Permit
23010-10000-04710
Plan Check / Job No.
B23LA22166
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New detached 2-story ADU w/ attached 1st story garage on Lot 218. ADU per GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33 (c)-(d), (g). <NFPA 13D fire sprinkleres REQD thru-out BLDG. >
Permit Issued
Issued on 3/27/2025
Issuing Office
Metro
Current Status
Issued on 3/27/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/22/2023 APPLICANT
Assigned to Plan Check Engineer 11/22/2023 HUAN LE
Corrections Issued 12/11/2023 HUAN LE
Quality Review Completed 12/13/2023 KESETE HAREGOT
Building Plans Picked Up 12/15/2023 APPLICANT
Applicant returned to address corrections 10/29/2024 HUAN LE
Applicant returned to address corrections 11/5/2024 HUAN LE
Plan Check Approved 11/20/2024 HUAN LE
Issued 3/27/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 1/18/2024 ARNULFO CHAMU
Hydrant and Access approval Cleared 1/26/2024 JOHN CONNEALLY
Low Impact Development (LID) Cleared 3/5/2024 LUIS CRUZ
Eng Process Fee Ord 176,300 Cleared 3/6/2024 ARNULFO CHAMU
Roof/Waste drainage to street Cleared 3/12/2024 CHRISTINA BRACO
Sewer availability Cleared 6/10/2024 ARNULFO CHAMU
Trees in Parkway Cleared 8/26/2024 ADALBERTO VERA
Construction near power lines Cleared 9/23/2024 RIDWAN HARDY

Contact Information

Contractor Ebenezer Construction; Lic. No.: 657529-B 9214 MANZANAR AVE      DOWNEY, CA 90240
Engineer Sandoval,, Martin; Lic. No.: C56905 12761 DAIRY ST      EASTVALE, CA 92880

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/3/2025 Partial Approval ANTHONY EGSON
PLUMBING-Rough 4/3/2025 Partial Approval ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 5/27/2025 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 5/29/2025 Not Ready for Inspection ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 6/25/2025 Corrections Issued ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 6/27/2025 Partial Approval ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 9/8/2025 Partial Approval ANTHONY EGSON
PLUMBING-Rough 9/8/2025 Approved ANTHONY EGSON
ELECTRICAL-Rough 9/11/2025 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 9/11/2025 Approved ANTHONY EGSON
Verify Sprinkler Sign Off 9/11/2025 Approved ANTHONY EGSON
Green Building Rough 9/16/2025 Approved ANTHONY EGSON
HVAC-Rough 9/16/2025 Approved ANTHONY EGSON
Insulation 10/9/2025 Approved ANTHONY EGSON
Interior/Exterior Lathing 10/9/2025 Approved ANTHONY EGSON
BUILDING-Rough-Frame 11/3/2025 Approved ANTHONY EGSON
Drywall Nailing 11/3/2025 Approved ANTHONY EGSON
Sewer 2/4/2026 Approved ARTHUR NEGRETE
ELECTRICAL-Final 3/5/2026 Approved ARTHUR NEGRETE
Final 3/5/2026 Corrections Issued ARTHUR NEGRETE
Footing/Foundation/Slab 3/5/2026 Approved ARTHUR NEGRETE
Green Building Final 3/5/2026 Approved ARTHUR NEGRETE
HVAC-Final 3/5/2026 Approved ARTHUR NEGRETE
PLUMBING-Final 3/5/2026 Approved ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 3/5/2026 SGSOV Not Ready ARTHUR NEGRETE
Service/Power Release 3/5/2026 Not Ready for Inspection ARTHUR NEGRETE
Smoke Detectors 3/5/2026 Approved ARTHUR NEGRETE
ELECTRICAL-Final 3/16/2026 Approved ARTHUR NEGRETE
Final 3/16/2026 Partial Approval ARTHUR NEGRETE
HVAC-Final 3/16/2026 Approved ARTHUR NEGRETE
PLUMBING-Final 3/16/2026 Approved ARTHUR NEGRETE
Pool Piping 3/16/2026 Approved ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 3/16/2026 SGSOV Not Required ARTHUR NEGRETE
Service/Power Release 3/16/2026 Approved ARTHUR NEGRETE