10915 1/2 S ANZAC AVE 90059
Certificate Information: 10915 1/2 S ANZAC AVE 90059
- Application / Permit
- 23010-10000-04710
- Plan Check / Job No.
- B23LA22166
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New detached 2-story ADU w/ attached 1st story garage on Lot 218. ADU per GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33 (c)-(d), (g). <NFPA 13D fire sprinkleres REQD thru-out BLDG. >
- Permit Issued
- Issued on 3/27/2025
- Issuing Office
- Metro
- Current Status
- Issued on 3/27/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/22/2023 | HUAN LE |
| Corrections Issued | 12/11/2023 | HUAN LE |
| Quality Review Completed | 12/13/2023 | KESETE HAREGOT |
| Building Plans Picked Up | 12/15/2023 | APPLICANT |
| Applicant returned to address corrections | 10/29/2024 | HUAN LE |
| Applicant returned to address corrections | 11/5/2024 | HUAN LE |
| Plan Check Approved | 11/20/2024 | HUAN LE |
| Issued | 3/27/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/18/2024 | ARNULFO CHAMU |
| Hydrant and Access approval | Cleared | 1/26/2024 | JOHN CONNEALLY |
| Low Impact Development (LID) | Cleared | 3/5/2024 | LUIS CRUZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/6/2024 | ARNULFO CHAMU |
| Roof/Waste drainage to street | Cleared | 3/12/2024 | CHRISTINA BRACO |
| Sewer availability | Cleared | 6/10/2024 | ARNULFO CHAMU |
| Trees in Parkway | Cleared | 8/26/2024 | ADALBERTO VERA |
| Construction near power lines | Cleared | 9/23/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Ebenezer Construction; Lic. No.: 657529-B | 9214 MANZANAR AVE DOWNEY, CA 90240 |
| Engineer | Sandoval,, Martin; Lic. No.: C56905 | 12761 DAIRY ST EASTVALE, CA 92880 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/3/2025 | Partial Approval | ANTHONY EGSON |
| PLUMBING-Rough | 4/3/2025 | Partial Approval | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 5/27/2025 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 5/29/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/25/2025 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2025 | Partial Approval | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/8/2025 | Partial Approval | ANTHONY EGSON |
| PLUMBING-Rough | 9/8/2025 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 9/11/2025 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/11/2025 | Approved | ANTHONY EGSON |
| Verify Sprinkler Sign Off | 9/11/2025 | Approved | ANTHONY EGSON |
| Green Building Rough | 9/16/2025 | Approved | ANTHONY EGSON |
| HVAC-Rough | 9/16/2025 | Approved | ANTHONY EGSON |
| Insulation | 10/9/2025 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 10/9/2025 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 11/3/2025 | Approved | ANTHONY EGSON |
| Drywall Nailing | 11/3/2025 | Approved | ANTHONY EGSON |
| Sewer | 2/4/2026 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Final | 3/5/2026 | Approved | ARTHUR NEGRETE |
| Final | 3/5/2026 | Corrections Issued | ARTHUR NEGRETE |
| Footing/Foundation/Slab | 3/5/2026 | Approved | ARTHUR NEGRETE |
| Green Building Final | 3/5/2026 | Approved | ARTHUR NEGRETE |
| HVAC-Final | 3/5/2026 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 3/5/2026 | Approved | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 3/5/2026 | SGSOV Not Ready | ARTHUR NEGRETE |
| Service/Power Release | 3/5/2026 | Not Ready for Inspection | ARTHUR NEGRETE |
| Smoke Detectors | 3/5/2026 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Final | 3/16/2026 | Approved | ARTHUR NEGRETE |
| Final | 3/16/2026 | Partial Approval | ARTHUR NEGRETE |
| HVAC-Final | 3/16/2026 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 3/16/2026 | Approved | ARTHUR NEGRETE |
| Pool Piping | 3/16/2026 | Approved | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 3/16/2026 | SGSOV Not Required | ARTHUR NEGRETE |
| Service/Power Release | 3/16/2026 | Approved | ARTHUR NEGRETE |