317 1/4-1/2 E 106TH ST 90003

Certificate Information: 317 1/4-1/2 E 106TH ST 90003

Application / Permit
23010-10000-04686
Plan Check / Job No.
B23LA22090
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan NEW TWO-UNIT, 2-STORY ADU PER GCS 65852.2(e)(1)(D) AND LAMC 12.22 A.33(c)(d) AND (g)
Permit Issued
Issued on 2/12/2024
Issuing Office
Current Status
CofO Issued on 9/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/21/2023 APPLICANT
Assigned to Plan Check Engineer 12/7/2023 MAHNAZ NOURHASHEMI
Corrections Issued 12/15/2023 MAHNAZ NOURHASHEMI
Quality Review Completed 1/4/2024 TU HUA
Plan Check Approved 1/29/2024 MAHNAZ NOURHASHEMI
Issued 2/12/2024 APPLICANT
CofO in Progress 9/23/2025 ANTHONY EGSON
Permit Finaled 9/23/2025 ANSON MAGLASANG
CofO Issued 9/23/2025 ANSON MAGLASANG
Permit Finaled 9/23/2025 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 12/29/2023 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 1/9/2024 ERIK BEASLEY
Low Impact Development (LID) Cleared 1/9/2024 SAMUEL LINN
Roof/Waste drainage to street Cleared 1/9/2024 ERIK BEASLEY
Sewer availability Cleared 1/9/2024 ERIK BEASLEY

Contact Information

Contractor Jarh Builders Corporation; Lic. No.: 1074687-B 15740 PARAMOUNT BLVD #E      PARAMOUNT, CA 90723
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/5/2024 Corrections Issued BEN MOLSTAD
Special/Order Compliance 8/5/2024 Partial Inspection BARRY HACHE
Footing/Foundation/Slab 8/29/2024 Corrections Issued BEN MOLSTAD
Excavation/Setback/Form/Re-Bar 9/4/2024 Approved BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 9/26/2024 Approved BARRY HACHE
Floor/Roof Diaphrgm/Shear Wall 10/24/2024 No Access for Inspection ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 10/28/2024 Corrections Issued BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 10/30/2024 Partial Approval BEN MOLSTAD
BUILDING-Rough-Frame 12/16/2024 Not Ready for Inspection BEN MOLSTAD
ELECTRICAL-Rough 12/16/2024 Not Ready for Inspection BEN MOLSTAD
Green Building Rough 12/16/2024 Not Ready for Inspection BEN MOLSTAD
HVAC-Rough 12/16/2024 Corrections Issued BEN MOLSTAD
PLUMBING-Rough 12/16/2024 Approved BEN MOLSTAD
Verify Sprinkler Sign Off 12/16/2024 Not Ready for Inspection BEN MOLSTAD
ELECTRICAL-Rough 12/19/2024 Corrections Issued ANTHONY EGSON
Green Building Rough 12/19/2024 Corrections Issued ANTHONY EGSON
HVAC-Rough 12/19/2024 Corrections Issued ANTHONY EGSON
BUILDING-Rough-Frame 1/7/2025 Corrections Issued ANTHONY EGSON
Green Building Rough 1/7/2025 Not Ready for Inspection ANTHONY EGSON
Rough-Elec/Plmb/HVAC 1/7/2025 Corrections Issued ANTHONY EGSON
Verify Sprinkler Sign Off 1/7/2025 Not Ready for Inspection ANTHONY EGSON
BUILDING-Rough-Frame 2/4/2025 Approved ANTHONY EGSON
Green Building Rough 2/4/2025 Approved ANTHONY EGSON
Rough-Elec/Plmb/HVAC 2/4/2025 Approved ANTHONY EGSON
Insulation 2/13/2025 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 2/13/2025 Partial Approval JOSEPH MCGARRY
Drywall Nailing 2/24/2025 Approved BEN MOLSTAD
PLUMBING-Rough 5/19/2025 Approved ANTHONY EGSON
Sewer 5/19/2025 Approved ANTHONY EGSON
ELECTRICAL-Final 7/28/2025 Corrections Issued ANTHONY EGSON
Final 7/28/2025 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 7/28/2025 Approved ANTHONY EGSON
Green Building Final 7/28/2025 Corrections Issued ANTHONY EGSON
HVAC-Final 7/28/2025 Corrections Issued ANTHONY EGSON
PLUMBING-Final 7/28/2025 Approved ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 7/28/2025 SGSOV Not Required ANTHONY EGSON
Service/Power Release 7/28/2025 Not Ready for Inspection ANTHONY EGSON
Smoke Detectors 7/28/2025 Approved ANTHONY EGSON
ELECTRICAL-Final 8/21/2025 Approved ANTHONY EGSON
Final 8/21/2025 Corrections Issued ANTHONY EGSON
Green Building Final 8/21/2025 Approved ANTHONY EGSON
Service/Power Release 8/21/2025 Not Ready for Inspection ANTHONY EGSON
Final 9/4/2025 Not Ready for Inspection ANTHONY EGSON
HVAC-Final 9/4/2025 Approved ANTHONY EGSON
Service/Power Release 9/4/2025 Approved ANTHONY EGSON
Final 9/22/2025 OK to Issue CofO ANTHONY EGSON