8853 N BALBOA BLVD 91325

Certificate Information: 8853 N BALBOA BLVD 91325

Application / Permit
23010-10000-04651
Plan Check / Job No.
B23VN15143
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*** Eplan*** New detached ADU with Open Trellis (Front) and 4 car Garage (Rear). LAMC 12.22.A33.(c) , (d) 2 of 2
Permit Issued
Issued on 10/30/2024
Issuing Office
Current Status
Issued on 10/30/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/4/2023 APPLICANT
Assigned to Plan Check Engineer 11/16/2023 TSE MING HUANG
Corrections Issued 11/20/2023 TSE MING HUANG
Quality Review Completed 11/21/2023 EUGENE BARBEAU
Plan Check Approved 9/5/2024 TSE MING HUANG
Issued 10/30/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 12/2/2023 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 12/4/2023 COLIN LOREDO
Miscellaneous Cleared 12/4/2023 ASHLEY RODARTE
Sewer availability Cleared 12/4/2023 COLIN LOREDO
Construction near power lines Cleared 3/8/2024 RIDWAN HARDY
Construction within easement Cleared 3/8/2024 RIDWAN HARDY
Low Impact Development (LID) Cleared 5/29/2024 MITESH PATEL
Roof/Waste drainage to street Cleared 6/1/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 7/16/2025 Partial Approval NICHOLAS TROWBRIDGE
Excavation/Setback/Form/Re-Bar 8/8/2025 Corrections Issued NICHOLAS TROWBRIDGE
Excavation/Setback/Form/Re-Bar 8/13/2025 Approved NICHOLAS TROWBRIDGE
Floor/Roof Diaphrgm/Shear Wall 9/3/2025 Partial Approval NICHOLAS TROWBRIDGE
Floor/Roof Diaphrgm/Shear Wall 9/23/2025 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 10/20/2025 Partial Approval NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 5/19/2026 Approved CHRISTOPHER ROJAS
ELECTRICAL-Rough 5/19/2026 Approved CHRISTOPHER ROJAS
Green Building Rough 5/19/2026 Approved CHRISTOPHER ROJAS
HVAC-Rough 5/19/2026 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 5/19/2026 Approved CHRISTOPHER ROJAS
Special/Order Compliance 5/19/2026 Corrections Issued CHRISTOPHER ROJAS
Insulation 6/11/2026 Approved KEVIN BERBERYAN
Sewer 6/11/2026 Approved KEVIN BERBERYAN
Underground Mechanical 6/11/2026 Approved KEVIN BERBERYAN