12901 N JOLETTE AVE 91344
Certificate Information: 12901 N JOLETTE AVE 91344
- Application / Permit
- 23010-10000-04635
- Plan Check / Job No.
- B23LA21905
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (22) Storage Building
- Work Description
- NEW STORAGE 14' X 24' PER WFPP
- Permit Issued
- Issued on 12/1/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2023 | FERNANDO FLORES |
| Corrections Issued | 11/21/2023 | FERNANDO FLORES |
| Building Plans Picked Up | 11/28/2023 | APPLICANT |
| Plan Check Approved | 12/1/2023 | SAMUEL GONZALEZ |
| Issued | 12/1/2023 | APPLICANT |
| CofO in Progress | 1/25/2024 | STEVEN BACK |
| Permit Finaled | 2/12/2024 | JOHN JANSON |
| CofO Issued | 2/12/2024 | JOHN JANSON |
| Permit Finaled | 2/12/2024 | JOHN JANSON |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 11/21/2023 | EDGAR ALCARAZ |
| BHO/Hillside ordinance | Cleared | 11/21/2023 | EDGAR ALCARAZ |
| BHO/Hillside ordinance | Cleared | 11/21/2023 | EDGAR ALCARAZ |
| BHO/Hillside ordinance | Cleared | 11/21/2023 | EDGAR ALCARAZ |
| BHO/Hillside ordinance | Cleared | 11/21/2023 | EDGAR ALCARAZ |
| Roof/Waste drainage to street | Cleared | 11/21/2023 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/22/2023 | BRYAN GODINEZ |
| Grading Pre-Inspection | Cleared | 11/28/2023 | ALEXANDER HELFER |
| ZA Case | Cleared | 11/29/2023 | DAVID URITA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Martirossyan,, Armen; Lic. No.: C64223 | 802 PORTOLA AVE GLENDALE, CA 91206 |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/6/2023 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 12/6/2023 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 12/18/2023 | Corrections Issued | STEVEN BACK |
| ELECTRICAL-Rough | 12/18/2023 | Approved | STEVEN BACK |
| Green Building Rough | 12/18/2023 | Not Ready for Inspection | STEVEN BACK |
| Verify Sprinkler Sign Off | 12/18/2023 | Not Ready for Inspection | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2023 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 12/19/2023 | No Access for Inspection | STEVEN BACK |
| Interior/Exterior Lathing | 12/26/2023 | Partial Approval | STEVEN BACK |
| BUILDING-Rough-Frame | 1/8/2024 | Approved | STEVEN BACK |
| Green Building Rough | 1/8/2024 | Approved | STEVEN BACK |
| Drywall Nailing | 1/10/2024 | Approved | STEVEN BACK |
| Final | 1/25/2024 | OK to Issue CofO | STEVEN BACK |
| Green Building Final | 1/25/2024 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 1/25/2024 | SGSOV Approved | STEVEN BACK |
| Smoke Detectors | 1/25/2024 | Approved | STEVEN BACK |