- eplan ADDITION TO (E) SFD WITH ATTACHED ADU PER LAMC 12.22 A.33 (c)-(e) AND ATT. GARAGE WITH MAJOR STR. REMODEL -BLDG SPRINKLERED THRU-OUT
- Permit Issued
- Issued on 9/20/2024
- Issuing Office
- Current Status
- Issued on 9/20/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/20/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2023 | MAHNAZ NOURHASHEMI |
| Plans on Hold | 11/25/2023 | MAHNAZ NOURHASHEMI |
| Hold Released | 12/5/2023 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 12/5/2023 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 12/13/2023 | TU HUA |
| Applicant returned to address corrections | 4/3/2024 | JAD BASMA |
| Applicant returned to address corrections | 6/25/2024 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 8/30/2024 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 9/20/2024 | MAHNAZ NOURHASHEMI |
| Issued | 9/20/2024 | APPLICANT |
Permit Application Clearance Information
| Watercourse | Cleared | 12/18/2023 | HISASHI KOBAYAKAWA |
| Hydrant and Access approval | Cleared | 2/2/2024 | MATTHEW CRAIG |
| BHO/Hillside ordinance | Cleared | 2/26/2024 | ANDREA SAINT-ANTONIN |
| BHO/Hillside ordinance | Cleared | 2/26/2024 | ANDREA SAINT-ANTONIN |
| BHO/Hillside ordinance | Cleared | 2/26/2024 | ANDREA SAINT-ANTONIN |
| BHO/Hillside ordinance | Cleared | 2/26/2024 | ANDREA SAINT-ANTONIN |
| BHO/Hillside ordinance | Cleared | 2/26/2024 | ANDREA SAINT-ANTONIN |
| Permit | Cleared | 2/26/2024 | ANDREA SAINT-ANTONIN |
| Address approval | Cleared | 2/27/2024 | VLADIMIR ARUTYUNYAN |
| Low Impact Development (LID) | Cleared | 3/7/2024 | MELINEH AGHAKHABIAN |
| Disturb/Remove Protected Trees | Cleared | 3/12/2024 | ADALBERTO VERA |
| Roof/Waste drainage to street | Cleared | 3/12/2024 | VLADIMIR ARUTYUNYAN |
| Trees in Parkway | Cleared | 3/13/2024 | ADALBERTO VERA |
| Eng Process Fee Ord 176,300 | Cleared | 6/4/2024 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 6/4/2024 | HISASHI KOBAYAKAWA |
| GPI Written Notices | Cleared | 8/27/2024 | MAHNAZ NOURHASHEMI |
| Grading Pre-Inspection | Cleared | 8/27/2024 | MAHNAZ NOURHASHEMI |
| Address approval | Cleared | 8/30/2024 | VLADIMIR ARUTYUNYAN |
Contact Information
| Contractor | Sls Properties Inc; Lic. No.: 1037218-B | , |
| Contractor | Sls Team Builders; Lic. No.: 1037218-B | , |
| Engineer | Messiha,, Hany Gamil; Lic. No.: C56766 | 19648 MULBERRY DR WALNUT, CA 91789 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/23/2025 | Corrections Issued | KEVIN SARGSYAN |
| Underground Mechanical | 3/21/2025 | Partial Approval | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 4/9/2025 | Corrections Issued | TEMISTOCLES CAAL |
| Excavation/Setback/Form/Re-Bar | 4/10/2025 | Corrections Issued | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 4/23/2025 | Partial Approval | HERBERT GIRON |
| Excavation/Setback/Form/Re-Bar | 5/8/2025 | Corrections Issued | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 5/12/2025 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2025 | Not Ready for Inspection | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/8/2025 | Partial Approval | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 10/17/2025 | Corrections Issued | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2025 | Partial Approval | KEVIN SARGSYAN |
| Gas Test | 11/5/2025 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 11/5/2025 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 11/21/2025 | Approved | KEVIN SARGSYAN |
| Shower Pan | 11/25/2025 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2025 | Corrections Issued | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2025 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 12/19/2025 | Not Ready for Inspection | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 12/29/2025 | Partial Approval | KEVIN SARGSYAN |
| Insulation | 1/8/2026 | Corrections Issued | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 1/15/2026 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 2/5/2026 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 2/6/2026 | Partial Approval | KEVIN SARGSYAN |
| HVAC-Rough | 2/13/2026 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 2/19/2026 | Not Ready for Inspection | KEVIN SARGSYAN |
| FLOOD-Proofing Certificate | 2/19/2026 | Approved | KEVIN SARGSYAN |
| Green Building Rough | 2/19/2026 | Approved | KEVIN SARGSYAN |
| Verify Sprinkler Sign Off | 2/19/2026 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 2/23/2026 | Corrections Issued | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 2/25/2026 | Not Ready for Inspection | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 3/2/2026 | Not Ready for Inspection | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 3/4/2026 | Partial Approval | KEVIN SARGSYAN |
| Insulation | 3/12/2026 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 3/23/2026 | Not Ready for Inspection | KEVIN SARGSYAN |
| Drywall Nailing | 3/25/2026 | Not Ready for Inspection | KEVIN SARGSYAN |
| Drywall Nailing | 3/27/2026 | Approved | KEVIN SARGSYAN |
| Underground Mechanical | 7/21/2026 | Corrections Issued | KEVIN SARGSYAN |