2018 N ALVARADO ST 90039

Certificate Information: 2018 N ALVARADO ST 90039

Application / Permit
23010-10000-04626
Plan Check / Job No.
B23LA21820
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePLAN. NEW 3-STORY SINGLE FAMILY DWELLING WITH ATTACHED CARPORT AND BASEMENT. TO BE EQUIPPED WITH NFPA 13D FIRE SPRINKLERS THROUGH OUT.
Permit Issued
Issued on 5/23/2025
Issuing Office
Current Status
Issued on 5/23/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/20/2023 APPLICANT
Assigned to Plan Check Engineer 11/21/2023 ADRIANA LOPEZ
Corrections Issued 12/2/2023 ADRIANA LOPEZ
Quality Review Completed 12/18/2023 HERNAN ARREOLA
Applicant returned to address corrections 5/1/2024 ADRIANA LOPEZ
Applicant returned to address corrections 5/16/2024 ADRIANA LOPEZ
Applicant returned to address corrections 7/11/2024 ADRIANA LOPEZ
Applicant returned to address corrections 10/15/2024 ADRIANA LOPEZ
Applicant returned to address corrections 10/22/2024 ADRIANA LOPEZ
Applicant returned to address corrections 11/8/2024 ADRIANA LOPEZ
Applicant returned to address corrections 12/23/2024 ADRIANA LOPEZ
Applicant returned to address corrections 2/5/2025 ADRIANA LOPEZ
Applicant returned to address corrections 2/11/2025 ADRIANA LOPEZ
Applicant returned to address corrections 4/10/2025 ADRIANA LOPEZ
Plan Check Approved 5/15/2025 ADRIANA LOPEZ
Issued 5/23/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 12/18/2023 TREVOR QUAN
BHO/Hillside ordinance Cleared 12/18/2023 TREVOR QUAN
BHO/Hillside ordinance Cleared 12/18/2023 TREVOR QUAN
BHO/Hillside ordinance Cleared 12/18/2023 TREVOR QUAN
BHO/Hillside ordinance Cleared 12/18/2023 TREVOR QUAN
BHO/Hillside ordinance Cleared 12/18/2023 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 12/19/2023 TREVOR QUAN
Hydrant and Access approval Cleared 1/26/2024 JOHN CONNEALLY
Trees in Parkway Cleared 1/30/2024 ADALBERTO VERA
Certificate of Compliance Cleared 3/19/2024 MAYELA VILLA
Low Impact Development (LID) Cleared 10/19/2024 JORGE MEJIA LEMUS
Excavation more than 5-ft deep Cleared 11/14/2024 CALOSHA APPROVED
Sewer availability Cleared 12/3/2024 TREVOR QUAN
Permit Cleared 1/25/2025 ARMEN MEHRABIAN
Roof/Waste drainage to street Cleared 1/30/2025 ARMEN MEHRABIAN
Work Adjacent to Public Way Cleared 4/3/2025 LARRY LEE

Contact Information

Architect Abdelsayed,, Marc A; Lic. No.: C38176 280 VIA LINDA VISTA      REDONDO BEACH, CA 90277
Contractor Red Stag Construction Company; Lic. No.: 964664-B       ,
Engineer Bermejo,, Gil Banzon; Lic. No.: C86264 2308 MOUNTAIN OAK RD      BAKERSFIELD, CA 93311
Engineer Salehipour,, Sassan A; Lic. No.: GE2579 1290 N LAKE AVENUE #204      PASADENA, CA 91104

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 8/20/2025 Approved HAMIK HARTOUNIAN
Piling/Pier/Caisson 8/29/2025 Partial Inspection HAMIK HARTOUNIAN
Piling/Pier/Caisson 9/3/2025 Partial Approval HAMIK HARTOUNIAN
Deputy Reinf. Concrete 9/5/2025 Conditional Approval ALEX COLIN
Piling/Pier/Caisson 9/8/2025 Partial Approval HAMIK HARTOUNIAN
Deputy Reinf. Concrete 9/9/2025 Conditional Approval JOSH MEISTER
Deputy Reinf. Concrete 9/11/2025 Conditional Approval JOSH MEISTER
Deputy Reinf. Concrete 9/16/2025 Conditional Approval HAMIK HARTOUNIAN
Piling/Pier/Caisson 9/16/2025 Partial Approval HAMIK HARTOUNIAN
Deputy Reinf. Concrete 9/17/2025 Conditional Approval HAMIK HARTOUNIAN
Deputy Reinf. Concrete 10/2/2025 Conditional Approval HAMIK HARTOUNIAN
Deputy Reinf. Concrete 10/3/2025 Conditional Approval HAMIK HARTOUNIAN
Deputy Reinf. Concrete 10/6/2025 Conditional Approval HAMIK HARTOUNIAN
Sewer 10/9/2025 Partial Approval WILLIAM SIERRA
Deputy Reinf. Masonry 10/21/2025 Conditional Approval HAMIK HARTOUNIAN
Deputy Reinf. Concrete 10/22/2025 Conditional Approval HAMIK HARTOUNIAN
Piling/Pier/Caisson 10/23/2025 Corrections Issued HAMIK HARTOUNIAN
Deputy Reinf. Concrete 10/24/2025 Conditional Approval HAMIK HARTOUNIAN
Deputy Reinf. Concrete 10/30/2025 Conditional Approval ALEX COLIN
Piling/Pier/Caisson 3/16/2026 Corrections Issued HAMIK HARTOUNIAN
Piling/Pier/Caisson 3/18/2026 Partial Approval HAMIK HARTOUNIAN
Deputy Reinf. Concrete 3/19/2026 Conditional Approval HAMIK HARTOUNIAN
Masonry Wall/Backfill 3/25/2026 Partial Approval HAMIK HARTOUNIAN
Piling/Pier/Caisson 4/15/2026 Not Ready for Inspection HAMIK HARTOUNIAN
Piling/Pier/Caisson 4/17/2026 Corrections Issued HAMIK HARTOUNIAN
Underground Mechanical 5/6/2026 Partial Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 5/13/2026 Partial Approval HAMIK HARTOUNIAN
Deputy Reinf. Concrete 5/14/2026 Conditional Approval ALEX COLIN
Deputy Drilled-In Anchors 5/28/2026 Conditional Approval ALIZAH MAYAGOITIA
Masonry Wall/Backfill 5/28/2026 Partial Approval HAMIK HARTOUNIAN
Underground Mechanical 5/28/2026 Not Ready for Inspection HAMIK HARTOUNIAN
Deputy Other (see comments) 5/29/2026 Conditional Approval HAMIK HARTOUNIAN
Underground Mechanical 6/24/2026 Not Ready for Inspection HAMIK HARTOUNIAN
Underground Mechanical 6/26/2026 Partial Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 7/1/2026 Partial Approval HAMIK HARTOUNIAN
Deputy Reinf. Concrete 7/2/2026 Conditional Approval HAMIK HARTOUNIAN
Deputy Reinf. Masonry 7/2/2026 Conditional Approval HAMIK HARTOUNIAN