10623 S MAIN ST 1-3 90003
Certificate Information: 10623 S MAIN ST 1-3 90003
- Application / Permit
- 23010-10000-04592
- Plan Check / Job No.
- B23LA21645
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- eplan. New 2-Story Duplex with Attached Garage and ADU per LAMC 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 6/5/2024
- Issuing Office
- Current Status
- CofO Issued on 5/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/16/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/30/2023 | GEORGE JOLAKIAN |
| Corrections Issued | 12/7/2023 | GEORGE JOLAKIAN |
| Quality Review Completed | 12/21/2023 | RODOLFO ARIAS |
| Plan Check Approved | 6/5/2024 | GEORGE JOLAKIAN |
| Issued | 6/5/2024 | APPLICANT |
| CofO in Progress | 5/6/2025 | BEN MOLSTAD |
| Permit Finaled | 5/12/2025 | RICHARD STEINBACH |
| CofO Issued | 5/12/2025 | RICHARD STEINBACH |
| Permit Finaled | 5/12/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 1/13/2024 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 1/24/2024 | ARNULFO CHAMU |
| Low Impact Development (LID) | Cleared | 2/27/2024 | ROGELIO CORTES |
| Hydrant and Access approval | Cleared | 3/1/2024 | MATTHEW CRAIG |
| Roof/Waste drainage to street | Cleared | 3/4/2024 | TREVOR QUAN |
| Community Plan Implem. Overlay | Cleared | 3/11/2024 | WALLIE JONG |
| Highway dedication | Cleared | 3/11/2024 | WALLIE JONG |
| Sewer availability | Cleared | 3/12/2024 | CELINA MORENO |
| Community Plan Implem. Overlay | Cleared | 3/13/2024 | DYNL MIRANDA |
| Community Plan Implem. Overlay | Cleared | 3/21/2024 | SEGAL ISMAEL |
| Community Plan Implem. Overlay | Cleared | 3/29/2024 | RIDWAN HARDY |
| Construction near power lines | Cleared | 3/29/2024 | RIDWAN HARDY |
| Community Plan Implem. Overlay | Cleared | 4/3/2024 | ANACANY HURTADO |
Contact Information
| Contractor | Total Property Services; Lic. No.: 732965-B | , |
| Engineer | Stewart,, Carl; Lic. No.: C86681 | 8811 GENTLE WIND DR CORONA, CA 92883 |
| Engineer | Stewart,, Carl; Lic. No.: NA86681 | , |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/25/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| PLUMBING-Rough | 6/25/2024 | Partial Approval | JAMES CHAVEZ |
| Pre-Inspection | 6/25/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| Excavation/Setback/Form/Re-Bar | 7/8/2024 | Corrections Issued | BEN MOLSTAD |
| Footing/Foundation/Slab | 7/8/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Excavation/Setback/Form/Re-Bar | 7/10/2024 | Approved | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 7/30/2024 | Partial Approval | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 9/9/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Deputy Wood Construction | 9/9/2024 | Conditional Approval | BEN MOLSTAD |
| Green Building Rough | 9/9/2024 | Not Ready for Inspection | BEN MOLSTAD |
| PLUMBING-Rough | 9/9/2024 | Corrections Issued | BEN MOLSTAD |
| Verify Sprinkler Sign Off | 9/9/2024 | Not Ready for Inspection | BEN MOLSTAD |
| BUILDING-Rough-Frame | 9/16/2024 | Not Ready for Inspection | BARRY HACHE |
| Green Building Rough | 9/16/2024 | Not Ready for Inspection | BARRY HACHE |
| Rough-Elec/Plmb/HVAC | 9/16/2024 | Not Ready for Inspection | BARRY HACHE |
| Verify Sprinkler Sign Off | 9/16/2024 | Not Ready for Inspection | BARRY HACHE |
| ELECTRICAL-Rough | 9/17/2024 | Corrections Issued | BARRY HACHE |
| Rough-Elec/Plmb/HVAC | 9/17/2024 | Approved | BARRY HACHE |
| BUILDING-Rough-Frame | 9/20/2024 | Approved | BEN MOLSTAD |
| Green Building Rough | 9/20/2024 | Approved | BEN MOLSTAD |
| Rough-Elec/Plmb/HVAC | 9/20/2024 | Approved | BEN MOLSTAD |
| Verify Sprinkler Sign Off | 9/20/2024 | Approved | BEN MOLSTAD |
| ELECTRICAL-Rough | 9/27/2024 | Approved | BEN MOLSTAD |
| Pre-Inspection | 9/27/2024 | Approved | BEN MOLSTAD |
| Insulation | 10/1/2024 | Approved | BEN MOLSTAD |
| Drywall Nailing | 10/10/2024 | Approved | BEN MOLSTAD |
| Interior/Exterior Lathing | 10/10/2024 | Approved | BEN MOLSTAD |
| PLUMBING-Rough | 11/19/2024 | Partial Approval | ANTHONY EGSON |
| Underground Mechanical | 11/19/2024 | Partial Approval | ANTHONY EGSON |
| Sewer | 12/2/2024 | Approved | BEN MOLSTAD |
| Service/Power Release | 12/6/2024 | Not Ready for Inspection | BEN MOLSTAD |
| HVAC-Final | 12/18/2024 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Final | 12/18/2024 | Corrections Issued | ANTHONY EGSON |
| HVAC-Final | 12/27/2024 | Approved | JOSEPH MCGARRY |
| PLUMBING-Final | 12/27/2024 | Not Ready for Inspection | JOSEPH MCGARRY |
| ELECTRICAL-Final | 12/30/2024 | Approved | BEN MOLSTAD |
| Final | 12/30/2024 | Corrections Issued | BEN MOLSTAD |
| Footing/Foundation/Slab | 12/30/2024 | Approved | BEN MOLSTAD |
| Green Building Final | 12/30/2024 | Approved | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 12/30/2024 | SGSOV Not Required | BEN MOLSTAD |
| Service/Power Release | 12/30/2024 | Approved | BEN MOLSTAD |
| Smoke Detectors | 12/30/2024 | Approved | BEN MOLSTAD |
| Final | 5/6/2025 | OK to Issue CofO | BEN MOLSTAD |
| Service/Power Release | 5/8/2025 | Approved | BEN MOLSTAD |