13033 W ROSE AVE 90066
Certificate Information: 13033 W ROSE AVE 90066
- Application / Permit
- 23010-10000-04591
- Plan Check / Job No.
- B23LA21644
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan:NEW 2-STORY 2ND DWELLING UNIT WITH ATTACHED 1-CAR GARAGE AND ROOF DECK PER SB-9 Unit (two unit developement) - BLDG SPRINKLERED THRU-OUT
- Permit Issued
- Issued on 6/11/2024
- Issuing Office
- Current Status
- CofO Issued on 5/11/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/15/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/16/2023 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 11/22/2023 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 12/5/2023 | TU HUA |
| Applicant returned to address corrections | 4/11/2024 | ARSALAN SHABESTARI |
| Plan Check Approved | 5/16/2024 | MAHNAZ NOURHASHEMI |
| Issued | 6/11/2024 | APPLICANT |
| CofO in Progress | 5/7/2026 | DAKOTA LOW |
| Permit Finaled | 5/11/2026 | RICHARD STEINBACH |
| Permit Finaled | 5/11/2026 | RICHARD STEINBACH |
| CofO Issued | 5/11/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 11/19/2023 | MAHNAZ NOURHASHEMI |
| Grading Pre-Inspection | Cleared | 11/19/2023 | MAHNAZ NOURHASHEMI |
| Eng Process Fee Ord 176,300 | Cleared | 12/11/2023 | VLADIMIR ARUTYUNYAN |
| Sewer availability | Cleared | 12/11/2023 | VLADIMIR ARUTYUNYAN |
| Address approval | Cleared | 12/13/2023 | HISASHI KOBAYAKAWA |
| Senate Bill 9 | Cleared | 12/13/2023 | YINGSHI HUANG |
| Hydrant and Access approval | Cleared | 1/25/2024 | MATTHEW CRAIG |
| Specific Plan | Cleared | 3/13/2024 | FREDDY GARCIA |
| Low Impact Development (LID) | Cleared | 3/14/2024 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 3/15/2024 | VLADIMIR ARUTYUNYAN |
| Construction near power lines | Cleared | 4/27/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 4/27/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Canan Development Inc; Lic. No.: 891167-B | , |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/18/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| PLUMBING-Rough | 10/17/2024 | Corrections Issued | JESUS PINEDA |
| Footing/Foundation/Slab | 10/23/2024 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Rough | 10/23/2024 | Partial Approval | JESUS PINEDA |
| Footing/Foundation/Slab | 10/24/2024 | Approved | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2025 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 2/28/2025 | Not Ready for Inspection | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2025 | Approved | JESUS PINEDA |
| HVAC-Rough | 2/28/2025 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Rough | 2/28/2025 | Corrections Issued | JESUS PINEDA |
| Special/Order Compliance | 2/28/2025 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Rough | 3/7/2025 | Corrections Issued | JESUS PINEDA |
| HVAC-Rough | 3/7/2025 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 3/7/2025 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 3/11/2025 | Partial Approval | MICHAEL ALLEN |
| ELECTRICAL-Rough | 3/13/2025 | Partial Approval | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 3/19/2025 | Approved | BOBBY KEY |
| Verify Sprinkler Sign Off | 3/19/2025 | Approved | BOBBY KEY |
| Shower Pan | 3/24/2025 | Corrections Issued | MICHAEL ALLEN |
| Insulation | 3/27/2025 | Approved | MICHAEL ALLEN |
| Drywall Nailing | 4/4/2025 | Approved | JAYLIN GRAVITTE |
| Shower Pan | 4/4/2025 | Approved | JAYLIN GRAVITTE |
| ELECTRICAL-Final | 12/5/2025 | Corrections Issued | WILBER ROSALES |
| ELECTRICAL-Final | 12/16/2025 | Approved | WILBER ROSALES |
| Service/Power Release | 12/16/2025 | Approved | WILBER ROSALES |
| ELECTRICAL-Final | 3/2/2026 | Corrections Issued | DAKOTA LOW |
| HVAC-Final | 3/2/2026 | Corrections Issued | DAKOTA LOW |
| PLUMBING-Final | 3/2/2026 | Corrections Issued | DAKOTA LOW |
| Final | 3/11/2026 | Corrections Issued | DAKOTA LOW |
| HVAC-Final | 3/11/2026 | Corrections Issued | DAKOTA LOW |
| PLUMBING-Final | 3/11/2026 | Corrections Issued | DAKOTA LOW |
| HVAC-Final | 3/26/2026 | Approved | DAKOTA LOW |
| PLUMBING-Final | 3/26/2026 | Corrections Issued | DAKOTA LOW |
| SGSOV-Seismic Gas S/O Valve | 4/16/2026 | SGSOV Not Ready | DAKOTA LOW |
| Final | 4/28/2026 | Corrections Issued | RUBEN RIVAS |
| PLUMBING-Final | 4/28/2026 | Approved | RUBEN RIVAS |
| SGSOV-Seismic Gas S/O Valve | 4/28/2026 | SGSOV No Gas | RUBEN RIVAS |
| Final | 5/5/2026 | OK to Issue CofO | DAKOTA LOW |
| PLUMBING-Final | 5/5/2026 | Approved | DAKOTA LOW |
| Smoke Detectors | 5/5/2026 | Approved | DAKOTA LOW |