603-603 1/2 W 85TH ST 90044
Certificate Information: 603-603 1/2 W 85TH ST 90044
- Application / Permit
- 23010-10000-04590
- Plan Check / Job No.
- B23LA21643
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2-STORY DUPLEX & ATTACHED GARAGE
- Permit Issued
- Issued on 2/27/2024
- Issuing Office
- Current Status
- CofO Issued on 9/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/15/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/16/2023 | JOE VO |
| Corrections Issued | 11/19/2023 | JOE VO |
| Quality Review Completed | 11/22/2023 | GARO TELMI |
| Plan Check Approved | 2/13/2024 | JOE VO |
| Issued | 2/27/2024 | APPLICANT |
| CofO in Progress | 9/9/2024 | MICHAEL LEWIS |
| Permit Finaled | 9/17/2024 | DEROLD HAUFF |
| CofO Issued | 9/17/2024 | DEROLD HAUFF |
| Permit Finaled | 9/17/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/29/2023 | CHRISTINA BRACO |
| Highway dedication | Cleared | 11/29/2023 | CHRISTINA BRACO |
| Miscellaneous | Cleared | 11/29/2023 | CHRISTINA BRACO |
| Eng Process Fee Ord 176,300 | Cleared | 12/1/2023 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 12/1/2023 | ADRIAN SANCHEZ |
| Hydrant and Access approval | Cleared | 1/11/2024 | LAVEON RIDER |
| Low Impact Development (LID) | Cleared | 1/29/2024 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 2/1/2024 | CHRISTINA BRACO |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | , |
| Engineer | Madero,, Fidencio; Lic. No.: NA81695 | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/27/2024 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 3/27/2024 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 4/26/2024 | Approved | ALEJANDRO DE ARTOLA |
| Wood Frame | 4/26/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2024 | Partial Approval | JOSEPH MCGARRY |
| Insulation | 4/29/2024 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2024 | Partial Approval | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 6/26/2024 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 6/26/2024 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 6/27/2024 | Corrections Issued | MICHAEL LEWIS |
| ELECTRICAL-Rough | 6/27/2024 | Approved | MICHAEL LEWIS |
| Green Building Rough | 6/27/2024 | Approved | MICHAEL LEWIS |
| MERV13>=Rough | 6/27/2024 | Partial Approval | MICHAEL LEWIS |
| Verify Sprinkler Sign Off | 6/27/2024 | Approved | MICHAEL LEWIS |
| Insulation | 6/28/2024 | Approved | JOSH MEISTER |
| Drywall Nailing | 7/9/2024 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 7/9/2024 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Final | 8/27/2024 | Partial Approval | MICHAEL LEWIS |
| HVAC-Final | 9/5/2024 | Approved | MICHAEL LEWIS |
| PLUMBING-Final | 9/5/2024 | Approved | MICHAEL LEWIS |
| Service/Power Release | 9/5/2024 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 9/6/2024 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Final | 9/6/2024 | Approved | MICHAEL LEWIS |
| Final | 9/6/2024 | OK to Issue CofO | MICHAEL LEWIS |
| Green Building Final | 9/6/2024 | Approved | MICHAEL LEWIS |
| MERV13>=Final | 9/6/2024 | Approved | MICHAEL LEWIS |
| MERV13>=Rough | 9/6/2024 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 9/6/2024 | SGSOV Not Required | MICHAEL LEWIS |
| Service/Power Release | 9/6/2024 | Approved | MICHAEL LEWIS |
| Smoke Detectors | 9/6/2024 | Approved | MICHAEL LEWIS |