1140 S DACOTAH ST 90023

Certificate Information: 1140 S DACOTAH ST 90023

Application / Permit
23010-10000-04578
Plan Check / Job No.
B23LA21579
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: (N) 1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
Permit Issued
Issued on 10/9/2024
Issuing Office
Current Status
CofO Issued on 11/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/14/2023 APPLICANT
Assigned to Plan Check Engineer 11/30/2023 DANIEL YIP
Corrections Issued 12/4/2023 DANIEL YIP
Quality Review Completed 12/5/2023 GARO TELMI
Applicant returned to address corrections 4/2/2024 DANIEL YIP
Applicant returned to address corrections 9/5/2024 DANIEL YIP
Applicant returned to address corrections 9/17/2024 DANIEL YIP
Plan Check Approved 9/23/2024 DANIEL YIP
Issued 10/9/2024 APPLICANT
CofO in Progress 11/26/2025 FREDDIE RIVERA
Permit Finaled 11/29/2025 DEROLD HAUFF
CofO Issued 11/29/2025 DEROLD HAUFF
Permit Finaled 11/29/2025 DEROLD HAUFF

Permit Application Clearance Information

Clean Up Green Up Cleared 1/23/2024 DANIEL CORONADO
Address approval Cleared 1/24/2024 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 1/29/2024 JEANIE LAM
Sewer availability Cleared 1/29/2024 JEANIE LAM
Low Impact Development (LID) Cleared 8/15/2024 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 8/19/2024 JUSTIN BICOL
Zoning Information File Cleared 9/5/2024 DANIEL YIP
Zoning Information File Cleared 9/5/2024 DANIEL YIP

Contact Information

Contractor Owner-Builder       ,
Engineer Sarrami,, Gholamali F; Lic. No.: C43720 4942 HIGHLAND VIEW AVENUE      LOS ANGELES, CA 90041

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/18/2025 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 2/18/2025 Partial Inspection FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 3/17/2025 Corrections Issued FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 3/18/2025 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 4/7/2025 Partial Approval FREDDIE RIVERA
PLUMBING-Rough 4/7/2025 Partial Approval FREDDIE RIVERA
Underground Mechanical 4/7/2025 Partial Inspection FREDDIE RIVERA
Sewer 4/16/2025 Approved ANTHONY RAMOS
Underground Mechanical 4/16/2025 Approved ANTHONY RAMOS
BUILDING-Rough-Frame 5/12/2025 Partial Inspection FREDDIE RIVERA
ELECTRICAL-Rough 5/12/2025 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 5/12/2025 Approved FREDDIE RIVERA
Green Building Rough 5/12/2025 Partial Inspection FREDDIE RIVERA
HVAC-Rough 5/12/2025 Approved FREDDIE RIVERA
MERV13>=Rough 5/12/2025 Approved FREDDIE RIVERA
PLUMBING-Rough 5/12/2025 Approved FREDDIE RIVERA
Shower Pan 5/12/2025 Partial Inspection FREDDIE RIVERA
Verify Sprinkler Sign Off 5/12/2025 Partial Inspection FREDDIE RIVERA
Shower Pan 5/14/2025 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 5/21/2025 Approved ALEX COLIN
Green Building Rough 5/21/2025 Not Ready for Inspection ALEX COLIN
Insulation 5/21/2025 Approved ALEX COLIN
Drywall Nailing 5/28/2025 Approved ALEX COLIN
Green Building Rough 5/28/2025 Approved ALEX COLIN
ELECTRICAL-Final 9/25/2025 Corrections Issued ARTHUR NEGRETE
Final 9/25/2025 Not Ready for Inspection ARTHUR NEGRETE
Footing/Foundation/Slab 9/25/2025 Approved ARTHUR NEGRETE
Green Building Final 9/25/2025 Not Ready for Inspection ARTHUR NEGRETE
HVAC-Final 9/25/2025 Approved ARTHUR NEGRETE
MERV13>=Final 9/25/2025 Approved ARTHUR NEGRETE
PLUMBING-Final 9/25/2025 Approved ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 9/25/2025 SGSOV Approved ARTHUR NEGRETE
Service/Power Release 9/25/2025 Not Ready for Inspection ARTHUR NEGRETE
Smoke Detectors 9/25/2025 Approved ARTHUR NEGRETE
ELECTRICAL-Final 10/20/2025 Approved FREDDIE RIVERA
Final 10/29/2025 Partial Inspection FREDDIE RIVERA
Green Building Final 10/29/2025 Corrections Issued FREDDIE RIVERA
Service/Power Release 10/29/2025 Partial Inspection FREDDIE RIVERA
Final 11/17/2025 Partial Inspection FREDDIE RIVERA
Green Building Final 11/17/2025 Approved FREDDIE RIVERA
Service/Power Release 11/17/2025 Approved FREDDIE RIVERA
Final 11/26/2025 OK to Issue CofO FREDDIE RIVERA