9988 W LIEBE DR 90210

Certificate Information: 9988 W LIEBE DR 90210

Application / Permit
23010-10000-04548
Plan Check / Job No.
B23LA21482
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Accessory Living Quarters
Work Description
ePlan: (N) 2-STORY ACCESSORY LIVING QUARTER W/ NFPA-13D FIRE SPRINKLER THROUGHOUT.
Permit Issued
Issued on 6/11/2024
Issuing Office
Current Status
CofO Issued on 5/6/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/13/2023 APPLICANT
Assigned to Plan Check Engineer 11/16/2023 DANIEL YIP
Corrections Issued 11/18/2023 DANIEL YIP
Quality Review Completed 11/28/2023 PRANITA SHAH
Applicant returned to address corrections 3/7/2024 DANIEL YIP
Applicant returned to address corrections 3/21/2024 DANIEL YIP
Applicant returned to address corrections 4/2/2024 DANIEL YIP
Applicant returned to address corrections 4/23/2024 DANIEL YIP
Plan Check Approved 6/11/2024 DANIEL YIP
Issued 6/11/2024 APPLICANT
CofO in Progress 5/5/2026 CARLOS MATAMOROS
Permit Finaled 5/6/2026 RICHARD STEINBACH
CofO Issued 5/6/2026 RICHARD STEINBACH
Permit Finaled 5/6/2026 RICHARD STEINBACH

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 12/7/2023 LIAM ODONOVAN
BHO/Hillside ordinance Cleared 12/7/2023 LIAM ODONOVAN
BHO/Hillside ordinance Cleared 12/7/2023 LIAM ODONOVAN
BHO/Hillside ordinance Cleared 12/7/2023 LIAM ODONOVAN
BHO/Hillside ordinance Cleared 12/7/2023 LIAM ODONOVAN
Eng Process Fee Ord 176,300 Cleared 12/19/2023 LIAM ODONOVAN
Sewer availability Cleared 12/19/2023 LIAM ODONOVAN
Hydrant and Access approval Cleared 1/18/2024 LAVEON RIDER
Low Impact Development (LID) Cleared 4/4/2024 SAMUEL LINN
Roof/Waste drainage to street Cleared 4/7/2024 BRENDEN HAWK
Excavation more than 5-ft deep Cleared 6/7/2024 CALOSHA APPROVED
GPI Written Notices Cleared 6/7/2024 DANIEL YIP
Grading Pre-Inspection Cleared 6/7/2024 DANIEL YIP

Contact Information

Contractor Owner-Builder       ,
Engineer De, Leon, Cynthia Aguilar; Lic. No.: C31604 8061 SAN MATEO CIR      BUENA PARK, CA 90620
Engineer Phillips,, Craig; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026

Inspector Information

CARLOS MATAMOROS, (310) 914-3878 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 9/20/2024 Partial Approval SEAN HAUPT
Deputy Reinf. Concrete 9/24/2024 Partial Approval SEAN HAUPT
Excavation/Setback/Form/Re-Bar 10/3/2024 Partial Approval SEAN HAUPT
Excavation/Setback/Form/Re-Bar 10/8/2024 Partial Approval SEAN HAUPT
Excavation/Setback/Form/Re-Bar 10/15/2024 Partial Approval SEAN HAUPT
Special/Order Compliance 10/15/2024 Approved SEAN HAUPT
Excavation/Setback/Form/Re-Bar 10/22/2024 Partial Approval SEAN HAUPT
Footing/Foundation/Slab 10/24/2024 Not Ready for Inspection SEAN HAUPT
Piling/Pier/Caisson 11/4/2024 Partial Approval SEAN HAUPT
Deputy Reinf. Concrete 11/6/2024 Conditional Approval MICHAEL PELHAM
Deputy Drilled-In Anchors 11/15/2024 Partial Approval SEAN HAUPT
Footing/Foundation/Slab 11/15/2024 Partial Approval SEAN HAUPT
Deputy Reinf. Concrete 11/18/2024 Partial Approval SEAN HAUPT
Excavation/Setback/Form/Re-Bar 11/22/2024 Partial Approval SEAN HAUPT
PLUMBING-Rough 12/2/2024 Partial Approval SEAN HAUPT
Excavation/Setback/Form/Re-Bar 12/18/2024 Partial Approval SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 1/13/2025 Partial Approval SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 2/11/2025 Partial Approval SEAN HAUPT
Green Building Rough 2/11/2025 Not Ready for Inspection SEAN HAUPT
Verify Sprinkler Sign Off 2/11/2025 Not Ready for Inspection SEAN HAUPT
Excavation/Setback/Form/Re-Bar 3/4/2025 Approved SEAN HAUPT
Footing/Foundation/Slab 3/4/2025 Approved SEAN HAUPT
Deputy Reinf. Concrete 3/5/2025 Conditional Approval MICHAEL PELHAM
BUILDING-Rough-Frame 4/16/2025 Corrections Issued SEAN HAUPT
ELECTRICAL-Rough 4/16/2025 Approved SEAN HAUPT
Green Building Rough 4/16/2025 Corrections Issued SEAN HAUPT
HVAC-Rough 4/16/2025 Approved SEAN HAUPT
PLUMBING-Rough 4/16/2025 Approved SEAN HAUPT
Verify Sprinkler Sign Off 4/16/2025 Not Ready for Inspection SEAN HAUPT
BUILDING-Rough-Frame 5/20/2025 Approved SEAN HAUPT
Green Building Rough 5/20/2025 Approved SEAN HAUPT
Interior/Exterior Lathing 5/20/2025 Partial Approval SEAN HAUPT
Shower Pan 5/20/2025 Approved SEAN HAUPT
Verify Sprinkler Sign Off 5/20/2025 Approved SEAN HAUPT
Interior/Exterior Lathing 5/23/2025 Approved SEAN HAUPT
Insulation 5/28/2025 Approved SEAN HAUPT
Drywall Nailing 6/5/2025 Approved SEAN HAUPT
PLUMBING-Rough 10/24/2025 Corrections Issued SEAN HAUPT
Sewer 10/24/2025 Partial Approval SEAN HAUPT
PLUMBING-Rough 10/28/2025 Partial Approval SEAN HAUPT
ELECTRICAL-Rough 10/29/2025 Partial Approval SEAN HAUPT
ELECTRICAL-Final 3/6/2026 Approved CARLOS MATAMOROS
PLUMBING-Final 3/6/2026 Approved CARLOS MATAMOROS
Final 4/8/2026 Corrections Issued CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 4/8/2026 SGSOV Not Ready CARLOS MATAMOROS
Final 4/27/2026 Corrections Issued CARLOS MATAMOROS
Green Building Final 4/27/2026 Approved CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 4/27/2026 SGSOV Not Ready CARLOS MATAMOROS
Service/Power Release 4/27/2026 Approved CARLOS MATAMOROS
Smoke Detectors 4/27/2026 Approved CARLOS MATAMOROS
Final 5/5/2026 OK to Issue CofO CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 5/5/2026 SGSOV Approved CARLOS MATAMOROS