16136 W DEVONSHIRE ST 1-15 91344
Certificate Information: 16136 W DEVONSHIRE ST 1-15 91344
- Application / Permit
- 23010-10000-04533
- Plan Check / Job No.
- B23LA21433
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- ePlan - NEW 3 STORY 14 UNITS + 1 ADU 100% AFFORDABLE HOUSING APARTMENT PER 12.22 A25 AND ADM-2023-8062-DB-VHCA-ED1
- Permit Issued
- Issued on 12/6/2024
- Issuing Office
- Current Status
- CofO Issued on 11/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/15/2023 | APPLICANT |
| Assigned to Zoning Architect | 11/17/2023 | CALEB WONG |
| Assigned to Plan Check Engineer | 11/21/2023 | VU NGUYEN |
| Corrections Issued | 11/28/2023 | VU NGUYEN |
| Quality Review Completed | 11/29/2023 | EUGENE BARBEAU |
| Plan Check Approved | 12/4/2024 | STARR CHEN |
| Issued | 12/6/2024 | APPLICANT |
| Permit Closed-Status Void | 3/28/2025 | ROBERT DAVIS |
| Re-Activate Permit | 4/3/2025 | ROBERT DAVIS |
| CofO in Progress | 10/24/2025 | JOHN KITCKO |
| Permit Finaled | 11/4/2025 | RICKEY JACKSON |
| CofO Issued | 11/4/2025 | RICKEY JACKSON |
| Permit Finaled | 11/4/2025 | RICKEY JACKSON |
Permit Application Clearance Information
| Address approval | Cleared | 1/24/2024 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/25/2024 | CARLOS RAMIREZ |
| Highway dedication | Cleared | 2/12/2024 | CARLOS RAMIREZ |
| Hydrant and Access approval | Cleared | 4/8/2024 | LAVEON RIDER |
| Trees in Parkway | Cleared | 4/10/2024 | ADALBERTO VERA |
| Permit | Cleared | 4/24/2024 | CARLOS RAMIREZ |
| Green Code | Cleared | 5/23/2024 | AARON COSTA |
| Building over 36-ft | Cleared | 5/24/2024 | CALOSHA APPROVED |
| Miscellaneous | Cleared | 6/3/2024 | ROSALINDA MEZA |
| Miscellaneous | Cleared | 6/3/2024 | ROSALINDA MEZA |
| Opn space landscape/Water mgmt | Cleared | 6/3/2024 | ROSALINDA MEZA |
| Low Impact Development (LID) | Cleared | 6/9/2024 | MARTIN FRAGOSO |
| Fire Marshal Fire Life Safety | Cleared | 6/13/2024 | FIRE DEPARTMENT |
| DAS Clearance | Cleared | 6/19/2024 | VU NGUYEN |
| Construction near power lines | Cleared | 6/26/2024 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 7/17/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 10/24/2024 | MARKOS PEREZ-BRAN |
| Density Bonus | Cleared | 11/5/2024 | LOUIE MILLER |
| Density Bonus | Cleared | 11/5/2024 | LOUIE MILLER |
| Density Bonus | Cleared | 11/5/2024 | LOUIE MILLER |
| Density Bonus | Cleared | 11/5/2024 | LOUIE MILLER |
| SB8 RUD | Cleared | 11/5/2024 | LOUIE MILLER |
| Miscellaneous | Cleared | 11/13/2024 | DANIEL CORONADO |
| Miscellaneous | Cleared | 11/13/2024 | DANIEL CORONADO |
| Miscellaneous | Cleared | 11/13/2024 | DANIEL CORONADO |
| Miscellaneous | Cleared | 11/13/2024 | DANIEL CORONADO |
| Miscellaneous | Cleared | 11/13/2024 | DANIEL CORONADO |
| Frnt yard landscape/Water mgmt | Cleared | 11/19/2024 | DANIEL CORONADO |
| Miscellaneous | Cleared | 11/19/2024 | DANIEL CORONADO |
| Zoning Plan Check | Cleared | 11/21/2024 | CALEB WONG |
Contact Information
| Architect | , ; Lic. No.: C34124 | 209 S MARKET STREET INGLEWOOD, CA 90301 |
| Contractor | Inhance Construction Inc; Lic. No.: 1073871-B | , |
| Engineer | Krief,, Dan D; Lic. No.: C76041 | 6420 WILSHIRE BLVD STE 1000 LOS ANGELES, CA 90048 |
| Engineer | Rybak,, Richard; Lic. No.: GE2131 | 20312 TAU PLACE CHATSWORTH, CA 91311 |
| Engineer | Soliven,, Sam Anunciacion; Lic. No.: L8269 | PO BOX 11034 BREA, CA 92822 |
| Engineer | Xia,, Ji; Lic. No.: S7144 | 260 S LOS ROBLES AVE, STE 100 PASADENA, CA 91101 |
Inspector Information
| GREGORY POMISH, (818) 374-3303 | Office Hours: 7:00-8:00 AM MON-FRI |
| EDWIN GREGORYONA, (818) 374-3303 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/9/2025 | Partial Inspection | GREGORY POMISH |
| Pre-Inspection | 1/9/2025 | Partial Inspection | GREGORY POMISH |
| Footing/Foundation/Slab | 1/21/2025 | Partial Approval | GREGORY POMISH |
| Deputy Wood Construction | 2/4/2025 | Conditional Approval | GREGORY POMISH |
| Floor/Roof Diaphrgm/Shear Wall | 2/5/2025 | Partial Approval | GREGORY POMISH |
| Floor/Roof Diaphrgm/Shear Wall | 2/21/2025 | Partial Approval | GREGORY POMISH |
| Deputy Wood Construction | 2/24/2025 | Partial Approval | GREGORY POMISH |
| Floor/Roof Diaphrgm/Shear Wall | 2/25/2025 | Partial Inspection | DANNY RODRIGUEZ |
| Deputy Wood Construction | 2/28/2025 | Approved | JOHN KITCKO |
| Drywall Nailing | 2/28/2025 | Not Ready for Inspection | JOHN KITCKO |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2025 | Partial Approval | JOHN KITCKO |
| Insulation | 2/28/2025 | Partial Approval | JOHN KITCKO |
| Special/Order Compliance | 2/28/2025 | Partial Inspection | JOHN KITCKO |
| Drywall Nailing | 3/4/2025 | Partial Approval | GREGORY POMISH |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2025 | Partial Inspection | GREGORY POMISH |
| Insulation | 3/4/2025 | Partial Approval | GREGORY POMISH |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2025 | Not Ready for Inspection | GREGORY POMISH |
| Deputy Wood Construction | 3/12/2025 | Conditional Approval | GREGORY POMISH |
| Floor/Roof Diaphrgm/Shear Wall | 3/12/2025 | Partial Approval | GREGORY POMISH |
| Insulation | 3/14/2025 | Partial Approval | GREGORY POMISH |
| Drywall Nailing | 3/19/2025 | Partial Approval | GREGORY POMISH |
| Deputy Wood Construction | 3/20/2025 | Conditional Approval | GREGORY POMISH |
| Insulation | 3/21/2025 | Partial Approval | GREGORY POMISH |
| Drywall Nailing | 3/28/2025 | Partial Approval | ROBERT DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 3/28/2025 | Partial Approval | ROBERT DAVIS |
| Wall Anchors | 3/28/2025 | Partial Approval | ROBERT DAVIS |
| Green Building Rough | 4/8/2025 | Partial Inspection | GREGORY POMISH |
| Verify Sprinkler Sign Off | 4/8/2025 | Partial Inspection | GREGORY POMISH |
| Wood Frame | 4/8/2025 | Partial Approval | GREGORY POMISH |
| Insulation | 4/11/2025 | Partial Approval | GREGORY POMISH |
| Insulation | 4/15/2025 | Partial Approval | GREGORY POMISH |
| Insulation | 4/21/2025 | Not Ready for Inspection | JEFFREY DURAN |
| Insulation | 4/22/2025 | Partial Approval | GREGORY POMISH |
| Green Building Rough | 4/25/2025 | Not Ready for Inspection | GREGORY POMISH |
| Verify Sprinkler Sign Off | 4/25/2025 | Partial Inspection | GREGORY POMISH |
| Wood Frame | 4/25/2025 | Partial Approval | GREGORY POMISH |
| Drywall Nailing | 4/28/2025 | Partial Approval | DANNY RODRIGUEZ |
| Insulation | 4/30/2025 | Partial Approval | GREGORY POMISH |
| Green Building Rough | 5/6/2025 | Partial Inspection | GREGORY POMISH |
| Verify Sprinkler Sign Off | 5/6/2025 | Partial Inspection | GREGORY POMISH |
| Wood Frame | 5/6/2025 | Partial Approval | GREGORY POMISH |
| Drywall Nailing | 5/9/2025 | Partial Approval | GREGORY POMISH |
| Insulation | 5/9/2025 | Partial Approval | GREGORY POMISH |
| Interior/Exterior Lathing | 5/14/2025 | Partial Approval | GREGORY POMISH |
| Green Building Rough | 5/16/2025 | Partial Inspection | GREGORY POMISH |
| Verify Sprinkler Sign Off | 5/16/2025 | Partial Inspection | GREGORY POMISH |
| Wood Frame | 5/16/2025 | Partial Approval | GREGORY POMISH |
| Drywall Nailing | 5/19/2025 | Partial Approval | GREGORY POMISH |
| Insulation | 5/20/2025 | Partial Approval | GREGORY POMISH |
| Drywall Nailing | 5/28/2025 | Partial Approval | GREGORY POMISH |
| Drywall Nailing | 6/3/2025 | Approved | GREGORY POMISH |
| Reinforced Concrete Frame | 6/20/2025 | Partial Approval | ROBERT DAVIS |
| Final | 10/20/2025 | OK to Issue CofO | GREGORY POMISH |
| Footing/Foundation/Slab | 10/20/2025 | Approved | GREGORY POMISH |
| Green Building Final | 10/20/2025 | Approved | GREGORY POMISH |
| Green Building Rough | 10/20/2025 | Approved | GREGORY POMISH |
| SGSOV-Seismic Gas S/O Valve | 10/20/2025 | SGSOV Approved | GREGORY POMISH |
| Smoke Detectors | 10/20/2025 | Approved | GREGORY POMISH |
| Verify Sprinkler Sign Off | 10/20/2025 | Approved | GREGORY POMISH |
| Wood Frame | 10/20/2025 | Approved | GREGORY POMISH |