3717 1/2-1/4 W 23RD ST 90018
Certificate Information: 3717 1/2-1/4 W 23RD ST 90018
- Application / Permit
- 23010-10000-04530
- Plan Check / Job No.
- B23LA21406
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: (N) 2-STORY 2-UNIT ACCESSORY DWELLING UNIT CA Govt. Code 65852.2(e)(1)(D) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 3/7/2024
- Issuing Office
- Current Status
- CofO Issued on 2/7/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/13/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2023 | DANIEL YIP |
| Corrections Issued | 11/25/2023 | DANIEL YIP |
| Quality Review Completed | 11/30/2023 | GARO TELMI |
| Applicant returned to address corrections | 12/15/2023 | DANIEL YIP |
| Applicant returned to address corrections | 2/14/2024 | DANIEL YIP |
| Plan Check Approved | 2/29/2024 | DANIEL YIP |
| Issued | 3/7/2024 | APPLICANT |
| CofO in Progress | 2/5/2026 | JUSTIN HAWLEY |
| Permit Finaled | 2/7/2026 | DEROLD HAUFF |
| CofO Issued | 2/7/2026 | DEROLD HAUFF |
| Permit Finaled | 2/7/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/4/2023 | ANTHONY TRAN |
| Low Impact Development (LID) | Cleared | 12/6/2023 | MELINEH AGHAKHABIAN |
| Eng Process Fee Ord 176,300 | Cleared | 12/18/2023 | ANTHONY TRAN |
| Roof/Waste drainage to street | Cleared | 12/18/2023 | ANTHONY TRAN |
| Sewer availability | Cleared | 12/18/2023 | ANTHONY TRAN |
| Community Plan Implem. Overlay | Cleared | 1/17/2024 | ISAIAH ROSS |
| Construction near power lines | Cleared | 1/31/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Jarh Builders Corporation; Lic. No.: 1074687-B | 15740 PARAMOUNT BLVD #E PARAMOUNT, CA 90723 |
| Engineer | Medina,, Ferdinand Casaclang; Lic. No.: C88007 | 1051 S HOLT AVE APT F LOS ANGELES, CA 90035 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 8/7/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| METHANE-Barrier | 8/8/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| METHANE-Subgrade | 8/8/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Underground Mechanical | 8/8/2024 | Partial Approval | JUSTIN HAWLEY |
| Excavation/Setback/Form/Re-Bar | 8/12/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| METHANE-Barrier | 8/12/2024 | Approved | JUSTIN HAWLEY |
| METHANE-Subgrade | 8/12/2024 | Approved | JUSTIN HAWLEY |
| Excavation/Setback/Form/Re-Bar | 8/15/2024 | Corrections Issued | JUSTIN HAWLEY |
| Excavation/Setback/Form/Re-Bar | 8/19/2024 | Approved | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 8/19/2024 | Approved | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2024 | Partial Approval | JUSTIN HAWLEY |
| Deputy Wood Construction | 8/27/2024 | Conditional Approval | JUSTIN HAWLEY |
| Deputy Wood Construction | 9/24/2024 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Rough | 9/24/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2024 | Approved | JUSTIN HAWLEY |
| PLUMBING-Rough | 9/24/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| ELECTRICAL-Rough | 9/27/2024 | Approved | JUSTIN HAWLEY |
| HVAC-Rough | 9/27/2024 | Approved | JUSTIN HAWLEY |
| PLUMBING-Rough | 9/27/2024 | Approved | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 10/4/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Green Building Rough | 10/4/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| MERV13>=Rough | 10/4/2024 | Approved | JUSTIN HAWLEY |
| METHANE-Rough | 10/4/2024 | Approved | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 10/11/2024 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 10/15/2024 | Approved | JUSTIN HAWLEY |
| Insulation | 10/15/2024 | Conditional Approval | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 10/15/2024 | Partial Approval | JUSTIN HAWLEY |
| Drywall Nailing | 11/4/2024 | Approved | JUSTIN HAWLEY |
| Insulation | 11/4/2024 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 11/4/2024 | Approved | JUSTIN HAWLEY |
| Underground Mechanical | 11/19/2024 | Approved | JOSE MACIAS |
| ELECTRICAL-Final | 9/19/2025 | Approved | JUSTIN HAWLEY |
| Final | 9/19/2025 | Corrections Issued | JUSTIN HAWLEY |
| Green Building Final | 9/19/2025 | Approved | JUSTIN HAWLEY |
| HVAC-Final | 9/19/2025 | Not Ready for Inspection | JUSTIN HAWLEY |
| MERV13>=Final | 9/19/2025 | Approved | JUSTIN HAWLEY |
| PLUMBING-Final | 9/19/2025 | Approved | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 9/19/2025 | SGSOV Approved | JUSTIN HAWLEY |
| Service/Power Release | 9/19/2025 | Not Ready for Inspection | JUSTIN HAWLEY |
| Smoke Detectors | 9/19/2025 | Approved | JUSTIN HAWLEY |
| Final | 2/5/2026 | OK to Issue CofO | JUSTIN HAWLEY |
| HVAC-Final | 2/5/2026 | Approved | JUSTIN HAWLEY |
| Service/Power Release | 2/5/2026 | Approved | JUSTIN HAWLEY |